Detail Letting Schedule for Trinity County (FY 2019)
Trinity County (FY 2019) |
CCSJ: 0319-01-067 |
|||
District: | LUFKIN | Let Date: | Nov 2018 |
Highway: | SH 94 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0319-01-067 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: | |
Limits From: | SH 19 | Fund Cat: | 1 |
Limits To: | US 287 | ESTIMATE: | $650,624 |
Length: | 16.5 | Actual | $0 |
Back... | Totals for 0319-01-067 | ||
---|---|---|---|
Length: | 16.5 | ||
Estimate: | $650,624 | ||
Actual: | |||
CCSJ: 0341-01-029 |
|||
District: | LUFKIN | Let Date: | May 2019 |
Highway: | US 287 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0341-01-029 |
Description: | MILLED EDGELINE AND CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.372 MI WEST OF FM 2262 | Fund Cat: | 8 |
Limits To: | POLK COUNTY LINE | ESTIMATE: | $90,280 |
Length: | 8.3 | Actual | $0 |
Back... | Totals for 0341-01-029 | ||
Length: | 8.3 | ||
Estimate: | $0 | ||
Actual: | TOTAL | ||
CCSJ: 0930-01-028 |
|||
District: | LUFKIN | Let Date: | Nov 2018 |
Highway: | FM 355 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0930-01-028 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: | |
Limits From: | US 287 | Fund Cat: | 1 |
Limits To: | FM 356 | ESTIMATE: | $497,695 |
Length: | 14.0 | Actual | $0 |
Back... | Totals for 0930-01-028 | ||
Length: | 14 | ||
Estimate: | $497,695 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |