Letting Schedule for Brownwood District (FY 2019)

Last Update: Monday, October 22, 2018
Brownwood District (FY 2019)
Brown | Comanche | Eastland | Mcculloch | San Saba | Stephens |

Brown County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0128-01-112US 377TentativeAug 2019$250,0008INSTALL PROTECTIVE DEVICES0.0
0923-00-060VAApprovedFeb 2019$200,0001THERMOPLASTIC STRIPING0.0
0923-06-081VATentativeAug 2019$250,0008INSTALL PROTECTIVE DEVICES0.0
0054-06-104US 67ApprovedFeb 2019$1,619,1128PROFILE CENTER AND EDGELINE MARKINGS0.0

Comanche County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0079-03-048US 67TentativeApr 2019$980,7338IMPROVE GUARDRAIL TO DESIGN STANDARDS0.0
0183-01-039SH 36TentativeJul 2019$5,781,6091REHAB EXISTING ROADWAY AND ADD PASSING LANES0.0
0183-01-045SH 36TentativeMar 2019$1,255,0001MILL AND SEAL COAT0.0

Eastland County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0007-03-092IH 20ApprovedNov 2018$8,402,2951SEAL COAT0.0

Mcculloch County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0128-04-038US 190ApprovedJan 2019$6,802,57911RECONSTRUCT ROADWAY TO INCLUDE CONCRETE PAVMENT,STORM DRAIN,0.0

San Saba County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0867-07-013RM 501ApprovedFeb 2019$2,211,7148IMPROVE GUARDRAIL, SAFETY TREAT FIXED OBJECTS, CONSTRUCT0.0

Stephens County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
3469-01-013FM 3099TentativeJun 2019$2,178,0008PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROFILE PAVEMENT0.0
0256-02-031SH 67TentativeMay 2019$7,500,00011ACP OVERLAY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract