Detail Letting Schedule for Montgomery County (FY 2019)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Montgomery County (FY 2019) |
CCSJ: 0110-02-027 |
|||
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | SH 75 | Let Status: | Approved |
Project ID: | BR 1902(175) | CSJ: | 0110-02-027 |
Description: | REPLACE BRIDGE AND APPROACHES (NBI# 12170011002001) | Handling Code: | |
Limits From: | AT LITTLE CANEY CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $2,000,000 |
Length: | 0.5 | Actual | $0 |
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | SH 75 | Let Status: | Approved |
Project ID: | STP 1902(175) | CSJ: | 0110-02-024 |
Description: | HOT MIX OVERLAY AND ADD SHOULDERS | Handling Code: | |
Limits From: | 0.46 MI S OF WALKER C/L | Fund Cat: | 1 |
Limits To: | 0.07 MI N OF WALKER C/L | ESTIMATE: | $955,000 |
Length: | 0.5 | Actual | $0 |
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | SH 75 | Let Status: | Approved |
Project ID: | STP 1902(175) | CSJ: | 0110-02-028 |
Description: | PLANING AND INLAY | Handling Code: | |
Limits From: | 0.379 MILES NORTH OF ROGERS RD | Fund Cat: | 1 |
Limits To: | FM 1097 (WEST STEWART ST) | ESTIMATE: | $90,000 |
Length: | 0.6 | Actual | $0 |
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | SH 75 | Let Status: | Approved |
Project ID: | STP 1902(175) | CSJ: | 0110-03-054 |
Description: | PLANING AND INLAY | Handling Code: | |
Limits From: | FM 1097 (WEST STEWART ST) | Fund Cat: | 1 |
Limits To: | 0.60 MILES SOUTH OF FM 2432 | ESTIMATE: | $135,000 |
Length: | 0.9 | Actual | $0 |
Back... | Totals for 0110-02-027 | ||
---|---|---|---|
Length: | 2.5 | ||
Estimate: | $3,180,000 | ||
Actual: | |||
CCSJ: 0177-05-113 |
|||
District: | HOUSTON | Let Date: | Sep 2018 |
Highway: | IH 69 | Let Status: | Actual |
Project ID: | NH 2019(022) | CSJ: | 0177-05-113 |
Description: | CONSTRUCT DETENTION POND | Handling Code: | |
Limits From: | FOSTORIA ROAD, NORTH | Fund Cat: | 1 |
Limits To: | LIBERTY COUNTY LINE | ESTIMATE: | $1,602,335 |
Length: | 0.1 | Actual | $1,256,328 |
Back... | Totals for 0177-05-113 | ||
Length: | 0.1 | ||
Estimate: | $1,602,335 | ||
Actual: | $1,256,328 | ||
CCSJ: 0177-05-117 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | IH 69 | Let Status: | Tentative |
Project ID: | ER 1802(636) | CSJ: | 0177-05-117 |
Description: | REPLACED TRAFFIC SIGNAL CABINET | Handling Code: | XX |
Limits From: | AT CREEKWOOD DR | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $219,322 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0177-05-117 | ||
Length: | 0 | ||
Estimate: | $219,322 | ||
Actual: | |||
CCSJ: 0177-05-119 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | IH 69 | Let Status: | Tentative |
Project ID: | ER 2019(126) | CSJ: | 0177-05-119 |
Description: | INSTALL FLEXIBLE RIP RAP PROTECTION SYSTEM | Handling Code: | XX |
Limits From: | AT PEACH CREEK | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $92,143 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0177-05-119 | ||
Length: | 0 | ||
Estimate: | $92,143 | ||
Actual: | |||
CCSJ: 0338-04-081 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | SH 105 | Let Status: | Tentative |
Project ID: | ER 1802(637) | CSJ: | 0338-04-081 |
Description: | REPLACED TRAFFIC SIGNAL CABINET | Handling Code: | XX |
Limits From: | AT FM 1485 | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $11,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0338-04-081 | ||
Length: | 0 | ||
Estimate: | $11,000 | ||
Actual: | |||
CCSJ: 0523-10-043 |
|||
District: | HOUSTON | Let Date: | Dec 2018 |
Highway: | FM 1488 | Let Status: | Actual |
Project ID: | C 523-10-43 | CSJ: | 0523-10-043 |
Description: | ADD RIGHT TURN LANE | Handling Code: | |
Limits From: | AT CARRIAGE HILLS | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $703,503 |
Length: | 0.1 | Actual | $619,717 |
Back... | Totals for 0523-10-043 | ||
Length: | 0.1 | ||
Estimate: | $703,503 | ||
Actual: | $619,717 | ||
CCSJ: 0912-37-234 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | CR | Let Status: | Tentative |
Project ID: | STP ( )FRS4 | CSJ: | 0912-37-234 |
Description: | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755879Y) | Handling Code: | XX |
Limits From: | NORTHPARK DRIVE IN PORTER @ UPRR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $250,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-37-234 | ||
Length: | 0 | ||
Estimate: | $250,000 | ||
Actual: | |||
CCSJ: 0912-37-235 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | CR | Let Status: | Tentative |
Project ID: | STP 2019(693)FRS2 | CSJ: | 0912-37-235 |
Description: | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755892M) | Handling Code: | XX |
Limits From: | NORTHPARK DRIVE IN NEW CANEY @ UPRR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $250,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-37-235 | ||
Length: | 0 | ||
Estimate: | $250,000 | ||
Actual: | |||
CCSJ: 0912-37-236 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | CR | Let Status: | Tentative |
Project ID: | STP 2019(693)FRS2 | CSJ: | 0912-37-236 |
Description: | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755882G) | Handling Code: | XX |
Limits From: | MARTIN DRIVE IN PORTER @ UPRR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $250,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-37-236 | ||
Length: | 0 | ||
Estimate: | $250,000 | ||
Actual: | |||
CCSJ: 1062-01-217 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | FM 1485 | Let Status: | Tentative |
Project ID: | ER 2019(127) | CSJ: | 1062-01-217 |
Description: | BRIDGE APPROACH SLAB REPAIR | Handling Code: | XX |
Limits From: | AT CANEY CREEK | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $135,560 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 1062-01-217 | ||
Length: | 0 | ||
Estimate: | $135,560 | ||
Actual: | |||
CCSJ: 1416-03-019 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | FM 1486 | Let Status: | Tentative |
Project ID: | CRX 1416-3-19 | CSJ: | 1416-03-019 |
Description: | REPLANK EXISTING RR CROSSING SURFACE | Handling Code: | XX |
Limits From: | DOBBIN ROAD @ BNSF RAILROAD | Fund Cat: | 10 |
Limits To: | DOT NUMBER 024319Y | ESTIMATE: | $55,360 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 1416-03-019 | ||
Length: | 0 | ||
Estimate: | $0 | ||
Actual: | TOTAL | ||
CCSJ: 1912-01-023 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | FM 2090 | Let Status: | Tentative |
Project ID: | ER 1802(638) | CSJ: | 1912-01-023 |
Description: | REPLACED TRAFFIC SIGNAL CABINET | Handling Code: | XX |
Limits From: | AT CROCKETT MARTIN RD | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $11,455 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 1912-01-023 | ||
Length: | 0 | ||
Estimate: | $11,455 | ||
Actual: | |||
CCSJ: 1912-02-014 |
|||
District: | HOUSTON | Let Date: | Mar 2019 |
Highway: | FM 2090 | Let Status: | Actual |
Project ID: | STP 2019(627) | CSJ: | 1912-02-014 |
Description: | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | Handling Code: | |
Limits From: | US 59L | Fund Cat: | 1 |
Limits To: | LIBERTY C/L | ESTIMATE: | $2,387,733 |
Length: | 3.7 | Actual | $2,298,814 |
Proposal Request Back... | Totals for 1912-02-014 | ||
Length: | 3.7 | ||
Estimate: | $2,387,733 | ||
Actual: | $2,298,814 | ||
CCSJ: 1912-02-015 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | FM 2090 | Let Status: | Tentative |
Project ID: | CRX 1912-2-15 | CSJ: | 1912-02-015 |
Description: | REPLANK EXISTING RR CROSSING SURFACE | Handling Code: | XX |
Limits From: | BU 59 @ UNION PACIFIC RAILROAD | Fund Cat: | 10 |
Limits To: | DOT NUMBER 755899K | ESTIMATE: | $30,080 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 1912-02-015 | ||
Length: | 0 | ||
Estimate: | $0 | ||
Actual: | TOTAL | ||
CCSJ: 2897-01-017 |
|||
District: | HOUSTON | Let Date: | Mar 2019 |
Highway: | FM 830 | Let Status: | Actual |
Project ID: | STP 2019(628) | CSJ: | 2897-01-017 |
Description: | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | Handling Code: | |
Limits From: | LAKE CONROE | Fund Cat: | 1 |
Limits To: | SH 75 | ESTIMATE: | $2,642,386 |
Length: | 6.0 | Actual | $2,483,807 |
Back... | Totals for 2897-01-017 | ||
Length: | 6 | ||
Estimate: | $2,642,386 | ||
Actual: | $2,483,807 | ||
CCSJ: 3538-01-035 |
|||
District: | HOUSTON | Let Date: | May 2019 |
Highway: | SH 242 | Let Status: | Approved |
Project ID: | STP 2019(952) | CSJ: | 3538-01-035 |
Description: | Widen Road - Add Lanes | Handling Code: | |
Limits From: | NEEDHAM DRIVE | Fund Cat: | 2M |
Limits To: | FM 1314 | ESTIMATE: | $40,989,584 |
Length: | 3.2 | Actual | $0 |
Back... | Totals for 3538-01-035 | ||
Length: | 3.2 | ||
Estimate: | $40,989,584 | ||
Actual: | |||
CCSJ: 3538-01-036 |
|||
District: | HOUSTON | Let Date: | Aug 2019 |
Highway: | SH 242 | Let Status: | Approved |
Project ID: | STP 2019(797) | CSJ: | 3538-01-036 |
Description: | Widen Road - Add Lanes | Handling Code: | |
Limits From: | WEST OF FM 1485 | Fund Cat: | 2M |
Limits To: | IH 69 | ESTIMATE: | $60,788,963 |
Length: | 7.2 | Actual | $0 |
Back... | Totals for 3538-01-036 | ||
Length: | 7.2 | ||
Estimate: | $60,788,963 | ||
Actual: | |||
CCSJ: 3538-01-052 |
|||
District: | HOUSTON | Let Date: | May 2019 |
Highway: | SH 242 | Let Status: | Approved |
Project ID: | STP 1902(124) | CSJ: | 3538-01-052 |
Description: | CONSTRUCT NEW SIGNAL AT GREAT OAKS DRIVE AND CLOSURE OF | Handling Code: | |
Limits From: | HARPERS WAY | Fund Cat: | 1 |
Limits To: | GREY OAKS DRIVE | ESTIMATE: | $441,491 |
Length: | 0.4 | Actual | $0 |
Back... | Totals for 3538-01-052 | ||
Length: | 0.4 | ||
Estimate: | $441,491 | ||
Actual: | |||
CCSJ: 3538-01-053 |
|||
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | SH 242 | Let Status: | Approved |
Project ID: | BR 1902(184) | CSJ: | 3538-01-053 |
Description: | REPLACE BEARING PADS (NBI# 121700353801008) | Handling Code: | |
Limits From: | AT UPRR | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $178,508 |
Length: | 0.0 | Actual | $0 |
District: | HOUSTON | Let Date: | Jul 2019 |
Highway: | FM 1485 | Let Status: | Approved |
Project ID: | BR 1902(184) | CSJ: | 1062-01-216 |
Description: | REPLACE BEARING PADS (NBI# 121700106201015) | Handling Code: | |
Limits From: | AT CANEY CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $129,116 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 3538-01-053 | ||
Length: | 0 | ||
Estimate: | $307,624 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |