Detail Letting Schedule for Guadalupe County (FY 2023)

Last Update: Friday, June 24, 2022

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Guadalupe County (FY 2023)

CCSJ: 0025-04-051

District:SAN ANTONIOLet Date:Jul 2023
Highway:UA 90Let Status:Tentative
Project ID:STP()HESCSJ:0025-04-051
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:500 FT EAST OF WEBER RDFund Cat:8
Limits To:500 FT WEST OF CR 202 (AUX AIRPORT RD)ESTIMATE:$1,174,372
Length:1.2Actual$0
 
Back...
Totals for 0025-04-051
Length:1.2
Estimate:$1,174,372
Actual:

CCSJ: 0025-10-097

District:SAN ANTONIOLet Date:Apr 2023
Highway:FM 78Let Status:Tentative
Project ID:STP ()HESCSJ:0025-10-097
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:FLEMING STFund Cat:8
Limits To:200' EAST OF 8TH STESTIMATE:$1,392,031
Length:0.6Actual$0
 
Back...
Totals for 0025-10-097
Length:0.6
Estimate:$1,392,031
Actual:

CCSJ: 0366-02-094

District:SAN ANTONIOLet Date:Feb 2023
Highway:SH 123Let Status:Tentative
Project ID:NH ()CSJ:0366-02-094
Description:RESURFACE ROADWAYHandling
Code:
 
Limits From:FM 20Fund Cat:1
Limits To:FM 758ESTIMATE:$8,297,557
Length:5.7Actual$0
 
Back...
Totals for 0366-02-094
Length:5.7
Estimate:$8,297,557
Actual:

CCSJ: 0915-46-054

District:SAN ANTONIOLet Date:Jul 2023
Highway:VALet Status:Tentative
Project ID:STP ()MMCSJ:0915-46-054
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
LC
Limits From:IN CIBOLO FROM SHAETHER ROAD/RECREATIONFund Cat:3
Limits To:FM 1103, SCHLATHER PARKESTIMATE:$1,443,964
Length:0.0Actual$0
 
Back...
Totals for 0915-46-054
Length:0
Estimate:$1,443,964
Actual:

CCSJ: 2021-02-018

District:SAN ANTONIOLet Date:Aug 2023
Highway:FM 1044Let Status:Tentative
Project ID:STP ( )FRS1CSJ:2021-02-018
Description:RAILROAD CROSSING IMPROVEMENTSHandling
Code:
XX
Limits From:0.1 MI N OF FM 78Fund Cat:8
Limits To:FM 78ESTIMATE:$450,000
Length:0.1Actual$0
 
Back...
Totals for 2021-02-018
Length:0.1
Estimate:$450,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract