Letting Schedule for Yoakum District (FY 2023)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Yoakum District (FY 2023) |
Austin | Calhoun | Colorado | Dewitt | Fayette | Gonzales | Jackson | Matagorda | Victoria | Wharton | | |||||||
Austin County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0187-02-070 | SH 36 | Tentative | Feb 2023 | $307,391 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0913-20-092 | CR | Tentative | Jun 2023 | $1,520,820 | 6 | BRIDGE REPLACEMENT | 0.0 |
Calhoun County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0420-03-018 | SH 172 | Tentative | May 2023 | $2,828,913 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0913-19-037 | CR | Tentative | Feb 2023 | $236,545 | 10 | STATE PARK IMPROVEMENTS | 0.0 |
Colorado County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0266-02-069 | SH 71 | Tentative | Jul 2023 | $2,553,205 | 8 | INSTALL RAISED MEDIAN | 0.0 |
0913-26-064 | CR | Tentative | Nov 2022 | $1,305,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
Dewitt County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0913-17-044 | VA | Tentative | Nov 2022 | $130,000 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0913-17-045 | CR | Tentative | Jul 2023 | $475,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0839-04-013 | FM 951 | Tentative | Feb 2023 | $885,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0143-08-100 | US 87 | Tentative | Jan 2023 | $750,000 | 11 | BRIDGE REPLACEMENT | 0.0 |
Fayette County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0267-02-038 | SH 159 | Tentative | Apr 2023 | $16,200,000 | 11 | SURFACING/ROADWAY RESTORATION | 0.0 |
0268-01-056 | US 77 | Tentative | Dec 2022 | $2,947,894 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0026-03-046 | US 90 | Tentative | Apr 2023 | $7,040,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0913-28-088 | CR | Tentative | Dec 2022 | $1,329,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0913-28-093 | VA | Tentative | Jun 2023 | $805,000 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0913-28-083 | CR | Tentative | Mar 2023 | $1,983,700 | 6 | BRIDGE REPLACEMENT | 0.0 |
Gonzales County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0913-22-016 | CR | Tentative | Apr 2023 | $1,200,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0913-22-051 | CR | Tentative | Apr 2023 | $405,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
0025-05-024 | UA 90 | Tentative | Nov 2022 | $13,044,040 | 1 | SEAL COAT | 0.0 |
Jackson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0346-01-040 | SH 111 | Tentative | Dec 2022 | $9,731,200 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0089-11-007 | SL 521 | Tentative | Mar 2023 | $2,310,200 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
1090-04-018 | FM 1593 | Tentative | Jul 2023 | $13,223,823 | 11 | WIDEN ROAD - ADD LANES | 0.0 |
Matagorda County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0179-04-102 | SH 35 | Tentative | May 2023 | $400,157 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0913-21-052 | CR | Approved | Oct 2022 | $400,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
Victoria County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2350-01-060 | SL 463 | Approved | Oct 2022 | $13,477,016 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0088-05-096 | US 59 | Tentative | Aug 2023 | $44,763,400 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0913-27-091 | CS | Tentative | May 2023 | $58,003 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0913-27-093 | CR | Tentative | Jul 2023 | $532,000 | 6 | BRIDGE REPLACEMENT | 0.0 |
Wharton County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0089-06-092 | US 59 | Tentative | Jul 2023 | $4,812,370 | 8 | INSTALL RAISED MEDIAN | 0.0 |
1412-03-038 | FM 1301 | Approved | Oct 2022 | $13,000,000 | 3 | HIGHWAY IMPROVEMENT | 0.0 |
0089-10-026 | SH 60 | Approved | Oct 2022 | $3,300,000 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
|