Letting Schedule for Abilene District (FY 2019)

Last Update: Monday, July 16, 2018
Abilene District (FY 2019)
Callahan | Fisher | Howard | Jones | Mitchell | Nolan | Scurry | Shackelford | Taylor |

Callahan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0437-04-029US 283TentativeJan 2019$563,0006BRIDGE REHAB0.0
0437-04-030US 283TentativeJan 2019$490,0006BRIDGE REHAB0.0
0437-02-017US 283TentativeJan 2019$4,500,000112"OVERLAY0.0
0007-01-062IH 20TentativeJan 2019$730,0006BRIDGE REHAB0.0
0437-03-042US 283TentativeDec 2018$01SEAL COAT0.0
0181-03-025SH 36TentativeFeb 2019$2,436,4118MILLED EDGELINE RUMBLE STRIPS0.0
0006-07-080IH 20TentativeMay 2019$6,700,0001MILL & SMA OVRLAY0.0

Fisher County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0317-01-037FM 57TentativeJun 2019$14,904,8401WIDEN ROADWAY AND STRUCTURES0.0

Howard County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0005-10-023BI 20-GTentativeDec 2018$13,332,1911SEAL COAT0.0
0908-12-028VATentativeDec 2018$60,00010SEAL COAT ROADS, PARKING LOTS, RESIDENCE DRIVES, AND0.0

Jones County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0033-04-063US 83ApprovedSep 2018$11,222,2601CONSTRUCT SUPER TWO0.0
1654-01-019FM 1661TentativeDec 2018$11,330,9081SEAL COAT0.0
0296-05-034US 180TentativeJan 2019$7,500,0001BASE REPAIR LEVEL UP AND OVERLAY0.0

Mitchell County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0006-01-100IH 20TentativeJan 2019$500,0001REMOVE EXISTING RAMP0.0

Nolan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0053-20-006BU 84-JTentativeDec 2018$01SEAL COAT0.0
0053-15-024FM 608TentativeMay 2019$3,491,0038SAFETY TREAT FIXED OBJECTS, PROVIDE ADDITIONAL PAVED SURFACE0.0
0006-02-115IH 20TentativeMar 2019$12,026,6401MILL AND FILL WITH SPOT PAVEMENT REPAIR0.0

Scurry County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1361-03-029SH 208TentativeAug 2019$010REPLANK RAILROAD CROSSING0.0
0908-19-025CRTentativeJun 2019$1,371,6896REMOVE AND REPLACE EXISTING BRIDGE AND APPROACHES0.0

Shackelford County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0125-04-033US 283TentativeJan 2019$11,820,60511REHABILITATE AND WIDEN ROADWAY0.0

Taylor County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0908-00-919VATentativeFeb 2019$01THERMOPLASTIC PAVEMENT MARKINGS AND RAISED PAVEMENT MARKERS0.0
0181-01-061SH 36TentativeApr 2019$4,650,0001MILL AND FILL0.0
0699-01-055FM 89TentativeMar 2019$2,500,0001MILL AND OVERLAY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract