Detail Letting Schedule for Wood County (FY 2018)
Wood County (FY 2018) |
CCSJ: 0096-02-049 |
|||
District: | TYLER | Let Date: | Oct 2017 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | STP 2018(196)HES | CSJ: | 0096-02-049 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 2659/CR 3780 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $35,127 |
Length: | 0.2 | Actual | $26,845 |
District: | TYLER | Let Date: | Oct 2017 |
Highway: | US 69 | Let Status: | Actual |
Project ID: | STP 2018(197)HES | CSJ: | 0191-02-065 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 855 | Fund Cat: | 8 |
Limits To: | IN MT SELMAN | ESTIMATE: | $29,660 |
Length: | 0.2 | Actual | $23,875 |
District: | TYLER | Let Date: | Oct 2017 |
Highway: | FM 2767 | Let Status: | Actual |
Project ID: | STP 2018(199)HES | CSJ: | 0424-07-016 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 757 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $29,746 |
Length: | 0.2 | Actual | $23,853 |
District: | TYLER | Let Date: | Oct 2017 |
Highway: | FM 14 | Let Status: | Actual |
Project ID: | STP 2018(198)HES | CSJ: | 0492-01-046 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 2710 | Fund Cat: | 8 |
Limits To: | N OF RED SPRINGS | ESTIMATE: | $32,640 |
Length: | 0.2 | Actual | $25,768 |
District: | TYLER | Let Date: | Oct 2017 |
Highway: | FM 1616 | Let Status: | Actual |
Project ID: | STP 2018(200)HES | CSJ: | 1099-03-014 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 2752 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $34,129 |
Length: | 0.2 | Actual | $27,095 |
District: | TYLER | Let Date: | Oct 2017 |
Highway: | FM 177 | Let Status: | Actual |
Project ID: | STP 2018(195)HES | CSJ: | 1161-03-006 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: | |
Limits From: | AT FM 3052 | Fund Cat: | 8 |
Limits To: | IN MIXON | ESTIMATE: | $41,269 |
Length: | 0.2 | Actual | $32,570 |
List Showing Order Bid List Proposal Request Addenda Bid Tabulations Award Status Back... | Totals for 0096-02-049 | ||
---|---|---|---|
Length: | 1.2 | ||
Estimate: | $202,570 | ||
Actual: | $160,005 | ||
CCSJ: 0910-35-035 |
|||
District: | TYLER | Let Date: | May 2018 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2017(226)TAPS | CSJ: | 0910-35-035 |
Description: | W COKE RD PEDESTRIAN SAFE RT & WINNSBORO ELEMENTARY SRTS | Handling Code: | LC |
Limits From: | ALONG FM 515 (W COKE) FROM SIMONS,E | Fund Cat: | 3 |
Limits To: | SH 37/S MAIN IN WINNSBORO | ESTIMATE: | $870,751 |
Length: | 0.6 | Actual | $446,289 |
Back... | Totals for 0910-35-035 | ||
Length: | 0.6 | ||
Estimate: | $870,751 | ||
Actual: | $446,289 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |