Detail Letting Schedule for King County (FY 2019)

Last Update: Tuesday, August 13, 2024

Bid Tabulations Dashboard

This report will no longer be updated, please access links on the Contract Letting page.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

King County (FY 2019)

CCSJ: 0032-06-038

District:CHILDRESSLet Date:Sep 2018
Highway:US 83Let Status:Actual
Project ID:STP 2019(014)CSJ:0032-06-038
Description:ASPHALTIC CONCRETE PAVEMENT OVERLAYHandling
Code:
 
Limits From:US 82, SOUTHFund Cat:1
Limits To:NORTH CROTON CREEKESTIMATE:$3,389,757
Length:5.8Actual$3,231,945
 
Back...
Totals for 0032-06-038
Length:5.8
Estimate:$3,389,757
Actual:$3,231,945

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract