Letting Schedule for Wichita Falls District (FY 2022)

Last Update: Tuesday, May 17, 2022

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Wichita Falls District (FY 2022)
Archer | Baylor | Clay | Cooke | Montague | Wichita | Wilbarger | Young |

Archer County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0249-03-054US 281ActualJan 2022$2,286,6691SURFACING/ROADWAY RESTORATION3.5
0156-05-063US 82ActualOct 2021$5,514,35411RESURFACE ROADWAY0.0

Baylor County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0133-04-042US 82ActualDec 2021$17,221,1621WIDEN ROAD - ADD LANES8.0

Clay County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0391-04-029SH 148ActualFeb 2022$010RAILROAD CROSSING IMPROVEMENTS0.0
0224-01-061US 287ActualJan 2022$2,052,6201SURFACING/ROADWAY RESTORATION0.0

Cooke County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0903-15-105CRActualJan 2022$1,592,0706BRIDGE REPLACEMENT6.5
1356-01-029FM 1201ActualJan 2022$4,621,3031SURFACING/ROADWAY RESTORATION8.0
0312-01-076FM 51ActualApr 2022$4,931,3286BRIDGE REPLACEMENT7.0

Montague County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0013-13-005SH 101ActualNov 2021$7,477,2181SEAL COAT0.0

Wichita County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0903-00-119VAActualMay 2022$548,6658INSTALL ILLUMINATION0.0
0903-00-120VAActualMay 2022$633,1658INSTALL ILLUMINATION0.0

Wilbarger County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0832-02-029FM 925ApprovedAug 2022$965,0006BRIDGE REPLACEMENT0.0

Young County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0134-02-060US 380ActualOct 2021$2,616,99711RESURFACE ROADWAY2.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract