Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Lufkin District (FY 2019) |
Angelina | Houston | Nacogdoches | Polk | Sabine | San Augustine | San Jacinto | Shelby | | |||||||
Angelina County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0911-00-078 | VA | Actual | Oct 2018 | $1,340,333 | 1 | INSTALL PROFILE PAVEMENT MARKINGS | 0.0 |
0200-01-091 | US 69 | Actual | Mar 2019 | $122,361 | 1 | INSTALL TRAFFIC SIGNAL | 0.0 |
0336-05-061 | SH 103 | Actual | Dec 2018 | $1,290,979 | 1 | RESURFACE WITH THIN OVERLAY MIXTURE | 0.0 |
0390-03-035 | SH 147 | Actual | Dec 2018 | $823,222 | 8 | SAFETY TREAT FIXED OBJECTS (IMPROVE GUARDRAIL TO SAFETY | 6.0 |
0336-03-071 | SH 103 | Actual | Mar 2019 | $1,219,821 | 11 | WIDENING EXISTING PAVING FOR ADDITIONAL TURNING LANES | 5.0 |
0911-00-076 | VA | Actual | Jul 2019 | $4,277,919 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 12.0 |
0200-03-021 | US 69 | Actual | Jun 2019 | $32,816,731 | 1 | HIGHWAY IMPROVEMENT | 4.5 |
2115-01-018 | FM 2251 | Actual | Aug 2019 | $72,000 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
2507-01-020 | FM 326 | Actual | Jul 2019 | $3,876,890 | 11 | HIGHWAY IMPROVEMENT | 8.0 |
0336-05-066 | SH 103 | Actual | Jul 2019 | $2,137,153 | 6 | BRIDGE MAINTENANCE | 2.0 |
Houston County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0109-03-037 | US 287 | Actual | May 2019 | $1,125,506 | 8 | HIGHWAY IMPROVEMENT | 0.0 |
0937-02-030 | FM 227 | Actual | Jul 2019 | $1,363,450 | 6 | BRIDGE REPLACEMENT | 4.0 |
2813-01-008 | FM 2781 | Actual | Oct 2018 | $4,279,843 | 1 | RECONSTRUCT & WIDEN EXISTING PAVEMENT | 7.0 |
0635-03-025 | FM 228 | Actual | Nov 2018 | $3,635,559 | 1 | RESURFACE WITH SEALCOAT | 0.0 |
Nacogdoches County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2560-01-083 | SL 224 | Actual | Feb 2019 | $1,603,357 | 1 | RESURFACE WITH THIN OVERLAY MIXTURE | 0.0 |
0138-06-044 | US 259 | Actual | Jan 2019 | $3,723,258 | 1 | PLANE, OCST AND PERMEABLE FRICTION COURSE | 0.0 |
0176-01-081 | US 59 | Actual | Jul 2019 | $78,199,878 | 1 | HIGHWAY IMPROVEMENT | 8.5 |
1407-01-028 | FM 1275 | Actual | Mar 2019 | $783,095 | 8 | SAFETY TREAT FIXED OBJECTS | 3.0 |
2590-02-010 | FM 2609 | Actual | Feb 2019 | $3,997,749 | 11 | RECONSTRUCT AND WIDEN PAVEMENT | 5.0 |
Polk County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0177-01-112 | US 59 | Actual | Aug 2019 | $1,821,724 | 6 | BRIDGE MAINTENANCE | 6.0 |
1876-01-037 | FM 1988 | Actual | Nov 2018 | $27,310 | 10 | PLACE FLOWABLE FILL UNDER RIPRAP SLOPE TO FILL VOID AND TO | 0.0 |
0176-05-187 | US 59 | Actual | Aug 2019 | $31,018 | 10 | EMERGENCY RELIEF | 0.0 |
0177-01-108 | US 59 | Actual | Aug 2019 | $430,594 | 10 | EMERGENCY RELIEF | 0.0 |
1408-01-025 | FM 1276 | Actual | Nov 2018 | $128,133 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
0176-05-184 | US 59 | Actual | Nov 2018 | $8,468 | 10 | EMERGENCY EROSION REPAIRS | 0.0 |
0911-04-055 | VA | Actual | Aug 2019 | $1,552,868 | 10 | HIGHWAY IMPROVEMENT | 0.0 |
1876-01-036 | FM 1988 | Actual | Nov 2018 | $116,154 | 10 | REESTABLISH SLOPE NEAR COLUMNS, REPLACE STONE RIPRAP IN THE | 0.0 |
0176-05-185 | US 59 | Actual | Feb 2019 | $14,544 | 10 | REESTABLISH THE EMBANKMENT TO PREVENT FURTHER EROSION | 0.0 |
0177-01-106 | US 59 | Actual | Feb 2019 | $18,962 | 10 | EMERGENCY RELIEF | 0.0 |
0177-01-104 | US 59 | Actual | Feb 2019 | $23,724 | 10 | EMERGENCY RELIEF | 0.0 |
0176-05-186 | US 59 | Actual | Jul 2019 | $1,858 | 10 | EMERGENCY RELIEF | 0.0 |
0911-04-076 | CR | Actual | Jul 2019 | $1,595,654 | 6 | BRIDGE REPLACEMENT | 6.0 |
0176-05-183 | US 59 | Actual | Jan 2019 | $9,142 | 10 | REPLACE ERODED EMBANKMENT AND REPLACE THE DAMAGED CONCRETE | 0.0 |
1408-01-026 | FM 1276 | Actual | Feb 2019 | $106,788 | 10 | REPAVE AND RETREAT FLEX BASE (ROUGHLY 1000 FT LONG) | 0.0 |
0176-05-181 | US 59 | Actual | Jan 2019 | $3,685,521 | 1 | PLANE, HMA & PERMEABLE FRICTION COURSE | 0.0 |
Sabine County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
1679-01-015 | FM 276 | Actual | Nov 2018 | $11,416 | 10 | EMERGENCY EROSION REPAIRS | 0.0 |
0064-06-055 | US 96 | Actual | May 2019 | $195,070 | 6 | HIGHWAY IMPROVEMENT | 0.0 |
1510-01-022 | FM 1592 | Actual | Feb 2019 | $3,918 | 10 | EMERGENCY EROSION REPAIRS | 0.0 |
1679-01-016 | FM 276 | Actual | Feb 2019 | $7,509 | 10 | REESTABLISH THE SLOPE AT THE EAST ABUTMENT | 0.0 |
1510-01-023 | FM 1592 | Actual | Feb 2019 | $23,016 | 10 | REESTABLISH THE FRONT SLOPE ON THE WEST SIDE OF THE | 0.0 |
0064-05-061 | FM 1 | Actual | Dec 2018 | $2,056,935 | 8 | SAFETY TREAT FIXED OBJECTS; PROVIDE ADDITIONAL PAVED SURFACE | 6.5 |
San Augustine County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
1079-01-036 | FM 705 | Actual | Sep 2018 | $72,132 | 10 | BRIDGE EMBANKMENT AND CONCRETE RIPRAP RESTORED | 0.0 |
0911-30-030 | CR | Actual | Jul 2019 | $1,073,324 | 6 | BRIDGE REPLACEMENT | 5.0 |
0118-12-019 | FM 353 | Actual | Jan 2019 | $212,884 | 10 | EMERGENCY REPAIR ON CULVERT | 0.0 |
0064-03-021 | SH 147 | Actual | Oct 2018 | $2,214,401 | 8 | PROFILE EDGELINE MARKINGS | 0.0 |
San Jacinto County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2829-02-008 | FM 2693 | Actual | Nov 2018 | $46,305 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
0403-01-048 | SH 156 | Actual | Feb 2019 | $15,991 | 10 | EMERGENCY RELIEF | 0.0 |
0395-02-044 | SH 150 | Actual | Nov 2018 | $90,642 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
3038-01-013 | FM 222 | Actual | Sep 2018 | $871 | 10 | EMERGENCY EROSION REPAIRS | 0.0 |
0395-02-046 | SH 150 | Actual | Nov 2018 | $9,222 | 10 | EMERGENCY EROSION REPAIRS | 0.0 |
0177-02-099 | US 59 | Actual | Sep 2018 | $12,737 | 10 | EMERGENCY RELIEF | 0.0 |
3038-01-014 | FM 222 | Actual | Sep 2018 | $16,853 | 10 | REPLACE RIPRAP UNDER BRIDGE AND FILL VOIDS BEHIND RIPRAP | 0.0 |
0177-02-102 | US 59 | Actual | Aug 2019 | $624,386 | 10 | EMERGENCY RELIEF | 0.0 |
0177-02-098 | US 59 | Actual | Nov 2018 | $15,746 | 10 | REPLACED FLOWABLE BACKFILL IN THE VOID AT THE ABUTMENT | 0.0 |
2829-02-009 | FM 2693 | Actual | Feb 2019 | $128,011 | 10 | REPLACE GUARDRAIL, REPLACE BASE MATERIAL AND PAVEMENT | 0.0 |
0395-02-047 | SH 150 | Actual | Sep 2018 | $66,579 | 10 | EMERGENCY RELIEF | 0.0 |
0395-03-045 | SH 150 | Actual | Sep 2018 | $13,516 | 10 | REPLACE RIPRAPUNDER BRIDGE AND REPLACE FLEXBASE ON ACCESS | 0.0 |
0395-02-041 | SH 150 | Actual | Oct 2018 | $11,874,733 | 1 | RECONSTRUCT PAVEMENT AND ADD PASSING LANES | 4.0 |
0395-02-045 | SH 150 | Actual | Feb 2019 | $34,986 | 10 | REPLACE OR RESET GUARDRAIL, REPLACE FAILED MOW STRIP/REPLACE | 0.0 |
0403-01-047 | SH 156 | Actual | Jul 2019 | $2,710 | 10 | EMERGENCY RELIEF | 0.0 |
Shelby County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0059-05-045 | SH 7 | Actual | Nov 2018 | $10,988,049 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
1682-01-015 | FM 1645 | Actual | Jun 2019 | $5,798,189 | 1 | HIGHWAY IMPROVEMENT | 5.0 |
0175-02-093 | US 84 | Actual | May 2019 | $1,390,881 | 1 | RESURFACE ROADWAY | 0.0 |
0063-06-099 | US 96 | Actual | Aug 2019 | $3,692,328 | 6 | BRIDGE MAINTENANCE | 6.0 |
|