Detail Letting Schedule for Montague County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Montague County (FY 2021) |
CCSJ: 0013-02-023 |
|||
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | US 81 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0013-02-023 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | RED RIVER | Fund Cat: | 1 |
Limits To: | SL 19 (LANES ONLY) | ESTIMATE: | $715,700 |
Length: | 3.4 | Actual | $549,785 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | US 81 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0013-03-037 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SL 19 | Fund Cat: | 1 |
Limits To: | FM 1806 W (LANES ONLY) | ESTIMATE: | $298,935 |
Length: | 0.0 | Actual | $279,016 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | US 81 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0013-04-022 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1806 W | Fund Cat: | 1 |
Limits To: | FM 174 (LANES ONLY) | ESTIMATE: | $212,464 |
Length: | 7.9 | Actual | $198,542 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | BU 287J | Let Status: | Actual |
Project ID: | NH 2B20(311) | CSJ: | 0043-17-033 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 1814 | Fund Cat: | 1 |
Limits To: | CITY VIEW DR | ESTIMATE: | $320,606 |
Length: | 6.0 | Actual | $305,414 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0124-03-063 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | CATO STREET | Fund Cat: | 1 |
Limits To: | NEAR CR 136 E | ESTIMATE: | $228,084 |
Length: | 5.1 | Actual | $213,801 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0124-04-041 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | NEAR CR 136E | Fund Cat: | 1 |
Limits To: | NEAR FM 2585 | ESTIMATE: | $68,664 |
Length: | 0.0 | Actual | $64,348 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1286 | Let Status: | Actual |
Project ID: | C 133-11-3 | CSJ: | 0133-11-003 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | SH 114 | Fund Cat: | 1 |
Limits To: | 0.68 MI SOUTH | ESTIMATE: | $25,610 |
Length: | 0.0 | Actual | $24,568 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | SH 25 | Let Status: | Actual |
Project ID: | C 137-2-29 | CSJ: | 0137-02-029 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | BEGIN STATE MAINTENANCE | Fund Cat: | 1 |
Limits To: | US 287 | ESTIMATE: | $232,932 |
Length: | 0.0 | Actual | $222,859 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2393 | Let Status: | Actual |
Project ID: | C 514-6-10 | CSJ: | 0514-06-010 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1740 | Fund Cat: | 1 |
Limits To: | SH 79 | ESTIMATE: | $142,351 |
Length: | 0.0 | Actual | $134,680 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1180 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0544-02-017 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | ARCHER COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 2846 | ESTIMATE: | $106,677 |
Length: | 4.2 | Actual | $103,706 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1180 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0544-03-008 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 2846 | Fund Cat: | 1 |
Limits To: | WICHITA COUNTY LINE | ESTIMATE: | $74,030 |
Length: | 3.3 | Actual | $69,715 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2374 | Let Status: | Actual |
Project ID: | C 562-2-15 | CSJ: | 0562-02-015 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 1285 | Fund Cat: | 1 |
Limits To: | END STATE MAINTENANCE | ESTIMATE: | $66,009 |
Length: | 3.0 | Actual | $62,425 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3164 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0782-01-037 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 678 | Fund Cat: | 1 |
Limits To: | FM 902 | ESTIMATE: | $166,933 |
Length: | 5.3 | Actual | $155,780 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 370 | Let Status: | Actual |
Project ID: | C 821-3-18 | CSJ: | 0821-03-018 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 70 | Fund Cat: | 1 |
Limits To: | WICHITA COUNTY LINE | ESTIMATE: | $244,022 |
Length: | 9.7 | Actual | $238,557 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 370 | Let Status: | Actual |
Project ID: | C 821-4-12 | CSJ: | 0821-04-012 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | WILBARGER COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 25 | ESTIMATE: | $28,735 |
Length: | 1.1 | Actual | $28,228 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 210 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0824-01-033 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | SH 25 | Fund Cat: | 1 |
Limits To: | FM 422 | ESTIMATE: | $221,813 |
Length: | 9.6 | Actual | $209,500 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 172 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0824-02-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 281 | Fund Cat: | 1 |
Limits To: | CLAY CO LINE | ESTIMATE: | $79,076 |
Length: | 2.7 | Actual | $77,094 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 172 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0824-03-017 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | ARCHER CL | Fund Cat: | 1 |
Limits To: | SH 148 | ESTIMATE: | $385,450 |
Length: | 13.5 | Actual | $363,418 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 925 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0832-02-030 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 392 | Fund Cat: | 1 |
Limits To: | US 287 | ESTIMATE: | $150,299 |
Length: | 6.5 | Actual | $145,857 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 0903-00-108 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | VARIOUS LOCATIONS DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $709,104 |
Length: | 0.1 | Actual | $681,406 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 923 | Let Status: | Actual |
Project ID: | C 982-4-12 | CSJ: | 0982-04-012 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 380 | Fund Cat: | 1 |
Limits To: | US 183 | ESTIMATE: | $184,490 |
Length: | 8.4 | Actual | $174,495 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 578 | Let Status: | Actual |
Project ID: | C 1031-7-12 | CSJ: | 1031-07-012 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 380 | Fund Cat: | 1 |
Limits To: | FM 209 | ESTIMATE: | $199,606 |
Length: | 9.2 | Actual | $189,371 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 209 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1076-01-039 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 183 | Fund Cat: | 1 |
Limits To: | YOUNG COUNTY LINE | ESTIMATE: | $130,844 |
Length: | 6.0 | Actual | $123,732 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2916 | Let Status: | Actual |
Project ID: | C 1162-1-16 | CSJ: | 1162-01-016 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 283 | Fund Cat: | 1 |
Limits To: | FM 924 | ESTIMATE: | $76,328 |
Length: | 3.0 | Actual | $74,534 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1152 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1297-01-014 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | W US 277 INTERSECTION | Fund Cat: | 1 |
Limits To: | E US 277 INTERSECTION | ESTIMATE: | $222,897 |
Length: | 10.2 | Actual | $211,692 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1352-02-024 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 922 | Fund Cat: | 1 |
Limits To: | COOKE COUNTY LINE | ESTIMATE: | $224,835 |
Length: | 7.7 | Actual | $215,950 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1352-03-011 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | MONTAGUE COUNTY LINE | Fund Cat: | 1 |
Limits To: | WISE COUNTY LINE | ESTIMATE: | $44,058 |
Length: | 1.5 | Actual | $42,494 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 678 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1357-01-028 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | SOUTH OF US 82 | Fund Cat: | 1 |
Limits To: | FM 2896 | ESTIMATE: | $115,945 |
Length: | 3.8 | Actual | $110,899 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 678 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1357-02-014 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | 1 MI SOUTH OF US 82 | Fund Cat: | 1 |
Limits To: | 0.07 MI SOUTH OF US 82 | ESTIMATE: | $29,172 |
Length: | 1.0 | Actual | $27,166 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1739 | Let Status: | Actual |
Project ID: | C 1614-1-12 | CSJ: | 1614-01-012 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | BU 287H | Fund Cat: | 1 |
Limits To: | SH 240 | ESTIMATE: | $233,703 |
Length: | 0.0 | Actual | $221,478 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 678 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1699-02-013 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 2896 | Fund Cat: | 1 |
Limits To: | FM 2383 | ESTIMATE: | $128,683 |
Length: | 5.8 | Actual | $121,176 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1811 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1770-01-018 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1763 | Fund Cat: | 1 |
Limits To: | WICHITA COUNTY LINE | ESTIMATE: | $389,288 |
Length: | 15.1 | Actual | $378,211 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1811 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1770-02-009 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | WILBARGER COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 25 | ESTIMATE: | $45,484 |
Length: | 1.8 | Actual | $44,378 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 98 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 1998-03-005 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FOARD COUNTY LINE | Fund Cat: | 1 |
Limits To: | US 70 | ESTIMATE: | $42,352 |
Length: | 1.7 | Actual | $41,560 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2581 | Let Status: | Actual |
Project ID: | C 2113-1-8 | CSJ: | 2113-01-008 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 25 | Fund Cat: | 1 |
Limits To: | US 281 | ESTIMATE: | $253,750 |
Length: | 11.2 | Actual | $240,365 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 925 | Let Status: | Actual |
Project ID: | C 2312-2-12 | CSJ: | 2312-02-012 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | HARDEMAN COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 392 | ESTIMATE: | $119,747 |
Length: | 5.1 | Actual | $116,145 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2384 | Let Status: | Actual |
Project ID: | C 2323-1-18 | CSJ: | 2323-01-018 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1739 | Fund Cat: | 1 |
Limits To: | BU 287H | ESTIMATE: | $109,968 |
Length: | 4.4 | Actual | $107,162 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2393 | Let Status: | Actual |
Project ID: | C 2405-1-13 | CSJ: | 2405-01-013 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 79 | Fund Cat: | 1 |
Limits To: | FM 3393 | ESTIMATE: | $64,612 |
Length: | 2.1 | Actual | $62,880 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 2393 | Let Status: | Actual |
Project ID: | C 2405-2-16 | CSJ: | 2405-02-016 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | LP 47 | Fund Cat: | 1 |
Limits To: | FM 1954 W | ESTIMATE: | $292,577 |
Length: | 8.1 | Actual | $281,994 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3206 | Let Status: | Actual |
Project ID: | C 2725-1-12 | CSJ: | 2725-01-012 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 677 | Fund Cat: | 1 |
Limits To: | END STATE MAINTENANCE | ESTIMATE: | $157,348 |
Length: | 0.0 | Actual | $151,797 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 1286 | Let Status: | Actual |
Project ID: | C 2861-1-7 | CSJ: | 2861-01-007 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | 0.68 MI S OF SH 114 | Fund Cat: | 1 |
Limits To: | END STATE MAINTENANCE | ESTIMATE: | $85,930 |
Length: | 3.8 | Actual | $81,083 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3043 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 3073-01-009 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 81 | Fund Cat: | 1 |
Limits To: | NELSON ST. | ESTIMATE: | $16,376 |
Length: | 0.3 | Actual | $15,348 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3430 | Let Status: | Actual |
Project ID: | C 3247-1-5 | CSJ: | 3247-01-005 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 433 | Fund Cat: | 1 |
Limits To: | END STATE MAINTENANCE | ESTIMATE: | $51,612 |
Length: | 1.5 | Actual | $50,433 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3207 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 3317-01-006 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 70 | Fund Cat: | 1 |
Limits To: | FM 433 | ESTIMATE: | $183,426 |
Length: | 5.0 | Actual | $177,980 |
District: | WICHITA FALLS | Let Date: | Nov 2020 |
Highway: | FM 3492 | Let Status: | Actual |
Project ID: | STP 2B20(301) | CSJ: | 3553-01-007 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 369 | Fund Cat: | 1 |
Limits To: | IH 44 | ESTIMATE: | $103,113 |
Length: | 0.0 | Actual | $100,333 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0013-02-023 | ||
---|---|---|---|
Length: | 198.1 | ||
Estimate: | $7,983,637 | ||
Actual: | $7,491,355 | ||
CCSJ: 0013-05-062 |
|||
District: | WICHITA FALLS | Let Date: | Jan 2021 |
Highway: | US 81 | Let Status: | Actual |
Project ID: | STP 2021(252) | CSJ: | 0013-05-062 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 174 | Fund Cat: | 11 |
Limits To: | FM 3043 | ESTIMATE: | $1,015,800 |
Length: | 0.0 | Actual | $775,964 |
District: | WICHITA FALLS | Let Date: | Jan 2021 |
Highway: | SH 59 | Let Status: | Actual |
Project ID: | STP 2021(252) | CSJ: | 0239-02-038 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | MILL STREET | Fund Cat: | 11 |
Limits To: | US 81 | ESTIMATE: | $942,759 |
Length: | 0.0 | Actual | $720,122 |
District: | WICHITA FALLS | Let Date: | Jan 2021 |
Highway: | SH 59 | Let Status: | Actual |
Project ID: | STP 2021(252) | CSJ: | 0239-05-034 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 81 | Fund Cat: | 11 |
Limits To: | WICHITA STREET | ESTIMATE: | $169,146 |
Length: | 0.0 | Actual | $132,071 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0013-05-062 | ||
Length: | 0 | ||
Estimate: | $2,127,704 | ||
Actual: | $1,628,158 | ||
CCSJ: 0044-04-047 |
|||
District: | WICHITA FALLS | Let Date: | Jul 2021 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | F 2021(704) | CSJ: | 0044-04-047 |
Description: | WIDEN ROAD - ADD LANES | Handling Code: | |
Limits From: | SH 175 / MONTAGUE STREET | Fund Cat: | 1 |
Limits To: | NEAR FM 1816 | ESTIMATE: | $35,990,334 |
Length: | 6.1 | Actual | $27,683,391 |
District: | WICHITA FALLS | Let Date: | Jul 2021 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | F 2021(704) | CSJ: | 0044-04-049 |
Description: | WIDEN ROAD - ADD LANES | Handling Code: | |
Limits From: | 0.5 MI EAST OF US 81 | Fund Cat: | 1 |
Limits To: | NEAR FM 1816 | ESTIMATE: | $27,909,182 |
Length: | 5.8 | Actual | $20,779,023 |
List Showing Order Proposal Request Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0044-04-047 | ||
Length: | 11.9 | ||
Estimate: | $63,899,516 | ||
Actual: | $48,462,414 | ||
CCSJ: 0224-03-060 |
|||
District: | WICHITA FALLS | Let Date: | Aug 2021 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | F 2021(872) | CSJ: | 0224-03-060 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | NEAR JACKSON RD | Fund Cat: | 11 |
Limits To: | US 81 | ESTIMATE: | $3,227,338 |
Length: | 5.8 | Actual | $3,203,181 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0224-03-060 | ||
Length: | 5.8 | ||
Estimate: | $3,227,338 | ||
Actual: | $3,203,181 | ||
CCSJ: 1767-03-020 |
|||
District: | WICHITA FALLS | Let Date: | Apr 2021 |
Highway: | FM 1816 | Let Status: | Actual |
Project ID: | F 2021(455) | CSJ: | 1767-03-020 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | ROBERTS ST | Fund Cat: | 1 |
Limits To: | SH 59 | ESTIMATE: | $327,495 |
Length: | 0.0 | Actual | $305,567 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 1767-03-020 | ||
Length: | 0 | ||
Estimate: | $327,495 | ||
Actual: | $305,567 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |