Letting Schedule for Waco District (FY 2019)

Last Update: Monday, January 14, 2019
Waco District (FY 2019)
Bell | Bosque | Coryell | Falls | Hamilton | Hill | Limestone | Mclennan |

Bell County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0185-01-030US 190TentativeJul 2019$62,800,0001WIDEN FROM 2 LANE TO 4 LANE DIVIDED RURAL0.0
3409-01-006FM 3481TentativeAug 2019$1,552,5001ADD TURN LANES0.0
2136-01-015FM 2268ApprovedFeb 2019$4,229,5036REPLACE BRIDGE AND APPROACHES8.0
0836-02-073SH 195ApprovedMay 2019$3,400,0001TURNAROUND UNDERPASS FOR NORTHBOUND AND SOUTHBOUND TRAFFIC0.0
0836-02-075SH 195ActualJan 2019$320,7168INSTALL TRAFFIC SIGNAL, ADVANCED WARNING SIGNAL, AND SIGNS0.0
0909-36-164CSTentativeAug 2019$250,0008UPGRADE RR CROSSING SIGNALS FEDERAL SAFETY PROGRAM (FSP)0.0
0320-01-072SH 95ApprovedApr 2019$5,000,0001MILL AND OVERLAY0.0
0015-05-050SH 317ApprovedMay 2019$543,1118IMPROVE AND INTERCONNECT TRAFFIC SIGNALS0.0
0231-03-145US 190TentativeJun 2019$46,695,3671WIDEN FROM FOUR TO SIX LANES AND RESURFACE0.0
0184-03-040SH 53ApprovedMar 2019$2,334,7601MILL AND INLAY0.0
1835-02-056FM 1741TentativeAug 2019$3,000,0001MILL AND OVERLAY0.0
1198-03-010FM 2670TentativeJun 2019$2,604,0008PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE0.0
0320-01-073SS 290ActualJan 2019$1,421,27811MILL AND INLAY0.0
0836-02-025SH 195ActualNov 2018$339,2041SAFETY LIGHTING0.0
0909-36-157CSActualNov 2018$2,375,1013CONSTRUCT HIKE AND BIKE TRAIL AND SIDEWALKS WITH LANDSCAPING0.0
2502-01-015SL 121TentativeJul 2019$110,0968IMPROVE TRAFFIC SIGNAL0.0
0015-14-126IH 35ActualJan 2019$7,788,3321MILL AND PFC OVERLAY0.0
0184-03-038SH 53ActualJan 2019$1,204,1281MILL/OVERLAY0.0

Bosque County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
2872-01-007FM 2840TentativeAug 2019$31,14410REPLACE CONCRETE CROSSING SURFACE0.0

Coryell County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0724-01-053FM 116ActualJan 2019$1,751,01711BASE REPAIR, SEAL AND OVERLAY0.0
1187-01-029FM 929ActualSep 2018$8,219,8851SEAL COAT0.0
0567-01-020FM 107ApprovedMay 2019$2,000,0001SEAL AND OVERLAY0.0

Falls County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0909-38-082CRTentativeJun 2019$816,0006REPLACE BRIDGE AND APPROACHES0.0
0909-38-080CRApprovedMay 2019$1,070,0006REPLACE BRIDGE AND APPROACHES0.0
0909-38-079CRTentativeJul 2019$290,0006REPLACE BRIDGE AND APPROACHES0.0
0382-02-036SH 7ApprovedFeb 2019$7,235,2061MILL/OVERLAY2.0
0909-38-081CRApprovedMar 2019$1,400,6506REPLACE BRIDGE AND APPROACHES0.0

Hamilton County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0120-05-025FM 218ActualNov 2018$510,9291INSTALL CHEVRONS ON CURVE, INCREASE SUPERELELVATION0.0
0183-03-050SH 36ApprovedMay 2019$10,500,00011ADD PASSING LANES0.0

Hill County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0048-09-029IH 35EApprovedMay 2019$110,377,8941RECONSTRUCT AND WIDEN FROM 4 LANES TO 6 LANES, RECONSTRUCT0.0
0596-01-021FM 66TentativeJun 2019$838,9578SAFETY TREAT FIXED OBJECTS0.0

Limestone County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1664-01-019FM 1633TentativeJul 2019$4,185,0001REHABILITATE PAVEMENT STRUCTURE0.0
0056-02-033US 84ActualNov 2018$9,150,8141WIDEN SHOULDERS AND ADD PASSING LANES6.5

Mclennan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
2506-01-041FM 1695TentativeMar 2019$66,40810REPLACE CONCRETE CROSSING SURFACE0.0
0909-22-176CRApprovedApr 2019$792,0003REPLACE BRIDGE AND APPROACHES0.0
0833-03-045FM 1637ApprovedMay 2019$9,968,7078SAFETY TREAT FIXED OBJECTS0.0
2311-01-041SL 340TentativeJun 2019$230,7808IMPROVE TRAFFIC SIGNALS, INTERCONNECT SIGNALS0.0
0162-01-094US 84ActualDec 2018$93,9748IMPROVE TRAFFIC SIGNAL, INSTALL ADVANCE WARNING SIGNALS AND0.0
0909-22-177CRTentativeJul 2019$875,0003REPLACE BRIDGE AND APPROACHES0.0
0014-10-064BU 77-LTentativeJul 2019$4,800,0001MILL, SEAL, CAN, TOM OVERLAY0.0
1192-01-024FM 939ActualJan 2019$6,879,5861WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND6.5
0015-01-243IH 35ActualDec 2018$383,763,6471RECONST, WIDEN MAINLANES FROM 6 TO 8, RECONST FRONTAGE RD11.0
2061-02-030FM 2114ActualOct 2018$9,370,2241REHABILITATE AND WIDEN ROADWAY7.0
0909-22-181VAApprovedMar 2019$515,8003CONSTRUCTION OF SIDEWALKS AND STRIPING OF BICYCLE LANES0.0
0209-01-063SL 2ApprovedFeb 2019$864,34711MILL AND OVERLAY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract