This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Bryan District (FY 2020) |
Brazos | Burleson | Freestone | Grimes | Leon | Madison | Milam | Robertson | Washington | | |||||||
Brazos County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0116-04-104 | SH 21 | Tentative | May 2020 | $332,814 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0599-01-009 | SH 308 | Tentative | Sep 2019 | $500,000 | 2U | CONSTRUCT SIDEWALKS & SHARED USE PATH | 0.0 |
2399-01-074 | FM 2818 | Tentative | Jun 2020 | $39,822,037 | 2U | WIDEN NON-FREEWAY FACILITY CONSISTING OF GRADING, BASE, | 0.0 |
0917-29-133 | CS | Tentative | Jun 2020 | $1,194,040 | 3 | CONCRETE SIDEWALKS AND BIKE LANES | 0.0 |
0049-12-105 | SH 6 | Tentative | Oct 2019 | $974,516 | 6 | Bridge Maintenance | 0.0 |
0117-09-002 | US 190 | Tentative | May 2020 | $182,511 | 8 | INSTALL INTERSECTION FLASHING BEACON | 0.0 |
0049-12-121 | US 190 | Tentative | May 2020 | $1,027,303 | 6 | PAINT STEEL SURFACES | 0.0 |
3138-01-029 | FM 2347 | Tentative | May 2020 | $1,009,813 | 8 | INSTALL RAISED MEDIAN | 0.0 |
0212-03-066 | SH 30 | Tentative | Dec 2019 | $300,704 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0049-12-115 | SH 6 | Tentative | Jun 2020 | $1,080,783 | 3 | CONC SHARED USE PATH E FRONTAGE RD | 0.0 |
Burleson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0917-30-054 | CR | Tentative | Nov 2019 | $1,090,000 | 6 | REPLACE EXISTING BRIDGE CONSISTING OF GRADING, STRUCTURES, | 0.0 |
0858-03-019 | FM 908 | Tentative | May 2020 | $4,457,904 | 8 | SAFETY TREAT FIXED OBJECTS | 0.0 |
Freestone County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0166-03-033 | SH 75 | Tentative | May 2020 | $6,594,668 | 8 | SAFETY TREAT FIXED OBJECTS | 0.0 |
0917-20-039 | CR | Tentative | Apr 2020 | $430,000 | 6 | RPLACE EXISTING BRIDGE CONSISTING OF GRADING, STRUCTURES, | 0.0 |
0166-02-044 | SH 75 | Tentative | Oct 2019 | $7,693,992 | 1 | Preventive Maintenance | 0.0 |
0459-01-079 | FM 488 | Tentative | Apr 2020 | $1,772,089 | 8 | SAFETY TREAT FIXED OBJECTS | 0.0 |
Grimes County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2827-01-011 | FM 2 | Tentative | Apr 2020 | $9,079 | 10 | REPAIR FRONT SLOPE EROSION | 0.0 |
0917-17-070 | CR | Tentative | May 2020 | $165,000 | 6 | REPLACE EXISTING BRIDGE CONSISTING OF GRADING, STRUCTURES, | 0.0 |
0050-03-106 | SH 6 | Tentative | Apr 2020 | $135,355 | 10 | Emergency Relief | 0.0 |
0050-03-105 | SH 6 | Tentative | Apr 2020 | $157,643 | 10 | Emergency Relief | 0.0 |
2827-01-012 | FM 2 | Tentative | Apr 2020 | $23,405 | 10 | CULVERT AND SCOUR REPAIR | 0.0 |
Leon County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0166-04-043 | SH 75 | Tentative | Sep 2019 | $2,500,000 | 1 | REPLACE CULVERT AT MILL BRANCH CREEK | 0.0 |
1145-02-022 | FM 811 | Tentative | Nov 2019 | $9,000,000 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF GRADING, STRUCTURES | 0.0 |
Madison County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0552-02-027 | FM 978 | Tentative | Feb 2020 | $330,000 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0117-05-054 | SH 21 | Tentative | Oct 2019 | $1,275,000 | 11 | WIDEN BRIDGE | 0.0 |
Milam County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0204-06-060 | US 79 | Tentative | Nov 2019 | $5,118,000 | 3 | SIDEWALK, RAMPS, BENCHES & LIGHT'G | 0.0 |
Robertson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0262-06-032 | FM 391 | Tentative | Apr 2020 | $600,000 | 6 | REPLACE EXISTING BRIDGE CONSISTING OF GRADING, STRUCTURES, | 0.0 |
Washington County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0186-06-089 | US 290 | Tentative | Apr 2020 | $196,645 | 10 | Emergency Relief | 0.0 |
0114-09-080 | US 290 | Tentative | Jan 2020 | $2,650,000 | 6 | DECK REHABILITATION | 0.0 |
0114-09-078 | US 290 | Tentative | May 2020 | $575,412 | 8 | INSTALL INTERSECTION FLASHING BEACON | 0.0 |
|