Detail Letting Schedule for Wood County (FY 2019)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Wood County (FY 2019) |
CCSJ: 0401-03-026 |
|||
District: | TYLER | Let Date: | Mar 2019 |
Highway: | SH 154 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 0401-03-026 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 1.458 MI E OF SH 37, QUITMAN CL,E | Fund Cat: | 8 |
Limits To: | UPSHUR C/L | ESTIMATE: | $307,765 |
Length: | 16.1 | Actual | $121,686 |
District: | TYLER | Let Date: | Mar 2019 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 0095-06-068 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 1.926 MI E OF SH 64-WILLS PT CL,E | Fund Cat: | 8 |
Limits To: | 0.470 MI W OF FM 1504/CR 3505 | ESTIMATE: | $76,701 |
Length: | 3.6 | Actual | $50,747 |
District: | TYLER | Let Date: | Mar 2019 |
Highway: | FM 312 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 0492-02-020 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 0.834 MI S OF FM 515, WNSBORO CL, S | Fund Cat: | 8 |
Limits To: | FM 2088 AT EAST POINT | ESTIMATE: | $136,963 |
Length: | 7.5 | Actual | $83,182 |
District: | TYLER | Let Date: | Mar 2019 |
Highway: | FM 515 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 0657-01-019 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 69(E) AT COKE, E | Fund Cat: | 8 |
Limits To: | 1.177 MI W OF SH 37-WNSBORO CL | ESTIMATE: | $129,017 |
Length: | 7.3 | Actual | $78,008 |
District: | TYLER | Let Date: | Mar 2019 |
Highway: | FM 751 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 1089-01-022 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | HUNT C/L, S | Fund Cat: | 8 |
Limits To: | 0.981 MI NW OF FM 47, WILLS PT CL | ESTIMATE: | $141,737 |
Length: | 8.5 | Actual | $89,482 |
District: | TYLER | Let Date: | Mar 2019 |
Highway: | FM 2869 | Let Status: | Actual |
Project ID: | STP 2019(620)HES | CSJ: | 2918-01-012 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 14, SW | Fund Cat: | 8 |
Limits To: | US 80 | ESTIMATE: | $104,969 |
Length: | 5.4 | Actual | $68,438 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0401-03-026 | ||
---|---|---|---|
Length: | 48.4 | ||
Estimate: | $897,151 | ||
Actual: | $491,543 | ||
CCSJ: 0910-35-033 |
|||
District: | TYLER | Let Date: | Mar 2019 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 1602(656) | CSJ: | 0910-35-033 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | CR 2790 AT BLACK CREEK | Fund Cat: | 6 |
Limits To: | STR#AA2790101, 0.25 MI S OF US 80 | ESTIMATE: | $389,734 |
Length: | 1.0 | Actual | $342,388 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0910-35-033 | ||
Length: | 1 | ||
Estimate: | $389,734 | ||
Actual: | $342,388 | ||
CCSJ: 1390-03-005 |
|||
District: | TYLER | Let Date: | Mar 2019 |
Highway: | FM 1254 | Let Status: | Actual |
Project ID: | BR 2018(791) | CSJ: | 1390-03-005 |
Description: | REPLACE BRIDGE & APPROACHES | Handling Code: | |
Limits From: | AT LAKE FORK CREEK | Fund Cat: | 6 |
Limits To: | STR# 005 | ESTIMATE: | $1,673,512 |
Length: | 0.1 | Actual | $1,518,306 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 1390-03-005 | ||
Length: | 0.1 | ||
Estimate: | $1,673,512 | ||
Actual: | $1,518,306 | ||
CCSJ: 3240-01-019 |
|||
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SL 564 | Let Status: | Actual |
Project ID: | STP 2019(323) | CSJ: | 3240-01-019 |
Description: | REPAIR & RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 69, NW OF MINEOLA, E, S & W | Fund Cat: | 1 |
Limits To: | US 69 SOUTH OF MINEOLA | ESTIMATE: | $5,912,280 |
Length: | 5.8 | Actual | $5,773,807 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 3240-01-019 | ||
Length: | 5.8 | ||
Estimate: | $5,912,280 | ||
Actual: | $5,773,807 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |