Detail Letting Schedule for Guadalupe County (FY 2019)

Last Update: Tuesday, August 13, 2024

Bid Tabulations Dashboard

This report will no longer be updated, please access links on the Contract Letting page.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Guadalupe County (FY 2019)

CCSJ: 0025-10-092

District:SAN ANTONIOLet Date:Nov 2018
Highway:FM 78Let Status:Actual
Project ID:STP 2019(171)CSJ:0025-10-092
Description:SPOT BASE REPAIR, OVERLAY & PAVEMENT MARKINGSHandling
Code:
 
Limits From:0.2 MI EAST OF GEMBLER ROADFund Cat:1
Limits To:0.1 MI WEST OF WESTGATE DRIVEESTIMATE:$4,270,673
Length:7.0Actual$3,808,767
 
District:SAN ANTONIOLet Date:Nov 2018
Highway:SH 46Let Status:Actual
Project ID:STP 2019(171)CSJ:0216-02-062
Description:MILL, OVERLAY & PAVEMENT MARKINGSHandling
Code:
 
Limits From:C.H. MATTHIES JRFund Cat:1
Limits To:0.7 MI EAST OF FM 467ESTIMATE:$3,583,457
Length:4.4Actual$3,512,736
 
Back...
Totals for 0025-10-092
Length:11.4
Estimate:$7,854,130
Actual:$7,321,503

CCSJ: 0366-03-068

District:SAN ANTONIOLet Date:Jun 2019
Highway:SH 123Let Status:Approved
Project ID:NH 1902(063)CSJ:0366-03-068
Description:Widen Road - Add ShouldersHandling
Code:
 
Limits From:SH 46Fund Cat:1
Limits To:WILSON/GUADALUPE COUNTY LINEESTIMATE:$24,540,496
Length:10.1Actual$0
 
Back...
Totals for 0366-03-068
Length:10.1
Estimate:$24,540,496
Actual:

CCSJ: 0366-12-030

District:SAN ANTONIOLet Date:May 2019
Highway:BS 123-Let Status:Approved
Project ID:STP 2019(901)HESCSJ:0366-12-030
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:0.4 MI N OF UA 90Fund Cat:8
Limits To:0.2 MI S OF UA 90ESTIMATE:$1,061,946
Length:0.6Actual$0
 
Back...
Totals for 0366-12-030
Length:0.6
Estimate:$1,061,946
Actual:

CCSJ: 2021-02-018

District:SAN ANTONIOLet Date:Aug 2019
Highway:FM 1044Let Status:Tentative
Project ID:STP ( )FRS1CSJ:2021-02-018
Description:INSTALL PREEMPTED TRAFFIC SIGNAL ON FM 1044 AT UPRR DOT 742Handling
Code:
XX
Limits From:0.1 MI N OF FM 78Fund Cat:8
Limits To:FM 78ESTIMATE:$450,000
Length:0.1Actual$0
 
Back...
Totals for 2021-02-018
Length:0.1
Estimate:$450,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract