The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

July, 2020 (FY 2020)(see Descriptions)
SEP 2019 | OCT 2019 | NOV 2019 | DEC 2019 | JAN 2020 | FEB 2020 | MAR 2020 | APR 2020 | MAY 2020 | JUN 2020 | JUL 2020 | AUG 2020 |
CCSJCounty/
District
HighwayLet StatusContract
Cost
Hndl
Code
Links
0911-00-103Angelina/
Lufkin
VAApproved$2,544,477  
0911-00-082Angelina/
Lufkin
VAApproved$2,022,964  
0573-01-039Bastrop/
Austin
SH 304Approved$8,642,475  
1186-02-020Bastrop/
Austin
FM 969Approved$3,190,151  
0100-08-095Bee/
Corpus Christi
US 181Approved$17,204,769  
0231-03-147Bell/
Waco
IH 14Approved$3,110,819  
0025-02-215Bexar/
San Antonio
IH 10Approved$155,658,878  
0915-12-544Bexar/
San Antonio
CSApproved$7,323,351LC 
0179-03-034Brazoria/
Houston
SH 35Approved$5,899,839  
3138-01-029Brazos/
Bryan
FM 2347Approved$2,515,560  
0255-04-099Brooks/
Pharr
US 281Approved$8,315,981  
0144-03-036Calhoun/
Yoakum
US 87Approved$8,276,423  
0684-03-022Cameron/
Pharr
FM 1732Approved$6,172,166  
0919-00-080Cass/
Atlanta
VAApproved$1,518,497  
0681-08-024Clay/
Wichita Falls
FM 174Approved$274,145  
1735-01-017Collin/
Dallas
FM 1778Approved$7,410,898  
0216-01-057Comal/
San Antonio
SL 337Approved$14,197,957  
0231-02-064Coryell/
Waco
BU 190EApproved$1,014,126  
0020-02-019Culberson/
El Paso
US 90Approved$767,820  
0918-47-299Dallas/
Dallas
VAApproved$2,903,090  
0918-00-305Dallas/
Dallas
VAApproved$4,089,191  
0906-00-190Ector/
Odessa
VAApproved$2,262,821  
0906-00-230Ector/
Odessa
VAApproved$2,093,361  
0228-06-086Ector/
Odessa
US 385Approved$25,550,438  
0906-00-191Ector/
Odessa
VAApproved$2,638,798  
0235-02-047Edwards/
San Angelo
SH 55Approved$300,860  
2552-03-049El Paso/
El Paso
SL 375Approved$72,276,375  
2121-05-051El Paso/
El Paso
IH 10Approved$5,397,225  
0924-06-544El Paso/
El Paso
VAApproved$2,813,772LC 
2121-02-171El Paso/
El Paso
IH 10Approved$653,428  
0924-06-064El Paso/
El Paso
CSApproved$1,482,914LC 
0833-06-019Falls/
Waco
FM 2027Approved$3,404,005  
1482-01-014Fannin/
Paris
FM 1550Approved$4,051,421  
0271-10-012Fort Bend/
Houston
US 90Approved$472,109  
0459-01-079Freestone/
Bryan
FM 488Approved$1,422,021  
0166-03-033Freestone/
Bryan
SH 75Approved$4,244,866  
0115-01-014Guadalupe/
San Antonio
FM 20Approved$3,531,861  
0905-12-044Hale/
Lubbock
CRApproved$391,373  
1685-03-058Harris/
Houston
FM 1960Approved$130,519,614  
1685-01-109Harris/
Houston
FM 1960Approved$864,133  
3256-03-097Harris/
Houston
SL 8Approved$767,517  
3510-06-025Harris/
Houston
SH 99Approved$4,389,514  
0495-08-127Harrison/
Atlanta
IH 20Approved$4,082,600  
0495-08-129Harrison/
Atlanta
IH 20Approved$354,300  
0914-33-079Hays/
Austin
CSApproved$429,847  
0016-02-149Hays/
Austin
IH 35Approved$12,907,781  
0458-01-025Henderson/
Tyler
FM 59Approved$1,763,399  
0039-04-129Hidalgo/
Pharr
BU 83-SApproved$2,399,526  
0014-23-038Hill/
Waco
IH 35WApproved$3,373,708  
0911-28-039Houston/
Lufkin
CRApproved$819,528  
0002-07-054Hudspeth/
El Paso
IH 10Approved$2,682,251  
0913-18-035Jackson/
Yoakum
CRApproved$564,609  
0920-00-128Jefferson/
Beaumont
VAApproved$1,603,233  
0902-50-125Johnson/
Ft Worth
VAApproved$2,151,274LC 
0902-50-131Johnson/
Ft Worth
VAApproved$5,681,010  
0133-03-038Knox/
Childress
US 82Approved$12,967,967  
0045-09-105Lamar/
Paris
BU 82-HApproved$1,062,050  
0769-02-033Lamar/
Paris
FM 906Approved$2,772,581  
0913-29-048Lavaca/
Yoakum
CRApproved$377,833  
0920-00-129Liberty/
Beaumont
VAApproved$1,454,102  
0909-40-075Limestone/
Waco
CRApproved$1,451,255  
0071-03-041Mason/
Austin
US 87Approved$858,902  
0204-06-060Milam/
Bryan
US 79Approved$5,219,673  
0013-05-063Montague/
Wichita Falls
US 81Approved$523,855  
0523-08-007Montgomery/
Houston
FM 1488Approved$31,561,621  
0883-02-087Orange/
Beaumont
FM 105Approved$1,210,853  
0249-08-042Palo Pinto/
Ft Worth
US 281Approved$26,057,055  
0063-03-065Panola/
Atlanta
US 59Approved$8,796,077  
0008-03-119Parker/
Ft Worth
US 180Approved$4,220,000LC 
0275-01-215Potter/
Amarillo
IH 40Approved$4,492,234  
0901-27-052Red River/
Paris
VAApproved$678,333  
0074-03-047San Patricio/
Corpus Christi
IH 37Approved$2,183,044  
0074-05-098San Patricio/
Corpus Christi
IH 37Approved$80,412,696  
0908-19-026Scurry/
Abilene
CSApproved$1,980,458  
0910-16-151Smith/
Tyler
VAApproved$156,744  
0910-00-127Smith/
Tyler
VAApproved$4,115,570  
0011-09-073Stephens/
Brownwood
US 180Approved$1,555,067  
0353-03-100Tarrant/
Ft Worth
SH 114Approved$35,077,363  
0902-90-175Tarrant/
Ft Worth
VAApproved$1,600,000LC 
1068-01-228Tarrant/
Ft Worth
IH 30Approved$536,860  
0008-13-234Tarrant/
Ft Worth
IH 20Approved$1,728,318  
0172-06-094Tarrant/
Ft Worth
SS 280Approved$3,594,158  
0908-00-101Taylor/
Abilene
VAApproved$294,709  
0907-24-048Tom Green/
San Angelo
CSApproved$2,272,852LC 
0114-01-063Travis/
Austin
US 290Approved$2,140,194  
0914-00-449Travis/
Austin
VAApproved$572,928  
1539-02-026Travis/
Austin
FM 1626Approved$11,351,274  
0911-40-029Trinity/
Lufkin
VAApproved$805,747  
0024-02-075Uvalde/
San Antonio
US 90Approved$2,481,352  
0088-05-104Victoria/
Yoakum
US 59Approved$6,598,470  
0903-00-112Wichita/
Wichita Falls
VAApproved$562,654  
0903-00-116Wichita/
Wichita Falls
VAApproved$904,439  
0903-00-113Wichita/
Wichita Falls
VAApproved$1,003,636  
0204-01-068Williamson/
Austin
US 79Approved$2,247,852  
0015-08-147Williamson/
Austin
IH 35Approved$50,237,775  
0151-05-115Williamson/
Austin
US 183Approved$15,200,000LC 

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract