Detail Letting Schedule for Navarro County (FY 2019)

Last Update: Tuesday, April 24, 2018
Navarro County (FY 2019)

CCSJ: 0092-13-024

District:DALLASLet Date:Nov 2018
Highway:BI 45-FLet Status:Tentative
Project ID:BR ( )CSJ:0092-13-024
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:SOUTHBOUND AT DRAWFund Cat:6
Limits To:.ESTIMATE:$2,332,628
Length:0.2Actual$0
 
District:DALLASLet Date:Nov 2018
Highway:BI 45-FLet Status:Tentative
Project ID:BR ( )CSJ:0092-13-025
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:SOUTHBOUND AT BRIAR CREEKFund Cat:6
Limits To:.ESTIMATE:$2,217,176
Length:0.3Actual$0
 
District:DALLASLet Date:Nov 2018
Highway:BI 45-FLet Status:Tentative
Project ID:BR ( )CSJ:0092-13-026
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:NORTHBOUND AT DRAWFund Cat:6
Limits To:.ESTIMATE:$2,229,453
Length:0.2Actual$0
 
District:DALLASLet Date:Nov 2018
Highway:BI 45-FLet Status:Tentative
Project ID:BR ( )CSJ:0092-13-027
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:NORTHBOUND AT BRIAR CREEKFund Cat:6
Limits To:.ESTIMATE:$2,313,286
Length:0.3Actual$0
 
Back...
Totals for 0092-13-024
Length:1
Estimate:$9,092,543
Actual:

CCSJ: 0121-08-019

District:DALLASLet Date:Oct 2018
Highway:FM 55Let Status:Tentative
Project ID:STP ( )CSJ:0121-08-019
Description:RESTORE EXISTING PAVEMENT AND ADD SHOULDERSHandling
Code:
 
Limits From:SH 31Fund Cat:1
Limits To:3RD ST IN BLOOMING GROVEESTIMATE:$13,794,087
Length:9.8Actual$0
 
Back...
Totals for 0121-08-019
Length:9.8
Estimate:$13,794,087
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract