Detail Letting Schedule for Houston County (FY 2023)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Houston County (FY 2023) |
CCSJ: 2707-01-011 |
|||
District: | LUFKIN | Let Date: | Nov 2022 |
Highway: | FM 2781 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 2707-01-011 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | CR 551 | Fund Cat: | 1 |
Limits To: | TRINITY COUNTY LINE | ESTIMATE: | $3,825,206 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2022 |
Highway: | FM 2781 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2707-01-014 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 7 | Fund Cat: | 1 |
Limits To: | COUNTY ROAD 551 | ESTIMATE: | $8,270,000 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2022 |
Highway: | FM 2781 | Let Status: | Tentative |
Project ID: | STP () | CSJ: | 2707-02-008 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | HOUSTON COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 358 | ESTIMATE: | $571,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 2707-01-011 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $12,666,206 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |