Detail Letting Schedule for Hill County (FY 2020)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Hill County (FY 2020) |
CCSJ: 0014-07-102 |
|||
District: | WACO | Let Date: | Mar 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2020(753) | CSJ: | 0014-07-102 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | MCLENNAN CO LINE | Fund Cat: | 11 |
Limits To: | SH 81 | ESTIMATE: | $2,787,567 |
Length: | 9.3 | Actual | $2,826,491 |
District: | WACO | Let Date: | Mar 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2020(753) | CSJ: | 0014-08-086 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 2114 | Fund Cat: | 11 |
Limits To: | HILL COUNTY LINE | ESTIMATE: | $1,118,242 |
Length: | 2.0 | Actual | $873,208 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0014-07-102 | ||
---|---|---|---|
Length: | 11.3 | ||
Estimate: | $3,905,809 | ||
Actual: | $3,699,699 | ||
CCSJ: 0014-07-104 |
|||
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0014-07-104 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | IH 35 @SH 81 | Fund Cat: | 8 |
Limits To: | MCLENNAN CO LINE | ESTIMATE: | $329,820 |
Length: | 9.3 | Actual | $143,859 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0014-08-087 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | HILL COUNTY LINE | Fund Cat: | 8 |
Limits To: | E HILLTOP STREET | ESTIMATE: | $206,617 |
Length: | 10.3 | Actual | $155,692 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0014-09-103 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | E HILLTOP STREET | Fund Cat: | 8 |
Limits To: | BU 77 | ESTIMATE: | $46,673 |
Length: | 2.5 | Actual | $35,513 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0014-24-063 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | IH 35 E/W SPLIT | Fund Cat: | 8 |
Limits To: | IH 35 @ SH 81 | ESTIMATE: | $89,080 |
Length: | 6.3 | Actual | $78,277 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-01-247 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | BU 77 | Fund Cat: | 8 |
Limits To: | S OF OLD TEMPLE ROAD | ESTIMATE: | $279,322 |
Length: | 22.5 | Actual | $218,880 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-02-062 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | S OF OLD TEMPLE RD | Fund Cat: | 8 |
Limits To: | FALL COUNTY LINE | ESTIMATE: | $80,320 |
Length: | 4.2 | Actual | $61,048 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-03-041 |
Description: | SAFETY ASSURANCE REVIEWS | Handling Code: | |
Limits From: | MCLENNAN COUNTY LINE | Fund Cat: | 8 |
Limits To: | BELL COUNTY LINE | ESTIMATE: | $42,678 |
Length: | 1.9 | Actual | $32,581 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-04-089 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FALLS COUNTY LINE | Fund Cat: | 8 |
Limits To: | S OF SL 363 IN TEMPLE | ESTIMATE: | $193,538 |
Length: | 9.9 | Actual | $147,080 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-06-085 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | S OF IH 14 | Fund Cat: | 8 |
Limits To: | AMITY RD | ESTIMATE: | $92,254 |
Length: | 5.2 | Actual | $72,555 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-07-083 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AMITY ROAD | Fund Cat: | 8 |
Limits To: | WILLIAMSON COUNTY ROAD | ESTIMATE: | $184,036 |
Length: | 9.8 | Actual | $138,699 |
District: | WACO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2020(526) | CSJ: | 0015-14-127 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | S OF SL 363 IN TEMPLE | Fund Cat: | 8 |
Limits To: | S OF IH 14 | ESTIMATE: | $114,538 |
Length: | 10.6 | Actual | $111,554 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0014-07-104 | ||
Length: | 92.5 | ||
Estimate: | $1,658,876 | ||
Actual: | $1,195,738 | ||
CCSJ: 0014-07-105 |
|||
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0014-07-105 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | COUNTY LINE ROAD | Fund Cat: | 8 |
Limits To: | SH 81 | ESTIMATE: | $212,807 |
Length: | 9.3 | Actual | $291,419 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0014-07-106 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | COUNTY LINE ROAD | Fund Cat: | 8 |
Limits To: | SH 81 | ESTIMATE: | $381,449 |
Length: | 9.2 | Actual | $431,166 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0014-08-089 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | HILLTOP ROAD | Fund Cat: | 8 |
Limits To: | COUNTY LINE ROAD | ESTIMATE: | $400,213 |
Length: | 10.3 | Actual | $457,200 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0014-09-104 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | BU 77-L | Fund Cat: | 8 |
Limits To: | HILLTOP ROAD | ESTIMATE: | $70,809 |
Length: | 2.5 | Actual | $82,070 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0014-24-064 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 81 | Fund Cat: | 8 |
Limits To: | IH 35 E/W SPLIT | ESTIMATE: | $729,594 |
Length: | 6.3 | Actual | $826,776 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0015-01-250 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 2063 | Fund Cat: | 8 |
Limits To: | BU77 | ESTIMATE: | $1,356,734 |
Length: | 22.5 | Actual | $1,658,291 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0015-06-086 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AMITY ROAD | Fund Cat: | 8 |
Limits To: | FM 436 | ESTIMATE: | $170,912 |
Length: | 5.2 | Actual | $197,090 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0015-07-085 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | WILLIAMSON COUNTY LINE | Fund Cat: | 8 |
Limits To: | AMITY ROAD | ESTIMATE: | $671,185 |
Length: | 9.8 | Actual | $802,009 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0015-14-128 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 436 | Fund Cat: | 8 |
Limits To: | 0.25 MI N OF IH 14 | ESTIMATE: | $341,389 |
Length: | 0.4 | Actual | $416,104 |
District: | WACO | Let Date: | Aug 2020 |
Highway: | SH 6 | Let Status: | Actual |
Project ID: | STP 2B20(189)HES | CSJ: | 0258-09-150 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.01 MI W OF IH 35 | Fund Cat: | 8 |
Limits To: | 0.01 MI E OF IH 35 | ESTIMATE: | $109,407 |
Length: | 0.1 | Actual | $133,184 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0014-07-105 | ||
Length: | 75.6 | ||
Estimate: | $4,444,499 | ||
Actual: | $5,295,309 | ||
CCSJ: 0014-23-038 |
|||
District: | WACO | Let Date: | Jul 2020 |
Highway: | IH 35W | Let Status: | Actual |
Project ID: | C 14-23-38 | CSJ: | 0014-23-038 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | IH 35 E/W SPLIT | Fund Cat: | 8 |
Limits To: | JOHNSON COUNTY LINE | ESTIMATE: | $3,373,708 |
Length: | 0.0 | Actual | $2,336,016 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0014-23-038 | ||
Length: | 0 | ||
Estimate: | $3,373,708 | ||
Actual: | $2,336,016 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |