Detail Letting Schedule for Tom Green County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Tom Green County (FY 2021) |
CCSJ: 0070-02-096 |
|||
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | US 87 | Let Status: | Actual |
Project ID: | NH 2021(243) | CSJ: | 0070-02-096 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | US 277 | Fund Cat: | 1 |
Limits To: | SL 570 N OF WALL | ESTIMATE: | $1,106,878 |
Length: | 0.0 | Actual | $878,186 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2021(243) | CSJ: | 0159-01-043 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | US 87 | Fund Cat: | 1 |
Limits To: | 1.189 MI S OF US 87 | ESTIMATE: | $159,527 |
Length: | 0.0 | Actual | $136,211 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 0264-05-032 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | SH 158 WEST BOUND | Fund Cat: | 1 |
Limits To: | TOM GREEN COUNTY LINE | ESTIMATE: | $1,057,251 |
Length: | 0.0 | Actual | $893,665 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | SH 208 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 0454-02-054 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | COKE COUNTY LINE | Fund Cat: | 1 |
Limits To: | 11.669 MI S OF COKE COUNTY LINE | ESTIMATE: | $883,089 |
Length: | 0.0 | Actual | $746,049 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | SH 137 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 0494-07-011 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | MIDLAND COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 158 | ESTIMATE: | $717,417 |
Length: | 0.0 | Actual | $605,657 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | SH 153 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 0650-03-032 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | TAYLOR COUNTY LINE | Fund Cat: | 1 |
Limits To: | US 83 | ESTIMATE: | $1,112,181 |
Length: | 0.0 | Actual | $940,135 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | FM 1692 | Let Status: | Actual |
Project ID: | C 2281-3-7 | CSJ: | 2281-03-007 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 380 | Fund Cat: | 1 |
Limits To: | FM 765 | ESTIMATE: | $261,864 |
Length: | 0.0 | Actual | $221,107 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | RM 1357 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 3052-01-010 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | MIDLAND COUNTY LINE | Fund Cat: | 1 |
Limits To: | REAGAN COUNTY LINE | ESTIMATE: | $396,918 |
Length: | 0.0 | Actual | $334,881 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | RM 1357 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 3052-02-011 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | GLASSCOCK COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 137 | ESTIMATE: | $686,962 |
Length: | 0.0 | Actual | $579,225 |
District: | SAN ANGELO | Let Date: | Dec 2020 |
Highway: | RM 1357 | Let Status: | Actual |
Project ID: | STP 2021(244) | CSJ: | 3052-03-008 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | SH 137 | Fund Cat: | 1 |
Limits To: | RM 33 | ESTIMATE: | $394,552 |
Length: | 0.0 | Actual | $332,880 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0070-02-096 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $6,776,639 | ||
Actual: | $5,667,996 | ||
CCSJ: 0158-02-092 |
|||
District: | SAN ANGELO | Let Date: | Feb 2021 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 2020(479) | CSJ: | 0158-02-092 |
Description: | BRIDGE MAINTENANCE | Handling Code: | |
Limits From: | AT BELL STREET | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $1,262,325 |
Length: | 0.0 | Actual | $653,340 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0158-02-092 | ||
Length: | 0 | ||
Estimate: | $1,262,325 | ||
Actual: | $653,340 | ||
CCSJ: 0907-00-175 |
|||
District: | SAN ANGELO | Let Date: | Sep 2020 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2021(011) | CSJ: | 0907-00-175 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | VARIOUS ROADWAYS IN SJT DISTRICT | Fund Cat: | 11 |
Limits To: | . | ESTIMATE: | $965,285 |
Length: | 0.0 | Actual | $933,273 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0907-00-175 | ||
Length: | 0 | ||
Estimate: | $965,285 | ||
Actual: | $933,273 | ||
CCSJ: 0907-00-197 |
|||
District: | SAN ANGELO | Let Date: | Jan 2021 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2021(214) | CSJ: | 0907-00-197 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | VARIOUS LOCATIONS IN SJT DISTRICT | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $2,375,579 |
Length: | 0.0 | Actual | $2,137,530 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0907-00-197 | ||
Length: | 0 | ||
Estimate: | $2,375,579 | ||
Actual: | $2,137,530 | ||
CCSJ: 0907-00-223 |
|||
District: | SAN ANGELO | Let Date: | May 2021 |
Highway: | VA | Let Status: | Actual |
Project ID: | F 2021(513) | CSJ: | 0907-00-223 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | VARIOUS LOCATIONS IN SJT DISTRICT | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $1,121,543 |
Length: | 0.0 | Actual | $1,017,760 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0907-00-223 | ||
Length: | 0 | ||
Estimate: | $1,121,543 | ||
Actual: | $1,017,760 | ||
CCSJ: 0907-24-048 |
|||
District: | SAN ANGELO | Let Date: | Jun 2021 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2019(685)TAPS | CSJ: | 0907-24-048 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | LC |
Limits From: | ON CHADBOURNE STREET FROM WEST | Fund Cat: | 3 |
Limits To: | BEAUREGARD AVENUE TO CONCHO RIVER | ESTIMATE: | $2,272,852 |
Length: | 0.0 | Actual | $8,867,715 |
Back... | Totals for 0907-24-048 | ||
Length: | 0 | ||
Estimate: | $2,272,852 | ||
Actual: | $8,867,715 | ||
CCSJ: 2574-01-049 |
|||
District: | SAN ANGELO | Let Date: | Aug 2021 |
Highway: | CS | Let Status: | Actual |
Project ID: | F 2021(716) | CSJ: | 2574-01-049 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | VARIOUS LOCATIONS IN SAN ANGELO | Fund Cat: | 8 |
Limits To: | - | ESTIMATE: | $165,548 |
Length: | 0.0 | Actual | $243,041 |
District: | SAN ANGELO | Let Date: | Aug 2021 |
Highway: | VA | Let Status: | Actual |
Project ID: | F 2021(854) | CSJ: | 0907-00-228 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | VARIOUS LOCATIONS IN SJT DISTRICT | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $207,816 |
Length: | 0.0 | Actual | $295,561 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 2574-01-049 | ||
Length: | 0 | ||
Estimate: | $373,364 | ||
Actual: | $538,601 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |