The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Kendall County (FY 2019)

CCSJ: 0072-06-074

District:SAN ANTONIOLet Date:Apr 2019
Highway:IH 10Let Status:Actual
Project ID:NH 2019(776)CSJ:0072-06-074
Description:RECONFIGURE RAMPS AND WIDEN FRONTAGE ROAD TO CONVERT TO ONEHandling
Code:
 
Limits From:CASCADE CAVERNS/SCENIC LOOPFund Cat:1
Limits To:KENDALL/BEXAR COUNTY LINEESTIMATE:$18,316,620
Length:1.5Actual$17,816,513
 
District:SAN ANTONIOLet Date:Apr 2019
Highway:IH 10Let Status:Actual
Project ID:ROW 72-6-79CSJ:0072-06-079
Description:UTILITYHandling
Code:
 
Limits From:CASCADE CAVERNS/SCENIC LOOPFund Cat:ROW
Limits To:KENDALL/BEXAR COUNTY LINEESTIMATE:
Length:1.5Actual$518,572
 
Back...
Totals for 0072-06-074
Length:3
Estimate:$18,316,620
Actual:$18,335,085

CCSJ: 0072-06-084

District:SAN ANTONIOLet Date:Apr 2019
Highway:IH 10Let Status:Actual
Project ID:NH 2019(768)CSJ:0072-06-084
Description:OVERLAY AND PAVEMENT MARKINGS ON MAIN LANESHandling
Code:
 
Limits From:CIBOLO CREEKFund Cat:1
Limits To:SH 46ESTIMATE:$2,667,715
Length:2.8Actual$2,347,057
 
District:SAN ANTONIOLet Date:Apr 2019
Highway:IH 10Let Status:Actual
Project ID:NH 2019(768)CSJ:0142-14-063
Description:BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ONHandling
Code:
 
Limits From:GILLESPIE/KERR COUNTY LINEFund Cat:1
Limits To:1.3 MI E OF GILLESPIE/KERR CTY LINEESTIMATE:$1,491,885
Length:1.2Actual$1,316,662
 
District:SAN ANTONIOLet Date:Apr 2019
Highway:IH 10Let Status:Actual
Project ID:NH 2019(768)CSJ:0142-14-064
Description:BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ONHandling
Code:
 
Limits From:0.4 MI E OF SH 16Fund Cat:1
Limits To:KERR/KENDALL COUNTY LINEESTIMATE:$12,977,933
Length:13.1Actual$11,972,251
 
Back...
Totals for 0072-06-084
Length:17.1
Estimate:$17,137,533
Actual:$15,635,971

CCSJ: 0072-14-030

District:SAN ANTONIOLet Date:Oct 2018
Highway:US 87Let Status:Actual
Project ID:NH 2019(068)CSJ:0072-14-030
Description:LANDSCAPE DEVELOPMENTHandling
Code:
 
Limits From:RICHTER AVEFund Cat:10
Limits To:E. SAN ANTONIO AVEESTIMATE:$193,288
Length:0.3Actual$188,428
 
Back...
Totals for 0072-14-030
Length:0.3
Estimate:$193,288
Actual:$188,428

CCSJ: 0142-15-026

District:SAN ANTONIOLet Date:May 2019
Highway:IH 10Let Status:Approved
Project ID:NH 2019(788)CSJ:0142-15-026
Description:Highway ImprovementHandling
Code:
 
Limits From:NORTH CREEK RD.Fund Cat:1
Limits To:US 87ESTIMATE:
Length:1.0Actual$0
 
District:SAN ANTONIOLet Date:May 2019
Highway:IH 10Let Status:Approved
Project ID:NH 2019(788)CSJ:0142-15-028
Description:OVERLAY AND PAVEMENT MARKINGS ON MAIN LANESHandling
Code:
 
Limits From:KENDALL/KERR COUNTY LINEFund Cat:1
Limits To:0.09 MILES NORTH OF FM 473ESTIMATE:$4,060,034
Length:1.9Actual$0
 
Back...
Totals for 0142-15-026
Length:2.9
Estimate:$4,060,034
Actual:

CCSJ: 1899-01-018

District:SAN ANTONIOLet Date:May 2019
Highway:RM 1376Let Status:Approved
Project ID:STP 2019(909)CSJ:1899-01-018
Description:WIDEN ROAD - ADD SHOULDERSHandling
Code:
 
Limits From:0.5 MI N OF WASP CREEK RDFund Cat:1
Limits To:US 87 BESTIMATE:$10,462,670
Length:8.1Actual$0
 
Back...
Totals for 1899-01-018
Length:8.1
Estimate:$10,462,670
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment