Letting Schedule for January, 2019 County (FY 2019)

Last Update: Monday, November 13, 2017
January, 2019 (FY 2019)(see Links)
SEP 2018 | OCT 2018 | NOV 2018 | DEC 2018 | JAN 2019 | FEB 2019 | MAR 2019 | APR 2019 | MAY 2019 | JUN 2019 | JUL 2019 | AUG 2019 |
CCSJCounty/
District
HighwayLet StatusContract
Cost
Fund
Cat
Description
0911-00-076Angelina/
Lufkin
VATentative$3,000,00010CONSTRUCT CURB RAMPS IN VARIOUS LOCATION IN THE LUFKIN
0914-18-107Bastrop/
Austin
CRTentative$600,0006REHABILITATE BRIDGE & APPROACHES
0184-03-038Bell/
Waco
SH 53Tentative$945,7071MILL/OVERLAY
0320-01-073Bell/
Waco
SS 290Tentative$900,00011MILL AND INLAY
0184-03-039Bell/
Waco
SH 53Tentative$1,913,0443INSTALLATION OF ON-STREET BIKE LAND AND ADA COMLPIANT
0915-12-562Bexar/
San Antonio
CRTentative$4,886,1163EXPAND FROM 2 TO 4 LANES, INCLUDING DRAINAGE IMPROVEMENTS,
0915-12-514Bexar/
San Antonio
CSTentative$933,0003CONSTRUCTION OF A HIKE AND BIKE TRAIL ALONG HUEBNER CREEK
0915-12-579Bexar/
San Antonio
VATentative$2,000,0003CONSTRUCT CITYWIDE PEDESTRIAN AND BICYCLE IMPROVEMENTS
0291-11-021Bexar/
San Antonio
SS 421Tentative$411,3848INSTALL RAISED MEDIANS WITH ACTUATED PED SYMBOLS
0178-02-089Brazoria/
Houston
SH 35Tentative$3,485,0001DIAMOND GRINDING MAINLANES AND 1.5" ACP OVERLAY ON SHOULDERS
0923-00-059Brown/
Brownwood
VATentative$1,000,0001THERMOPLASTIC STRIPING
1378-04-051Burnet/
Austin
RM 1431Tentative$475,0001FULL DEPTH REPAIR & SEAL COAT
0144-03-037Calhoun/
Yoakum
US 87Tentative$733,3148IMPROVE GUARDRAIL TO DESIGN STANDARDS
0437-02-017Callahan/
Abilene
US 283Tentative$4,500,000112"OVERLAY
0921-06-252Cameron/
Pharr
CSTentative$7,412,83911CONSRTUCT 2 LANE RURAL
0921-06-207Cameron/
Pharr
VATentative$6,696,80211CONSTRUCTION OF BORDER SAFETY INSPECTION FACILITY (BSIF)
0220-05-075Cameron/
Pharr
SH 48Tentative$02MPROPOSED RAISED MEDIAN
3403-01-001Camp/
Atlanta
SL 255Tentative$5,946,70011CONSTRUCT 2-LANE ROADWAY ON NEW LOCATION
0277-03-028Cass/
Atlanta
SH 77Tentative$4,368,0001RESURFACE EXISTING 2-LANE HIGHWAY
0926-01-023Cherokee/
Tyler
FM 343Tentative$638,0918IMPROVE DRAINAGE AND CULVERTS FOR SAFETY
0345-03-023Cherokee/
Tyler
SH 110Tentative$1,465,7338INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS
0925-00-069Childress/
Childress
VATentative$1,000,0001DISTRICT WIDE STRIPING
0816-04-096Collin/
Dallas
FM 455Tentative$2,514,2201RECONSTRUCT EXISTING PAVEMENT AND ADD SHOULDERS
0724-01-053Coryell/
Waco
FM 116Tentative$217,80011BASE REPAIR, SEAL AND OVERLAY
0918-00-277Dallas/
Dallas
VATentative$300,0001WAREHOUSE PROCUREMENT TO REFURBISH ITS EQUIPMENT
0918-00-276Dallas/
Dallas
VATentative$1,072,6881DMS REHABILITATION
0004-07-130Ector/
Odessa
IH 20Tentative$2,067,1636BRIDGE REPAIR
0924-06-537El Paso/
El Paso
VATentative$1,000,00052ND YEAR OF DYER BRT-RTS OPERATIONS
2121-02-161El Paso/
El Paso
IH 10Tentative$1,500,0003BRIDGE AESTHETICS AND LANDSCAPE IMPROVEMENTS
0924-06-550El Paso/
El Paso
VATentative$1,000,0005FIRST YEAR OF ALAMEDA BRT-RTS OPERATIONS
1317-01-015Ellis/
Dallas
FM 1183Tentative$16,452,7061RECONSTRUCT EXISTING PAVEMENT AND ADD SHOULDERS
0909-38-079Falls/
Waco
CRTentative$270,0006REPLACE BRIDGE AND APPROACHES
0188-10-021Fort Bend/
Houston
FM 1463Tentative$33,400,0002MWIDEN FROM 2 TO 4 AND 6 LANES URBAN DIVIDED
0912-34-192Fort Bend/
Houston
VATentative$6,092,0003INSTALL WIRELESS TRAFFIC SIGNAL COMMUNICATION SYSTEM
0228-02-048Gaines/
Lubbock
US 62Tentative$6,000,0001RESTORATION OF ROADWAY
0912-73-207Galveston/
Houston
CSTentative$1,756,0003MILL AND OVERLAY
0912-72-360Harris/
Houston
CSTentative$10,750,0003RECONSTRUCT ROADWAY
0912-72-388Harris/
Houston
VATentative$40,225,6313CONSTRUCT RAILROAD UNDERPASS AT NAVIGATION/COMMERCE AND
1062-04-022Harris/
Houston
FM 2100Tentative$39,000,0002MWIDEN TO 4-LANE DIVIDED
0912-00-554Harris/
Houston
VATentative$2,000,0003REGIONAL ITS INFRASTRUCTURE - HARDWARE/SOFTWARE, UTILITIES
0912-72-347Harris/
Houston
CSTentative$598,0006REPLACE BRIDGE & APPROACHES (NBI# 12102B31961177)
0912-72-352Harris/
Houston
CSTentative$327,0006REPLACE BRIDGE & APPROACHES NBI# 12102B38857153
1685-01-090Harris/
Houston
FM 1960Tentative$31,367,0001INTERSECTION IMPROVEMENTS
0028-01-098Harris/
Houston
BU 90-UTentative$1,400,0001UPGRADE DRAINAGE STRUCTURES (EB & WB)
0912-00-526Harris/
Houston
VATentative$1,000,0001UPGRADE LIGHTING SYSTEMS
0108-03-042Henderson/
Tyler
SH 19Tentative$1,031,4488INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS
0921-02-375Hidalgo/
Pharr
CSTentative$07WIDEN TO 5 LANE CURB & GUTTER
0921-02-155Hidalgo/
Pharr
VATentative$07TRAFFIC SIGNAL HARDWARE IMPROVEMENTS
0918-11-090Kaufman/
Dallas
CRTentative$1,077,9126REPLACE BRIDGE AND APPROACHES
0918-11-089Kaufman/
Dallas
CRTentative$838,7636REPLACE BRIDGE AND APPROACHES
0133-03-046Knox/
Childress
US 82Tentative$4,154,0001REHABILITATION OF EXISTING ROADWAY
0346-06-049Lavaca/
Yoakum
SH 111Tentative$1,233,9938SAFETY TREAT FIXED OBJECTS
0334-05-031Lee/
Austin
FM 141Tentative$341,3601REPAIR, LEVEL-UP & SEAL COAT
0055-08-119Mclennan/
Waco
US 84Tentative$2,306,50011MILL AND PFC OVERLAY
0915-45-053Medina/
San Antonio
CRTentative$469,1956REPLACE BRIDGE & APPROACHES
0110-02-024Montgomery/
Houston
SH 75Tentative$1,180,0001HOT MIX OVERLAY AND ADD SHOULDERS
0920-30-078Orange/
Beaumont
CSTentative$3,000,0006REPLACE BRIDGE AND APPROACHES
0902-39-033Palo Pinto/
Ft Worth
CRTentative$945,9456REPLACE BRIDGE AND APPROACHES
0008-09-036Parker/
Ft Worth
FM 5Tentative$5,203,6721REPAIR BASE FAILURES, HMAC OVERLAY, PAVEMENT MARKINGS
0041-07-106Potter/
Amarillo
US 87Tentative$3,500,0006REPLACE BRIDGE AND APPROACHES
0558-09-035Reagan/
San Angelo
SH 137Tentative$12,548,45511GRADING, BASE AND SURFACING
2363-01-006Rockwall/
Dallas
FM 2453Tentative$1,011,2008PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE
1290-03-024Rockwall/
Dallas
SH 276Tentative$3,326,3291MILL, OVERLAY, FULL DEPTH REPAIR AND PAVEMENT MARKINGS
0372-01-103San Patricio/
Corpus Christi
US 77Tentative$614,1478SAFETY LIGHTING AT INTERSECTION
0125-04-033Shackelford/
Abilene
US 283Tentative$8,552,85211REHABILITATE AND WIDEN ROADWAY
0910-00-107Smith/
Tyler
VATentative$235,0001FY 2019 DISTRICT-WIDE THERMO PROGRAM
0256-02-031Stephens/
Brownwood
SH 67Tentative$17,099,77611ACP OVERLAY
0902-00-157Tarrant/
Ft Worth
VATentative$970,0003SCHOOL BUS, CLEAN TECHNOLOGY REVOLVING LOAN PROGRAM,
0902-00-166Tarrant/
Ft Worth
VATentative$1,899,3351NON-SITE SPECIFIC TRAFFIC SIGNAL INSTALLATION
0008-07-035Tarrant/
Ft Worth
SH 180Tentative$6,169,0521REPAIR BASE FAILURES, MILL, HMAC OVERLAY, PAVEMENT MARKINGS
2102-01-071Travis/
Austin
RM 2244Tentative$451,0001OVERLAY ROAD WITH EDGE MILLING
0016-01-125Travis/
Austin
SL 275Tentative$560,0001TOM OVERLAY WITH EDGE MILLING
0043-08-076Wichita/
Wichita Falls
US 287Tentative$270,3778SAFETY LIGHTING
0043-08-075Wichita/
Wichita Falls
US 287Tentative$1,970,00011WIDEN SHOULDERS
0038-05-040Zapata/
Pharr
US 83Tentative$011WIDEN FROM 2 LANE RURAL TO 4 LANE DIVIDED


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract