Detail Letting Schedule for Gray County (FY 2020)

Last Update: Tuesday, August 13, 2024

Bid Tabulations Dashboard

This report will no longer be updated, please access links on the Contract Letting page.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Gray County (FY 2020)

CCSJ: 0275-11-083

District:AMARILLOLet Date:Dec 2019
Highway:IH 40Let Status:Tentative
Project ID:NH ( )CSJ:0275-11-083
Description:CRCP REPAIR, OVERLAY AND BRIDGE RAIL REPLACEMENT (EBL ONLY)Handling
Code:
 
Limits From:DONLEY COUNTY LINEFund Cat:1
Limits To:0.5 MILES WEST OF ALANREEDESTIMATE:$2,620,000
Length:5.7Actual$0
 
District:AMARILLOLet Date:Dec 2019
Highway:IH 40Let Status:Tentative
Project ID:NH ( )CSJ:0275-08-040
Description:CRCP REPAIR AND ACP OVERLAY (EBL ONLY)Handling
Code:
 
Limits From:0.5 MILES EAST OF SH 70Fund Cat:1
Limits To:GRAY COUNTY LINEESTIMATE:$1,470,000
Length:1.8Actual$0
 
District:AMARILLOLet Date:Dec 2019
Highway:IH 40Let Status:Tentative
Project ID:NH ( )CSJ:0275-09-029
Description:CRCP REPAIR AND ACP OVERLAY (EBL ONLY)Handling
Code:
 
Limits From:DONLEY COUNTY LINEFund Cat:1
Limits To:DONLEY COUNTY LINEESTIMATE:$572,000
Length:0.6Actual$0
 
District:AMARILLOLet Date:Dec 2019
Highway:IH 40Let Status:Tentative
Project ID:NH ( )CSJ:0275-10-032
Description:CRCP REPAIR AND ACP OVERLAY (EBL ONLY)Handling
Code:
 
Limits From:GRAY COUNTY LINEFund Cat:1
Limits To:GRAY COUNTY LINEESTIMATE:$1,334,000
Length:2.2Actual$0
 
Award Status
Back...
Totals for 0275-11-083
Length:10.3
Estimate:$5,996,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract