The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Atascosa County (FY 2019)

CCSJ: 0017-04-042

District:SAN ANTONIOLet Date:Mar 2019
Highway:IH 35Let Status:Actual
Project ID:NH 2019(646)CSJ:0017-04-042
Description:BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ONHandling
Code:
 
Limits From:ATASCOSA/BEXAR COUNTY LINEFund Cat:1
Limits To:ATASCOSA/MEDINA COUNTY LINEESTIMATE:$3,295,353
Length:2.5Actual$3,383,807
 
District:SAN ANTONIOLet Date:Mar 2019
Highway:IH 35Let Status:Actual
Project ID:NH 2019(646)CSJ:0017-05-094
Description:BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ONHandling
Code:
 
Limits From:FRIO/MEDINA COUNTY LINEFund Cat:1
Limits To:MEDINA/ATASCOSA COUNTY LINEESTIMATE:$11,023,614
Length:12.7Actual$9,526,910
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0017-04-042
Length:15.2
Estimate:$14,318,967
Actual:$12,910,717

CCSJ: 0017-13-010

District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 132Let Status:Actual
Project ID:STP 2019(044)HESCSJ:0017-13-010
Description:IMPROVE TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT SOMERSET STREETFund Cat:8
Limits To:.ESTIMATE:$159,823
Length:0.2Actual$141,038
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:US 90Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0024-06-062
Description:INSTALL FLASHING BEACON AND SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT CR 482 (BIPPERT LN)Fund Cat:8
Limits To:.ESTIMATE:$59,544
Length:0.2Actual$55,314
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:US 90Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0024-06-063
Description:INSTALL FLASHING BEACON & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT CR 485Fund Cat:8
Limits To:.ESTIMATE:$73,619
Length:0.1Actual$68,566
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SL 345Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0072-08-140
Description:IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT CINNAMON CREEK DRFund Cat:8
Limits To:.ESTIMATE:$296,786
Length:0.2Actual$285,498
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 27Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0142-04-048
Description:IMPROVE TRAFFIC SIGNALSHandling
Code:
 
Limits From:AT FM 394Fund Cat:8
Limits To:.ESTIMATE:$188,799
Length:0.2Actual$170,638
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 27Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0142-04-049
Description:IMPROVE TRAFFIC SIGNALSHandling
Code:
 
Limits From:AT METHODIST ENCAMPMENT ROADFund Cat:8
Limits To:.ESTIMATE:$211,796
Length:0.2Actual$209,403
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 27Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0142-04-050
Description:IMPROVE TRAFFIC SIGNALSHandling
Code:
 
Limits From:AT RM 783Fund Cat:8
Limits To:.ESTIMATE:$232,794
Length:0.2Actual$218,265
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 117Let Status:Actual
Project ID:STP 2019(044)HESCSJ:0236-04-025
Description:INSTALL INTERSECTION FLASHING BEACON, ADVANCE WARNINGHandling
Code:
 
Limits From:AT FM 1581Fund Cat:8
Limits To:.ESTIMATE:$85,851
Length:0.2Actual$74,428
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 16Let Status:Actual
Project ID:STP 2019(044)HESCSJ:0291-03-070
Description:INSTALL TRAFFIC SIGNAL, INSTALL ADVANCE WARNING SIGNALS ANDHandling
Code:
 
Limits From:AT LA CASA DRFund Cat:8
Limits To:.ESTIMATE:$246,454
Length:0.2Actual$230,277
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 16Let Status:Actual
Project ID:STP 2019(044)HESCSJ:0291-10-104
Description:IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT GILBEAU RDFund Cat:8
Limits To:.ESTIMATE:$281,947
Length:0.2Actual$254,615
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 16Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0291-10-105
Description:IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT TEZEL RDFund Cat:8
Limits To:.ESTIMATE:$303,710
Length:0.2Actual$282,584
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 16Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0291-10-106
Description:IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT MAINLAND DRFund Cat:8
Limits To:.ESTIMATE:$332,561
Length:0.2Actual$323,147
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SH 16Let Status:Actual
Project ID:STP 2019(044)HESCSJ:0613-02-061
Description:INSTALL FLASHING BEACON & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT VIEWPOINTFund Cat:8
Limits To:.ESTIMATE:$59,898
Length:0.2Actual$55,654
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 471Let Status:Actual
Project ID:STP 2019(043)HESCSJ:0849-01-052
Description:IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT HEATH ROADFund Cat:1
Limits To:.ESTIMATE:$241,248
Length:0.2Actual$218,713
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 1341Let Status:Actual
Project ID:STP 2019(044)HESCSJ:1135-03-028
Description:IMPROVE TRAFFIC SIGNALSHandling
Code:
 
Limits From:AT SL 534Fund Cat:8
Limits To:.ESTIMATE:$195,536
Length:0.2Actual$188,329
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 1283Let Status:Actual
Project ID:STP 2019(044)HESCSJ:1730-01-042
Description:INSTALL FLASHING BEACON & SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT LAKEWOOD DRFund Cat:8
Limits To:.ESTIMATE:$58,682
Length:0.2Actual$53,886
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 1957Let Status:Actual
Project ID:STP 2019(043)HESCSJ:2104-02-034
Description:IMPROVE TRAFFIC SIGNALSHandling
Code:
 
Limits From:AT RICHLAND HILLSFund Cat:8
Limits To:.ESTIMATE:$317,233
Length:0.2Actual$320,879
 
District:SAN ANTONIOLet Date:Sep 2018
Highway:SL 534Let Status:Actual
Project ID:STP 2019(043)HESCSJ:3362-01-017
Description:INSTALL FLASHING BEACON AND SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:AT LEGION DRFund Cat:8
Limits To:.ESTIMATE:$61,687
Length:0.2Actual$56,456
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0017-13-010
Length:3.5
Estimate:$3,407,966
Actual:$3,207,690

CCSJ: 0748-05-040

District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 140Let Status:Actual
Project ID:STP 2019(110)CSJ:0748-05-040
Description:REHAB AND WIDEN NARROW ROADWAYHandling
Code:
 
Limits From:SH 16Fund Cat:1
Limits To:LA PARITA CREEKESTIMATE:$5,322,842
Length:3.5Actual$4,730,331
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0748-05-040
Length:3.5
Estimate:$5,322,842
Actual:$4,730,331

CCSJ: 0915-13-028

District:SAN ANTONIOLet Date:Mar 2019
Highway:CRLet Status:Actual
Project ID:BR 1702(572)CSJ:0915-13-028
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:ON CR 324 0.5 MI W OF SH 16Fund Cat:6
Limits To:AT GOOSE CREEKESTIMATE:$639,796
Length:0.0Actual$823,867
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0915-13-028
Length:0
Estimate:$639,796
Actual:$823,867

CCSJ: 0915-13-029

District:SAN ANTONIOLet Date:May 2019
Highway:CRLet Status:Actual
Project ID:BR 2019(907)CSJ:0915-13-029
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:CR 422 @ LA PARITA CREEKFund Cat:6
Limits To:.ESTIMATE:$486,586
Length:0.1Actual$619,854
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0915-13-029
Length:0.1
Estimate:$486,586
Actual:$619,854

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract