Letting Schedule for San Angelo District (FY 2020)

Last Update: Tuesday, July 07, 2020

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

San Angelo District (FY 2020)
Crockett | Edwards | Glasscock | Kimble | Reagan | Runnels | Tom Green |

Crockett County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0140-11-046IH 10ActualApr 2020$3,098,6611PREVENTIVE MAINTENANCE0.0

Edwards County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0235-02-047SH 55ApprovedJul 2020$300,8608INSTALL/REPLACE SIGNS0.0

Glasscock County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0558-07-019RM 33ActualFeb 2020$2,442,1181PREVENTIVE MAINTENANCE0.0
0494-08-015SH 137ApprovedAug 2020$30,651,5341SURFACING/ROADWAY RESTORATION2.5
0463-04-024SH 158ApprovedAug 2020$29,138,51111HIGHWAY IMPROVEMENT10.0

Kimble County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0112-01-019US 290ActualJun 2020$5,110,59511HAZARD ELIMINATION & SAFETY6.0
0141-09-071IH 10ApprovedAug 2020$2,484,8208HAZARD ELIMINATION & SAFETY0.0
0036-01-015US 83ActualDec 2019$13,843,5981PREVENTIVE MAINTENANCE0.0

Reagan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0076-08-027US 67ActualMar 2020$25,496,7891HIGHWAY IMPROVEMENT7.5
0558-09-037SH 137ActualDec 2019$5,878,35711PREVENTIVE MAINTENANCE0.0

Runnels County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0907-13-012CRActualJun 2020$2,414,9846BRIDGE REPLACEMENT8.0

Tom Green County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0907-00-222VAActualMay 2020$972,4478HIGHWAY IMPROVEMENT0.0
0907-00-186VAActualJan 2020$1,834,0181HIGHWAY IMPROVEMENT0.0
0077-06-101US 67ActualJun 2020$991,5358HAZARD ELIMINATION & SAFETY5.0
0907-24-048CSApprovedJul 2020$2,272,8523CONSTRUCT PEDESTRIAN INFRASTRUCTURE0.0
0907-00-221VAActualFeb 2020$187,7738HIGHWAY IMPROVEMENT0.0
0907-00-201VAApprovedAug 2020$4,359,16510CONSTRUCT PEDESTRIAN INFRASTRUCTURE0.0
0907-00-225VAApprovedAug 2020$2,277,8838HAZARD ELIMINATION & SAFETY0.0
0907-00-174VAActualOct 2019$1,459,18811TRAFFIC SIGNAL IMPROVEMENTS5.0
2410-01-011FM 2105ActualMar 2020$18,366,6401HIGHWAY IMPROVEMENT9.5
0907-00-224VAApprovedAug 2020$3,255,2828HAZARD ELIMINATION & SAFETY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract