Detail Letting Schedule for Bandera County (FY 2020)

Last Update: Thursday, July 02, 2020

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Bandera County (FY 2020)

CCSJ: 0855-04-032

District:SAN ANTONIOLet Date:Aug 2020
Highway:RM 337Let Status:Approved
Project ID:BR 2B20(064)CSJ:0855-04-032
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT MILL CREEKFund Cat:1
Limits To:.ESTIMATE:$1,499,096
Length:0.2Actual$0
 
Proposal Request
Back...
Totals for 0855-04-032
Length:0.2
Estimate:$1,499,096
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract