Letting Schedule for Wichita Falls District (FY 2022)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Wichita Falls District (FY 2022) |
Archer | Baylor | Clay | Cooke | Montague | Wichita | Wilbarger | Young | | |||||||
Archer County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0249-03-054 | US 281 | Actual | Jan 2022 | $2,286,669 | 1 | SURFACING/ROADWAY RESTORATION | 3.5 |
0156-05-063 | US 82 | Actual | Oct 2021 | $5,514,354 | 11 | RESURFACE ROADWAY | 0.0 |
Baylor County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0133-04-042 | US 82 | Actual | Dec 2021 | $17,221,162 | 1 | WIDEN ROAD - ADD LANES | 8.0 |
Clay County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0391-04-029 | SH 148 | Actual | Feb 2022 | $0 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0224-01-061 | US 287 | Actual | Jan 2022 | $2,052,620 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
Cooke County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0312-01-076 | FM 51 | Actual | Apr 2022 | $4,931,328 | 6 | BRIDGE REPLACEMENT | 7.0 |
1356-01-029 | FM 1201 | Actual | Jan 2022 | $4,621,303 | 1 | SURFACING/ROADWAY RESTORATION | 8.0 |
0903-15-105 | CR | Actual | Jan 2022 | $1,592,070 | 6 | BRIDGE REPLACEMENT | 6.5 |
Montague County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0013-13-005 | SH 101 | Actual | Nov 2021 | $7,477,218 | 1 | SEAL COAT | 0.0 |
Wichita County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0903-00-120 | VA | Actual | May 2022 | $633,165 | 8 | INSTALL ILLUMINATION | 0.0 |
0903-00-119 | VA | Actual | May 2022 | $548,665 | 8 | INSTALL ILLUMINATION | 0.0 |
Wilbarger County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0832-02-029 | FM 925 | Approved | Aug 2022 | $983,955 | 6 | BRIDGE REPLACEMENT | 0.0 |
Young County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0134-02-060 | US 380 | Actual | Oct 2021 | $2,616,997 | 11 | RESURFACE ROADWAY | 2.0 |
|