Detail Letting Schedule for Webb County (FY 2020)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Webb County (FY 2020) |
CCSJ: 0018-06-136 |
|||
District: | LAREDO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0018-06-136 |
Description: | WIDEN OF MAINLANES AND RR GRADE SEPARATION | Handling Code: | |
Limits From: | SHILOH DRIVE | Fund Cat: | 1 |
Limits To: | 0.25 MILES N. OF US 59/ IH 69W | ESTIMATE: | $54,000,000 |
Length: | 1.4 | Actual | $0 |
District: | LAREDO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0018-06-183 |
Description: | CONSTRUCTION OF DIRECT CONNECTOR INTERCHANGE (DC#5) | Handling Code: | |
Limits From: | 0.50 MI SOUTH OF US59 | Fund Cat: | 1 |
Limits To: | 0.50 MI EAST OF IH35 | ESTIMATE: | $30,000,000 |
Length: | 0.5 | Actual | $0 |
District: | LAREDO | Let Date: | Dec 2019 |
Highway: | IH 35 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0018-06-198 |
Description: | Widen Road - Add Lanes | Handling Code: | |
Limits From: | 0.38 MILES SOUTH OF US59/IH35 INT | Fund Cat: | 11 |
Limits To: | 0.80 MILES NORTH OF US59/IH35 INT | ESTIMATE: | $5,000,000 |
Length: | 1.2 | Actual | $0 |
Back... | Totals for 0018-06-136 | ||
---|---|---|---|
Length: | 3.1 | ||
Estimate: | $89,000,000 | ||
Actual: | |||
CCSJ: 0037-10-037 |
|||
District: | LAREDO | Let Date: | Sep 2019 |
Highway: | US 83 | Let Status: | Tentative |
Project ID: | NH 2019(047) | CSJ: | 0037-10-037 |
Description: | FOR THE REHABILITATION OF AN EXISTING HIGHWAY | Handling Code: | |
Limits From: | 3.442 MILES SOUTH OF SH 44 | Fund Cat: | 11 |
Limits To: | IH35/US83 INTERSECTION EAST FRTG RD | ESTIMATE: | $61,429,214 |
Length: | 16.4 | Actual | $0 |
District: | LAREDO | Let Date: | Sep 2019 |
Highway: | IH 35 | Let Status: | Tentative |
Project ID: | NH 2019(049) | CSJ: | 0018-05-099 |
Description: | REHABILITATION OF EXISTING HIGHWAY | Handling Code: | |
Limits From: | IH35/US83 INTERSECTION WEST FRTG RD | Fund Cat: | 1 |
Limits To: | 0.37 MI SOUTH OF US83/IH35 INT | ESTIMATE: | $1,227,627 |
Length: | 0.4 | Actual | $0 |
Back... | Totals for 0037-10-037 | ||
Length: | 16.8 | ||
Estimate: | $62,656,841 | ||
Actual: | |||
CCSJ: 0086-14-084 |
|||
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | IH 69W | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0086-14-084 |
Description: | WIDENING OF EXISTING FREEWAY (6 LANES) | Handling Code: | |
Limits From: | WORLD TRADE BRIDGE GSA FACILITIES | Fund Cat: | 11 |
Limits To: | IH 35 | ESTIMATE: | $15,000,000 |
Length: | 1.8 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | FM 1472 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 2150-04-076 |
Description: | Rehab Of Transportation Management | Handling Code: | |
Limits From: | BIG BEND BLVD NORTHBOUND | Fund Cat: | 11 |
Limits To: | KILLAM INDUSTRIAL BLVD NORTHBOUND | ESTIMATE: | $3,340,000 |
Length: | 1.4 | Actual | $0 |
Proposal Request Back... | Totals for 0086-14-084 | ||
Length: | 3.2 | ||
Estimate: | $18,340,000 | ||
Actual: | |||
CCSJ: 0237-03-035 |
|||
District: | LAREDO | Let Date: | Mar 2020 |
Highway: | SH 44 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0237-03-035 |
Description: | SAFETY TREAT FIXED OBJECT | Handling Code: | |
Limits From: | LA SALLE COUNTY LINE | Fund Cat: | 8 |
Limits To: | 23 MILES E OF LA SALLE COUNTY LINE | ESTIMATE: | $921,568 |
Length: | 23.0 | Actual | $0 |
District: | LAREDO | Let Date: | Mar 2020 |
Highway: | FM 624 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2373-01-020 |
Description: | SAFETY TREAT FIXED OBJECT | Handling Code: | |
Limits From: | 13.610 MI W OF MCMULLEN CL | Fund Cat: | 8 |
Limits To: | MCMULLEN COUNTY LINE | ESTIMATE: | $1,074,307 |
Length: | 13.6 | Actual | $0 |
Back... | Totals for 0237-03-035 | ||
Length: | 36.6 | ||
Estimate: | $1,995,875 | ||
Actual: | |||
CCSJ: 0922-00-066 |
|||
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0922-00-066 |
Description: | UPGRADE BRIDGE RAIL AND MBGF | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 11 |
Limits To: | . | ESTIMATE: | $2,250,000 |
Length: | 0.1 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | US 90 | Let Status: | Tentative |
Project ID: | BR ( ) | CSJ: | 0023-02-042 |
Description: | REPLACEMENT OF BRIDGE AND APPROACH RAIL | Handling Code: | |
Limits From: | VALVERDE COUNTY LINE | Fund Cat: | 6 |
Limits To: | AT SYCAMORE CREEK | ESTIMATE: | $775,030 |
Length: | 0.5 | Actual | $0 |
Proposal Request Back... | Totals for 0922-00-066 | ||
Length: | 0.6 | ||
Estimate: | $3,025,030 | ||
Actual: | |||
CCSJ: 0922-00-070 |
|||
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0922-00-070 |
Description: | CONSTRUCTION OF RAISED MEDIAN | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 11 |
Limits To: | . | ESTIMATE: | $150,000 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 0922-00-070 | ||
Length: | 0.1 | ||
Estimate: | $150,000 | ||
Actual: | |||
CCSJ: 0922-33-076 |
|||
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | DMO 2012(628) | CSJ: | 0922-33-076 |
Description: | NEW LOCATION TWO LANE HIGHWAY | Handling Code: | LC |
Limits From: | INTERSECTION OF FM 1472 AND FLECHA | Fund Cat: | 3 |
Limits To: | 0.174 MILES EAST OF FM 1472 | ESTIMATE: | $1,810,434 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0922-33-076 | ||
Length: | 0.2 | ||
Estimate: | $1,810,434 | ||
Actual: | |||
CCSJ: 0922-33-093 |
|||
District: | LAREDO | Let Date: | Aug 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | DMO 2002(972) | CSJ: | 0922-33-093 |
Description: | CONSTRUCTION OF A GRADE SEPARATION INTERCHANGE | Handling Code: | LC |
Limits From: | 0.25 M EAST OF CALTON/SAN MARIA_INT | Fund Cat: | 3 |
Limits To: | 0.25 M WEST OF CALTON/SAN MARIA INT | ESTIMATE: | $16,242,001 |
Length: | 0.5 | Actual | $0 |
Back... | Totals for 0922-33-093 | ||
Length: | 0.5 | ||
Estimate: | $16,242,001 | ||
Actual: | |||
CCSJ: 0922-33-149 |
|||
District: | LAREDO | Let Date: | Jan 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | HP 1302(030) | CSJ: | 0922-33-149 |
Description: | CONSTRUCTION OF A PEDESTRIAN TRAIL AT CHACON CREEK | Handling Code: | LC |
Limits From: | SPUR 400 | Fund Cat: | 3 |
Limits To: | US 59 | ESTIMATE: | $1,400,000 |
Length: | 1.2 | Actual | $0 |
Back... | Totals for 0922-33-149 | ||
Length: | 1.2 | ||
Estimate: | $1,400,000 | ||
Actual: | |||
CCSJ: 0922-33-169 |
|||
District: | LAREDO | Let Date: | Oct 2019 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0922-33-169 |
Description: | UPGRADE AND INTERCONNECTION OF TRAFFIC SIGNALS | Handling Code: | |
Limits From: | AT VARIOUS LOCATIONS IN WEBB COUNTY | Fund Cat: | 11 |
Limits To: | . | ESTIMATE: | $500,000 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 0922-33-169 | ||
Length: | 0.1 | ||
Estimate: | $500,000 | ||
Actual: | |||
CCSJ: 0922-33-177 |
|||
District: | LAREDO | Let Date: | Jan 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP 2019(696)TP | CSJ: | 0922-33-177 |
Description: | RIVER VEGA MULTI-USE ALTERNATIVE TRANSPORTATION TRAIL | Handling Code: | LC |
Limits From: | ANNA PARK | Fund Cat: | 3 |
Limits To: | LCC CAMPUS | ESTIMATE: | $815,799 |
Length: | 1.5 | Actual | $0 |
Back... | Totals for 0922-33-177 | ||
Length: | 1.5 | ||
Estimate: | $815,799 | ||
Actual: | |||
CCSJ: 2150-02-009 |
|||
District: | LAREDO | Let Date: | Mar 2020 |
Highway: | FM 1472 | Let Status: | Tentative |
Project ID: | SSW 215-2-9 | CSJ: | 2150-02-009 |
Description: | MILLED EDGELINE RUMBLE STRIPS, MILLED CENTERLINE RUMBLE STRP | Handling Code: | |
Limits From: | 14.537 MI N OF SH 255 | Fund Cat: | 8 |
Limits To: | 12.537 MI N OF SH 255 | ESTIMATE: | $1,200,000 |
Length: | 2.0 | Actual | $0 |
District: | LAREDO | Let Date: | Mar 2020 |
Highway: | FM 1472 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 2150-03-026 |
Description: | MILLED EDGELINE RUMBLE STRIPS, MILLED CENTERLINE RUMBLE STRP | Handling Code: | |
Limits From: | 12.537 MI N OF SH 255 | Fund Cat: | 8 |
Limits To: | 10.486 MI N OF SH 255 | ESTIMATE: | $1,230,600 |
Length: | 2.1 | Actual | $0 |
Back... | Totals for 2150-02-009 | ||
Length: | 4.1 | ||
Estimate: | $2,430,600 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |