Detail Letting Schedule for Gray County (FY 2020)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Gray County (FY 2020) |
CCSJ: 0275-11-083 |
|||
District: | AMARILLO | Let Date: | Dec 2019 |
Highway: | IH 40 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0275-11-083 |
Description: | CRCP REPAIR, OVERLAY AND BRIDGE RAIL REPLACEMENT (EBL ONLY) | Handling Code: | |
Limits From: | DONLEY COUNTY LINE | Fund Cat: | 1 |
Limits To: | 0.5 MILES WEST OF ALANREED | ESTIMATE: | $2,620,000 |
Length: | 5.7 | Actual | $0 |
District: | AMARILLO | Let Date: | Dec 2019 |
Highway: | IH 40 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0275-08-040 |
Description: | CRCP REPAIR AND ACP OVERLAY (EBL ONLY) | Handling Code: | |
Limits From: | 0.5 MILES EAST OF SH 70 | Fund Cat: | 1 |
Limits To: | GRAY COUNTY LINE | ESTIMATE: | $1,470,000 |
Length: | 1.8 | Actual | $0 |
District: | AMARILLO | Let Date: | Dec 2019 |
Highway: | IH 40 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0275-09-029 |
Description: | CRCP REPAIR AND ACP OVERLAY (EBL ONLY) | Handling Code: | |
Limits From: | DONLEY COUNTY LINE | Fund Cat: | 1 |
Limits To: | DONLEY COUNTY LINE | ESTIMATE: | $572,000 |
Length: | 0.6 | Actual | $0 |
District: | AMARILLO | Let Date: | Dec 2019 |
Highway: | IH 40 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0275-10-032 |
Description: | CRCP REPAIR AND ACP OVERLAY (EBL ONLY) | Handling Code: | |
Limits From: | GRAY COUNTY LINE | Fund Cat: | 1 |
Limits To: | GRAY COUNTY LINE | ESTIMATE: | $1,334,000 |
Length: | 2.2 | Actual | $0 |
Award Status Back... | Totals for 0275-11-083 | ||
---|---|---|---|
Length: | 10.3 | ||
Estimate: | $5,996,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |