Detail Letting Schedule for Liberty County (FY 2020)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Liberty County (FY 2020) |
CCSJ: 0028-04-078 |
|||
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0028-04-078 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT LAYL DR | Fund Cat: | 8 |
Limits To: | 0.1 MI E OF LAYL DR | ESTIMATE: | $200,985 |
Length: | 0.2 | Actual | $118,301 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0028-06-085 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT TURNER RD | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $36,406 |
Length: | 0.2 | Actual | $43,328 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0064-08-061 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT RE 255 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $44,343 |
Length: | 0.2 | Actual | $53,352 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0065-04-084 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 722 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $35,616 |
Length: | 0.2 | Actual | $42,153 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0065-04-085 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 721 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $35,565 |
Length: | 0.2 | Actual | $42,064 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0065-05-151 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT OLD EVADALE RD | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $36,392 |
Length: | 0.2 | Actual | $42,854 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | US 69 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0200-10-084 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT ELLIS DR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $25,134 |
Length: | 0.2 | Actual | $31,569 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 62 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0243-03-066 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT COHENOUR RD | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $20,876 |
Length: | 0.2 | Actual | $26,196 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 87 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0305-03-043 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT FM 1004 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $47,813 |
Length: | 0.2 | Actual | $60,769 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 87 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0305-07-070 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT ABES DR. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $23,526 |
Length: | 0.2 | Actual | $29,510 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 124 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0368-04-031 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT LABELLE RD | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $21,180 |
Length: | 0.1 | Actual | $26,509 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 146 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0389-01-043 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT FM 1413 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $31,629 |
Length: | 0.2 | Actual | $39,882 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 12 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0499-03-062 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT EVANGELINE LN | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $30,228 |
Length: | 0.2 | Actual | $38,106 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 321 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0593-01-125 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 668 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $25,642 |
Length: | 0.2 | Actual | $32,289 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 321 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0593-01-127 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 676 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $23,629 |
Length: | 0.2 | Actual | $29,833 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 327 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0602-01-047 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT S 21ST ST | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $27,309 |
Length: | 0.2 | Actual | $34,417 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 92 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0703-01-064 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 4565 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $28,293 |
Length: | 0.2 | Actual | $35,747 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 105 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0710-02-067 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT FM 2802 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $35,091 |
Length: | 0.2 | Actual | $44,573 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 1960 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0762-01-033 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 608 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $22,266 |
Length: | 0.2 | Actual | $28,018 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 1409 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0762-02-048 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 470 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $22,752 |
Length: | 0.2 | Actual | $27,794 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 787 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0813-02-040 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT FM 2798 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $24,704 |
Length: | 0.2 | Actual | $30,947 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | SH 105 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 0951-01-067 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT CR 2235 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $25,125 |
Length: | 0.2 | Actual | $31,791 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 1442 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 1284-01-076 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT LISTON RD | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $26,279 |
Length: | 0.2 | Actual | $33,196 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 1442 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 1284-01-077 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT JAPANESE LN | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $25,564 |
Length: | 0.2 | Actual | $32,192 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 3247 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 1284-02-019 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT ROSEWOOD DR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $21,618 |
Length: | 0.2 | Actual | $27,159 |
District: | BEAUMONT | Let Date: | Oct 2019 |
Highway: | FM 1293 | Let Status: | Actual |
Project ID: | STP 2020(138)HES | CSJ: | 1947-02-015 |
Description: | INSTALL/UPGRADE ROADWAY LIGHTING | Handling Code: | |
Limits From: | AT FM 1003 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $28,037 |
Length: | 0.2 | Actual | $35,549 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0028-04-078 | ||
---|---|---|---|
Length: | 5.1 | ||
Estimate: | $926,002 | ||
Actual: | $1,018,097 | ||
CCSJ: 0177-03-103 |
|||
District: | BEAUMONT | Let Date: | Feb 2020 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | NH 2020(591) | CSJ: | 0177-03-103 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | SL 573 (SOUTH) | Fund Cat: | 11 |
Limits To: | SL 573 (NORTH) | ESTIMATE: | $2,748,971 |
Length: | 3.6 | Actual | $2,133,678 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0177-03-103 | ||
Length: | 3.6 | ||
Estimate: | $2,748,971 | ||
Actual: | $2,133,678 | ||
CCSJ: 0593-01-122 |
|||
District: | BEAUMONT | Let Date: | Apr 2020 |
Highway: | SH 321 | Let Status: | Actual |
Project ID: | STP 2020(782)HES | CSJ: | 0593-01-122 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 105 | Fund Cat: | 8 |
Limits To: | 0.30 MI S OF FM 1008 | ESTIMATE: | $1,129,194 |
Length: | 0.0 | Actual | $1,074,621 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0593-01-122 | ||
Length: | 0 | ||
Estimate: | $1,129,194 | ||
Actual: | $1,074,621 | ||
CCSJ: 0813-01-105 |
|||
District: | BEAUMONT | Let Date: | May 2020 |
Highway: | FM 787 | Let Status: | Actual |
Project ID: | ER 1802(450) | CSJ: | 0813-01-105 |
Description: | EMERGENCY RELIEF | Handling Code: | XX |
Limits From: | 0.25 MI W OF TRINITY RIVER, EAST | Fund Cat: | 10 |
Limits To: | 0.50 MI EAST | ESTIMATE: | $1,995,740 |
Length: | 0.5 | Actual | $0 |
Back... | Totals for 0813-01-105 | ||
Length: | 0.5 | ||
Estimate: | $1,995,740 | ||
Actual: | |||
CCSJ: 0920-00-129 |
|||
District: | BEAUMONT | Let Date: | Jul 2020 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 920-00-129 | CSJ: | 0920-00-129 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $1,448,102 |
Length: | 0.0 | Actual | $1,556,025 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0920-00-129 | ||
Length: | 0 | ||
Estimate: | $1,448,102 | ||
Actual: | $1,556,025 | ||
CCSJ: 0920-02-091 |
|||
District: | BEAUMONT | Let Date: | Aug 2020 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2020(868) | CSJ: | 0920-02-091 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | AT GAYLOR CREEK 1.1 MI NE | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $750,219 |
Length: | 0.0 | Actual | $777,586 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0920-02-091 | ||
Length: | 0 | ||
Estimate: | $750,219 | ||
Actual: | $777,586 | ||
CCSJ: 0920-02-094 |
|||
District: | BEAUMONT | Let Date: | Sep 2019 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2019(760) | CSJ: | 0920-02-094 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | CR 2142 AT MENARD CRK | Fund Cat: | 6 |
Limits To: | (STR AA0612002) | ESTIMATE: | $1,314,354 |
Length: | 0.1 | Actual | $1,811,810 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0920-02-094 | ||
Length: | 0.1 | ||
Estimate: | $1,314,354 | ||
Actual: | $1,811,810 | ||
CCSJ: 0920-02-095 |
|||
District: | BEAUMONT | Let Date: | May 2020 |
Highway: | CS | Let Status: | Actual |
Project ID: | ER 1902(430) | CSJ: | 0920-02-095 |
Description: | EMERGENCY RELIEF | Handling Code: | XX |
Limits From: | AT CR 319 | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $11,133 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0920-02-095 | ||
Length: | 0 | ||
Estimate: | $11,133 | ||
Actual: | |||
CCSJ: 1912-03-010 |
|||
District: | BEAUMONT | Let Date: | May 2020 |
Highway: | FM 2090 | Let Status: | Actual |
Project ID: | ER 1802(236) | CSJ: | 1912-03-010 |
Description: | EMERGENCY RELIEF | Handling Code: | XX |
Limits From: | 0.40 MI W OF FM 1010 | Fund Cat: | 10 |
Limits To: | FM 1010 | ESTIMATE: | $455,485 |
Length: | 0.4 | Actual | $0 |
Back... | Totals for 1912-03-010 | ||
Length: | 0.4 | ||
Estimate: | $455,485 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |