Detail Letting Schedule for Comal County (FY 2023)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Comal County (FY 2023) |
CCSJ: 0016-05-122 |
|||
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | C 16-5-122 | CSJ: | 0016-05-122 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SOLMS ROAD | Fund Cat: | 1 |
Limits To: | WALNUT STREET | ESTIMATE: | $102,333 |
Length: | 3.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | C 16-5-123 | CSJ: | 0016-05-123 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SOLMS RD. | Fund Cat: | 1 |
Limits To: | SL 337 | ESTIMATE: | $56,012 |
Length: | 1.2 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 10 | Let Status: | Approved |
Project ID: | C 72-6-85 | CSJ: | 0072-06-085 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | AUSTIN DR SOUTH | Fund Cat: | 1 |
Limits To: | FREDERICK CREEK | ESTIMATE: | $55,053 |
Length: | 1.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 10 | Let Status: | Approved |
Project ID: | C 72-6-86 | CSJ: | 0072-06-086 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 10 WB EXIT RAMP | Fund Cat: | 1 |
Limits To: | JOHN'S ROAD | ESTIMATE: | $2,267 |
Length: | 1.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 10 | Let Status: | Approved |
Project ID: | C 72-6-87 | CSJ: | 0072-06-087 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BOERNE CITY PARK ENTRANCE | Fund Cat: | 1 |
Limits To: | JOHN'S ROAD | ESTIMATE: | $23,087 |
Length: | 0.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 41 | Let Status: | Approved |
Project ID: | C 201-7-17 | CSJ: | 0201-07-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | KERR/REAL COUNTY LINE | Fund Cat: | 1 |
Limits To: | 3.3 MI E OF FM 1340 | ESTIMATE: | $209,848 |
Length: | 11.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 41 | Let Status: | Approved |
Project ID: | C 201-7-18 | CSJ: | 0201-07-018 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 3.3 MI E OF FM 1340 | Fund Cat: | 1 |
Limits To: | 0.33 MI W OF HENRY PRIOUR RANCH ROAD | ESTIMATE: | $319,800 |
Length: | 7.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 41 | Let Status: | Approved |
Project ID: | C 201-8-24 | CSJ: | 0201-08-024 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.33 MI W OF HENRY PRIOUR | Fund Cat: | 1 |
Limits To: | IH 10 | ESTIMATE: | $595,032 |
Length: | 12.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 466 | Let Status: | Approved |
Project ID: | C 216-3-35 | CSJ: | 0216-03-035 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | FM 477 | ESTIMATE: | $125,909 |
Length: | 3.8 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 117 | Let Status: | Approved |
Project ID: | C 236-1-23 | CSJ: | 0236-01-023 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 83 | Fund Cat: | 1 |
Limits To: | UVALDE/ZAVALA COUNTY LINE | ESTIMATE: | $280,284 |
Length: | 8.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 173 | Let Status: | Approved |
Project ID: | C 421-7-15 | CSJ: | 0421-07-015 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | MEDINA RIVER BRIDGE | Fund Cat: | 1 |
Limits To: | BANDERA/MEDINA COUNTY LINE | ESTIMATE: | $299,552 |
Length: | 7.2 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 173 | Let Status: | Approved |
Project ID: | C 609-1-23 | CSJ: | 0609-01-023 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | CAMP MEETING CREEK | ESTIMATE: | $110,732 |
Length: | 1.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | RM 187 | Let Status: | Approved |
Project ID: | C 678-1-34 | CSJ: | 0678-01-034 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | UVALDE/BANDERA COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 127 | ESTIMATE: | $685,666 |
Length: | 21.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1023 | Let Status: | Approved |
Project ID: | C 678-3-15 | CSJ: | 0678-03-015 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | FM 1049 | ESTIMATE: | $323,192 |
Length: | 10.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1340 | Let Status: | Approved |
Project ID: | C 829-4-34 | CSJ: | 0829-04-034 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 41 | Fund Cat: | 1 |
Limits To: | SH 39 | ESTIMATE: | $698,876 |
Length: | 21.3 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 306 | Let Status: | Approved |
Project ID: | C 857-1-38 | CSJ: | 0857-01-038 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 3424 | Fund Cat: | 1 |
Limits To: | .085 MI S OF N PARK ROAD | ESTIMATE: | $151,217 |
Length: | 3.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 140 | Let Status: | Approved |
Project ID: | C 875-1-19 | CSJ: | 0875-01-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 117 | Fund Cat: | 1 |
Limits To: | UVALDE/ZAVALA COUNTY LINE | ESTIMATE: | $638,882 |
Length: | 16.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1049 | Let Status: | Approved |
Project ID: | C 1168-2-17 | CSJ: | 1168-02-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 127 | Fund Cat: | 1 |
Limits To: | US 90 | ESTIMATE: | $398,040 |
Length: | 0.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1049 | Let Status: | Approved |
Project ID: | C 1168-3-14 | CSJ: | 1168-03-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | FM 1023 | ESTIMATE: | $161,960 |
Length: | 4.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | RM 1050 | Let Status: | Approved |
Project ID: | C 1169-1-27 | CSJ: | 1169-01-027 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 83 | Fund Cat: | 1 |
Limits To: | RM 187 | ESTIMATE: | $396,056 |
Length: | 14.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 306 | Let Status: | Approved |
Project ID: | C 1728-2-64 | CSJ: | 1728-02-064 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.85 MI SOUTH OF N PARK ROAD | Fund Cat: | 1 |
Limits To: | GRUENE HAVEN | ESTIMATE: | $277,725 |
Length: | 8.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2369 | Let Status: | Approved |
Project ID: | C 2175-1-16 | CSJ: | 2175-01-016 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 WEST | Fund Cat: | 1 |
Limits To: | SPUR 144 | ESTIMATE: | $296,826 |
Length: | 6.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2369 | Let Status: | Approved |
Project ID: | C 2175-2-14 | CSJ: | 2175-02-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SPUR 144 | Fund Cat: | 1 |
Limits To: | US 90 EAST | ESTIMATE: | $201,860 |
Length: | 4.4 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 539 | Let Status: | Approved |
Project ID: | C 2233-2-7 | CSJ: | 2233-02-007 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 467 | Fund Cat: | 1 |
Limits To: | GUADALUPE/WILSON COUNTY LINE | ESTIMATE: | $119,853 |
Length: | 3.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1023 | Let Status: | Approved |
Project ID: | C 2563-1-10 | CSJ: | 2563-01-010 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2369 | Fund Cat: | 1 |
Limits To: | US 90 | ESTIMATE: | $54,243 |
Length: | 1.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2438 | Let Status: | Approved |
Project ID: | C 2651-1-11 | CSJ: | 2651-01-011 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | US 90A | ESTIMATE: | $197,348 |
Length: | 6.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 3009 | Let Status: | Approved |
Project ID: | C 3107-1-44 | CSJ: | 3107-01-044 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 46 | Fund Cat: | 1 |
Limits To: | BAT CAVE LOOP | ESTIMATE: | $397,678 |
Length: | 9.2 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 3351 | Let Status: | Approved |
Project ID: | C 3212-3-19 | CSJ: | 3212-03-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | RM 473 | Fund Cat: | 1 |
Limits To: | SH 46 | ESTIMATE: | $412,221 |
Length: | 0.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1403 | Let Status: | Approved |
Project ID: | C 3253-1-9 | CSJ: | 3253-01-009 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 55 | Fund Cat: | 1 |
Limits To: | FM 2369 | ESTIMATE: | $9,931 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0016-05-122 | ||
---|---|---|---|
Length: | 190.2 | ||
Estimate: | $7,601,483 | ||
Actual: | |||
CCSJ: 0016-19-025 |
|||
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 482 | Let Status: | Approved |
Project ID: | C 16-19-25 | CSJ: | 0016-19-025 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 35 N | Fund Cat: | 1 |
Limits To: | IH 35 S | ESTIMATE: | $242,524 |
Length: | 7.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | C 17-2-79 | CSJ: | 0017-02-079 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 410 | Fund Cat: | 1 |
Limits To: | NEW LAREDO HIGHWAY | ESTIMATE: | $13,116 |
Length: | 0.3 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | C 17-9-107 | CSJ: | 0017-09-107 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | IH 410 | Fund Cat: | 1 |
Limits To: | SOMERSET ROAD | ESTIMATE: | $88,732 |
Length: | 2.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | C 17-9-108 | CSJ: | 0017-09-108 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | NEW LAREDO HIGHWAY | Fund Cat: | 1 |
Limits To: | SOMERSET ROAD | ESTIMATE: | $71,245 |
Length: | 2.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 132 | Let Status: | Approved |
Project ID: | C 17-14-19 | CSJ: | 0017-14-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | MEDINA/ATASCOSA COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 471 (WALTON ST.) | ESTIMATE: | $232,368 |
Length: | 3.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | US 90 | Let Status: | Approved |
Project ID: | C 24-6-68 | CSJ: | 0024-06-068 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CR 4643 (DUNLAY RD) | Fund Cat: | 1 |
Limits To: | FM 1343 | ESTIMATE: | $457,316 |
Length: | 5.4 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-5-73 | CSJ: | 0073-05-073 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 1.4 NI N OF FM 791 | Fund Cat: | 1 |
Limits To: | 0.5 MI N OF PULLIN ROAD | ESTIMATE: | $313,060 |
Length: | 10.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-54 | CSJ: | 0073-10-054 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | CASAREZ ROAD | Fund Cat: | 1 |
Limits To: | SH 97 | ESTIMATE: | $77,776 |
Length: | 2.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-55 | CSJ: | 0073-10-055 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 97 | Fund Cat: | 1 |
Limits To: | END FRONTAGE ROAD | ESTIMATE: | $69,464 |
Length: | 2.4 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-56 | CSJ: | 0073-10-056 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.5 MI N OF PULLIN ROAD | Fund Cat: | 1 |
Limits To: | SS 199 (LEAL ROAD) | ESTIMATE: | $58,304 |
Length: | 1.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-57 | CSJ: | 0073-10-057 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | ATASCOSA RIVER | Fund Cat: | 1 |
Limits To: | CORGEY ROAD | ESTIMATE: | $24,936 |
Length: | 0.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-58 | CSJ: | 0073-10-058 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 281N | Fund Cat: | 1 |
Limits To: | 0.5 MI N OF PULLIN ROAD | ESTIMATE: | $112,244 |
Length: | 1.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | IH 37 | Let Status: | Approved |
Project ID: | C 73-10-59 | CSJ: | 0073-10-059 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.5 MI N OF PULLIN ROAD | Fund Cat: | 1 |
Limits To: | US 281 SOUTH | ESTIMATE: | $220,825 |
Length: | 1.4 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | US 87 | Let Status: | Approved |
Project ID: | C 143-3-50 | CSJ: | 0143-03-050 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BEXAR/WILSONCOUNTY LINE | Fund Cat: | 1 |
Limits To: | POST OAK RD. | ESTIMATE: | $514,216 |
Length: | 7.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | US 87 | Let Status: | Approved |
Project ID: | C 143-4-69 | CSJ: | 0143-04-069 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 539 | Fund Cat: | 1 |
Limits To: | FM 538 | ESTIMATE: | $298,580 |
Length: | 9.2 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | US 57 | Let Status: | Approved |
Project ID: | C 276-7-32 | CSJ: | 0276-07-032 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 140 | Fund Cat: | 1 |
Limits To: | IH 35 | ESTIMATE: | $550,265 |
Length: | 13.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | SH 97 | Let Status: | Approved |
Project ID: | C 328-2-45 | CSJ: | 0328-02-045 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BU 181 | Fund Cat: | 1 |
Limits To: | US 181 | ESTIMATE: | $20,726 |
Length: | 0.6 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 541 | Let Status: | Approved |
Project ID: | C 366-9-33 | CSJ: | 0366-09-033 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 181 | Fund Cat: | 1 |
Limits To: | SH 123 | ESTIMATE: | $327,305 |
Length: | 10.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 462 | Let Status: | Approved |
Project ID: | C 848-1-42 | CSJ: | 0848-01-042 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2200 | Fund Cat: | 1 |
Limits To: | FRIO/MEDINA COUNTY LINE | ESTIMATE: | $232,733 |
Length: | 5.4 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 463 | Let Status: | Approved |
Project ID: | C 849-6-7 | CSJ: | 0849-06-007 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 132 | Fund Cat: | 1 |
Limits To: | IH 35 | ESTIMATE: | $34,732 |
Length: | 0.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 3432 | Let Status: | Approved |
Project ID: | C 850-4-30 | CSJ: | 0850-04-030 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | WILSON/BEXAR COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 775 | ESTIMATE: | $131,511 |
Length: | 4.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1334 | Let Status: | Approved |
Project ID: | C 853-3-6 | CSJ: | 0853-03-006 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 281 | Fund Cat: | 1 |
Limits To: | .15 MI E JOE K. WILLIAMS ROAD | ESTIMATE: | $40,027 |
Length: | 1.2 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 537 | Let Status: | Approved |
Project ID: | C 1009-2-19 | CSJ: | 1009-02-019 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 181 | Fund Cat: | 1 |
Limits To: | FM 1922 | ESTIMATE: | $192,469 |
Length: | 0.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2252 | Let Status: | Approved |
Project ID: | C 1433-2-48 | CSJ: | 1433-02-048 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 482 | Fund Cat: | 1 |
Limits To: | FM 3009 | ESTIMATE: | $94,885 |
Length: | 2.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1346 | Let Status: | Approved |
Project ID: | C 1437-2-17 | CSJ: | 1437-02-017 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 87 | Fund Cat: | 1 |
Limits To: | FM 775 | ESTIMATE: | $35,328 |
Length: | 0.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 3499 | Let Status: | Approved |
Project ID: | C 1479-2-5 | CSJ: | 1479-02-005 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 1937 | Fund Cat: | 1 |
Limits To: | LP 1604 | ESTIMATE: | $18,418 |
Length: | 0.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1582 | Let Status: | Approved |
Project ID: | C 1500-1-26 | CSJ: | 1500-01-026 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SPUR 581 | Fund Cat: | 1 |
Limits To: | SH 85 | ESTIMATE: | $348,020 |
Length: | 9.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 1937 | Let Status: | Approved |
Project ID: | C 2255-1-86 | CSJ: | 2255-01-086 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 281 | Fund Cat: | 1 |
Limits To: | LP 1604 | ESTIMATE: | $217,135 |
Length: | 6.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 624 | Let Status: | Approved |
Project ID: | C 2373-2-18 | CSJ: | 2373-02-018 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LASALLE/MCMULLEN COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 16 | ESTIMATE: | $551,147 |
Length: | 14.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 624 | Let Status: | Approved |
Project ID: | C 2373-3-16 | CSJ: | 2373-03-016 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | MCMULLEN/LIVE OAK COUNTY LINE | ESTIMATE: | $635,709 |
Length: | 16.1 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2536 | Let Status: | Approved |
Project ID: | C 2440-1-26 | CSJ: | 2440-01-026 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | IH 410 | ESTIMATE: | $128,662 |
Length: | 3.9 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 2537 | Let Status: | Approved |
Project ID: | C 2441-1-13 | CSJ: | 2441-01-013 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | PLEASANTON ROAD | Fund Cat: | 1 |
Limits To: | US 281 | ESTIMATE: | $48,770 |
Length: | 1.5 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 775 | Let Status: | Approved |
Project ID: | C 3440-1-14 | CSJ: | 3440-01-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 3432 | Fund Cat: | 1 |
Limits To: | FM 1303 | ESTIMATE: | $340,485 |
Length: | 0.0 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | Oct 2022 |
Highway: | FM 3510 | Let Status: | Approved |
Project ID: | C 3576-1-5 | CSJ: | 3576-01-005 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 3351 | Fund Cat: | 1 |
Limits To: | SH 97 | ESTIMATE: | $58,221 |
Length: | 1.5 | Actual | $0 |
Back... | Totals for 0016-19-025 | ||
Length: | 152.7 | ||
Estimate: | $6,801,254 | ||
Actual: | |||
CCSJ: 0915-17-076 |
|||
District: | SAN ANTONIO | Let Date: | May 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ()TP | CSJ: | 0915-17-076 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | LC |
Limits From: | IN NEW BRAUNFELS ON COMMON ST. | Fund Cat: | 3 |
Limits To: | FROM LIBERTY AVE. TO SH 46/LP 337 | ESTIMATE: | $1,321,637 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0915-17-076 | ||
Length: | 0 | ||
Estimate: | $1,321,637 | ||
Actual: | |||
CCSJ: 1433-02-044 |
|||
District: | SAN ANTONIO | Let Date: | May 2023 |
Highway: | FM 2252 | Let Status: | Tentative |
Project ID: | STP ()MM | CSJ: | 1433-02-044 |
Description: | WIDEN ROAD - ADD LANES | Handling Code: | |
Limits From: | BEXAR/COMAL COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 3009 | ESTIMATE: | $37,400,000 |
Length: | 2.7 | Actual | $0 |
District: | SAN ANTONIO | Let Date: | May 2023 |
Highway: | FM 2252 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1433-01-028 |
Description: | WIDEN ROAD - ADD LANES | Handling Code: | |
Limits From: | EVANS ROAD | Fund Cat: | 11 |
Limits To: | COMAL/BEXAR COUNTY LINE | ESTIMATE: | $500,000 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 1433-02-044 | ||
Length: | 2.8 | ||
Estimate: | $37,900,000 | ||
Actual: | |||
CCSJ: 1728-02-065 |
|||
District: | SAN ANTONIO | Let Date: | Jul 2023 |
Highway: | FM 306 | Let Status: | Tentative |
Project ID: | STP ()MM | CSJ: | 1728-02-065 |
Description: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Handling Code: | |
Limits From: | GUADALUPE RIVER- EASTERN CROSSSING | Fund Cat: | 1 |
Limits To: | GUADALUPE RIVER- WESTERN CROSSING | ESTIMATE: | $3,502,400 |
Length: | 0.4 | Actual | $0 |
Back... | Totals for 1728-02-065 | ||
Length: | 0.4 | ||
Estimate: | $3,502,400 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |