Detail Letting Schedule for Atascosa County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Atascosa County (FY 2021) |
CCSJ: 0017-04-045 |
|||
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0017-04-045 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | ATASCOSA / MEDINA COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 3175 | ESTIMATE: | $1,236,855 |
Length: | 0.7 | Actual | $1,084,759 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0017-05-097 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CR 770 | Fund Cat: | 1 |
Limits To: | MEDINA / ATASCOSA COUNTY LINE | ESTIMATE: | $196,146 |
Length: | 4.7 | Actual | $183,665 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0017-06-087 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 140 | Fund Cat: | 1 |
Limits To: | FM 3352 | ESTIMATE: | $257,747 |
Length: | 7.0 | Actual | $251,483 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0024-04-067 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | MEDINA / UVALDE COUNTY LINE | Fund Cat: | 1 |
Limits To: | 0.11 MILES E OF CR 424 | ESTIMATE: | $987,672 |
Length: | 13.1 | Actual | $927,914 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0024-05-100 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.11 MI E OF CR 424 | Fund Cat: | 1 |
Limits To: | CASTRO AVENUE | ESTIMATE: | $192,053 |
Length: | 2.5 | Actual | $181,976 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0072-05-095 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 1.2 MI S OF LITTLE JOSHUA CREEK | Fund Cat: | 1 |
Limits To: | CIBOLO CREEK | ESTIMATE: | $99,211 |
Length: | 4.8 | Actual | $93,183 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | NH 2021(065) | CSJ: | 0072-06-088 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CIBOLO CREEK | Fund Cat: | 1 |
Limits To: | IH 10 ENTRANCE | ESTIMATE: | $16,165 |
Length: | 0.4 | Actual | $14,143 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 106 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0143-11-005 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 87 E | Fund Cat: | 1 |
Limits To: | US 87 W | ESTIMATE: | $58,474 |
Length: | 1.7 | Actual | $54,061 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 107 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0143-12-005 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 87 | Fund Cat: | 1 |
Limits To: | FM 3465 | ESTIMATE: | $56,941 |
Length: | 1.3 | Actual | $52,697 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 321 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0143-14-007 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 87 E | Fund Cat: | 1 |
Limits To: | US 87 W | ESTIMATE: | $34,247 |
Length: | 0.8 | Actual | $31,162 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | BU 87-U | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0143-15-033 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 87 E | Fund Cat: | 1 |
Limits To: | US 87 W | ESTIMATE: | $108,450 |
Length: | 2.0 | Actual | $100,695 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 39 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0193-01-039 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | KERR / REAL COUNTYLINE | Fund Cat: | 1 |
Limits To: | CAMP MYSTIC | ESTIMATE: | $1,027,091 |
Length: | 23.1 | Actual | $971,218 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 39 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0193-02-046 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CAMP MYSTIC | Fund Cat: | 1 |
Limits To: | INGRAM DAM | ESTIMATE: | $503,377 |
Length: | 11.9 | Actual | $454,351 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 46 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0215-07-053 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | KENDALL/COMAL COLUNTY LINE | Fund Cat: | 1 |
Limits To: | FARHILLS DRIVE | ESTIMATE: | $518,614 |
Length: | 7.5 | Actual | $473,808 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1681 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0215-11-023 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 123 | Fund Cat: | 1 |
Limits To: | CR 448 | ESTIMATE: | $430,059 |
Length: | 8.1 | Actual | $410,654 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1681 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0215-11-024 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CR 448 | Fund Cat: | 1 |
Limits To: | WILSON/GONZALEZ COUNTY LINE | ESTIMATE: | $263,531 |
Length: | 3.8 | Actual | $251,395 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0291-03-075 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | RIVERHILL BLVD. | Fund Cat: | 1 |
Limits To: | KERR/BANDERA C/L | ESTIMATE: | $656,255 |
Length: | 11.9 | Actual | $593,136 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0328-01-015 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.4 MI N BLUEBONNET DR | Fund Cat: | 1 |
Limits To: | US 87 | ESTIMATE: | $579,726 |
Length: | 9.5 | Actual | $532,447 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 99 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0348-13-021 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LIVE OAK/MCMULLEN C/L | Fund Cat: | 1 |
Limits To: | SH 72 | ESTIMATE: | $706,909 |
Length: | 12.3 | Actual | $679,601 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1347 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0366-08-010 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 123 | Fund Cat: | 1 |
Limits To: | SH 119 | ESTIMATE: | $89,055 |
Length: | 1.9 | Actual | $75,253 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | RM 187 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0369-03-029 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | UVALDE / ZAVALA COUNTY LINE | ESTIMATE: | $611,232 |
Length: | 17.2 | Actual | $566,047 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 173 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0421-04-033 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2504 | Fund Cat: | 1 |
Limits To: | SH 16 | ESTIMATE: | $1,302,232 |
Length: | 15.2 | Actual | $1,238,222 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 3350 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0421-09-020 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | FM 3510 | ESTIMATE: | $286,527 |
Length: | 3.3 | Actual | $268,685 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1518 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0465-02-030 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 10 | Fund Cat: | 1 |
Limits To: | FM 1346 | ESTIMATE: | $189,244 |
Length: | 4.6 | Actual | $175,411 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | RM 32 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0511-02-025 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BLANCO/COMAL COUNTY LINE | Fund Cat: | 1 |
Limits To: | COMAL/HAYS COUNTY LINE | ESTIMATE: | $668,440 |
Length: | 12.7 | Actual | $603,918 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0849-02-051 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 1283 | Fund Cat: | 1 |
Limits To: | MEDINA/BEXAR COUNTY LINE | ESTIMATE: | $46,369 |
Length: | 0.8 | Actual | $41,412 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 472 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 0849-04-036 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 173 | Fund Cat: | 1 |
Limits To: | FM 462 | ESTIMATE: | $65,951 |
Length: | 3.0 | Actual | $61,715 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1347 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1010-01-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 119 | Fund Cat: | 1 |
Limits To: | FM 538 | ESTIMATE: | $210,629 |
Length: | 4.6 | Actual | $179,370 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1347 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1010-02-006 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 541 | Fund Cat: | 1 |
Limits To: | SH 123 | ESTIMATE: | $134,694 |
Length: | 4.6 | Actual | $114,563 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1435 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1167-02-012 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | US 83 | ESTIMATE: | $29,499 |
Length: | 1.0 | Actual | $27,490 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1962 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1205-02-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | 0.43 MI E OF RHODE RANCH RD (END STATE M | ESTIMATE: | $291,747 |
Length: | 9.2 | Actual | $268,268 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1102 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1273-01-038 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 35 | Fund Cat: | 1 |
Limits To: | WATSON LN | ESTIMATE: | $193,719 |
Length: | 2.9 | Actual | $163,617 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1628 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1540-01-010 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LP 106 | Fund Cat: | 1 |
Limits To: | FM 3432 | ESTIMATE: | $77,584 |
Length: | 1.8 | Actual | $72,349 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1547-01-050 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | FM 2790 | ESTIMATE: | $239,554 |
Length: | 4.8 | Actual | $221,907 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1303 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1548-01-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2579 | Fund Cat: | 1 |
Limits To: | FM 536 | ESTIMATE: | $301,432 |
Length: | 10.8 | Actual | $282,807 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 2730 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1589-02-011 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 127 | Fund Cat: | 1 |
Limits To: | US 90 | ESTIMATE: | $87,220 |
Length: | 2.6 | Actual | $80,115 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1283 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1730-01-045 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | BANDERA/MEDINA CL | ESTIMATE: | $609,816 |
Length: | 11.7 | Actual | $552,510 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1283 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1730-02-023 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BANDERA/MEDINA CL | Fund Cat: | 1 |
Limits To: | FM 471 | ESTIMATE: | $473,876 |
Length: | 9.1 | Actual | $428,578 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 2790 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1741-02-037 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | 0.25 MI E FM 476 (SOMERSET CITY LIMITS) | ESTIMATE: | $54,694 |
Length: | 1.7 | Actual | $49,443 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1979 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1898-03-013 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 123 | Fund Cat: | 1 |
Limits To: | FM 621 | ESTIMATE: | $225,908 |
Length: | 5.4 | Actual | $192,172 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | RM 1376 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1899-01-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | RM 473 E | Fund Cat: | 1 |
Limits To: | 0.25 MILE N. OF WASP CRK RD. | ESTIMATE: | $120,257 |
Length: | 3.9 | Actual | $109,572 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | RM 1376 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 1899-02-020 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | GILLESPIE / KENDALL CL | Fund Cat: | 1 |
Limits To: | RM 0473 WEST | ESTIMATE: | $385,877 |
Length: | 12.0 | Actual | $351,784 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2020-02-034 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | 0.71 MI N OF FM 2536 | ESTIMATE: | $683,020 |
Length: | 10.3 | Actual | $626,608 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1044 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2021-02-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | COMAL/GUADALUPE CL | Fund Cat: | 1 |
Limits To: | FM 78 | ESTIMATE: | $318,269 |
Length: | 6.4 | Actual | $270,975 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SS 144 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2175-01-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2369 | Fund Cat: | 1 |
Limits To: | US 83 | ESTIMATE: | $18,628 |
Length: | 0.4 | Actual | $16,790 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2255-02-029 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 3432 | Fund Cat: | 1 |
Limits To: | SAN ANTONIO RIVER | ESTIMATE: | $593,639 |
Length: | 10.2 | Actual | $541,261 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 2439 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2293-02-008 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | COMAL/HAYS | Fund Cat: | 1 |
Limits To: | FM 1102 | ESTIMATE: | $35,925 |
Length: | 0.5 | Actual | $29,703 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2452-01-071 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.71 MI N OF FM 2536 | Fund Cat: | 1 |
Limits To: | MACDONA/LACOSTE RD. | ESTIMATE: | $60,669 |
Length: | 1.2 | Actual | $55,613 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 3465 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2452-05-004 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LP 1604 N | Fund Cat: | 1 |
Limits To: | LP 1604 S | ESTIMATE: | $45,374 |
Length: | 1.4 | Actual | $41,575 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 1347 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 2549-01-008 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 538 | Fund Cat: | 1 |
Limits To: | US 87 | ESTIMATE: | $87,852 |
Length: | 3.2 | Actual | $74,462 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 3176 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 3257-01-010 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | WATSON AVE (DEVINE CITY LIMITS) | Fund Cat: | 1 |
Limits To: | MEDINA / FRIO COUNTY LINE | ESTIMATE: | $82,931 |
Length: | 2.9 | Actual | $69,866 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | FM 3176 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 3257-02-008 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | MEDINA / FRIO COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 462 | ESTIMATE: | $80,679 |
Length: | 2.8 | Actual | $68,056 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 211 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 3544-02-007 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | BEXAR/MEDINA CO LINE | ESTIMATE: | $352,379 |
Length: | 5.4 | Actual | $324,147 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 211 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 3544-03-008 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BEXAR/MEDINA CL | Fund Cat: | 1 |
Limits To: | FM 471 | ESTIMATE: | $114,575 |
Length: | 1.9 | Actual | $104,366 |
District: | SAN ANTONIO | Let Date: | Oct 2020 |
Highway: | SH 211 | Let Status: | Actual |
Project ID: | STP 2021(120) | CSJ: | 3544-04-010 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 1957 | Fund Cat: | 1 |
Limits To: | US 90 | ESTIMATE: | $283,048 |
Length: | 3.8 | Actual | $257,541 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0017-04-045 | ||
---|---|---|---|
Length: | 322.3 | ||
Estimate: | $17,382,063 | ||
Actual: | $15,948,519 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |