Detail Letting Schedule for Mclennan County (FY 2023)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Mclennan County (FY 2023) |
CCSJ: 0014-10-064 |
|||
District: | WACO | Let Date: | Jun 2023 |
Highway: | BU 77-L | Let Status: | Tentative |
Project ID: | C 14-10-64 | CSJ: | 0014-10-064 |
Description: | RECONSTRUCT EXISTING ROADWAY | Handling Code: | |
Limits From: | IH 35 | Fund Cat: | 1 |
Limits To: | SL 574 | ESTIMATE: | $13,728,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0014-10-064 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $13,728,000 | ||
Actual: | |||
CCSJ: 0209-01-071 |
|||
District: | WACO | Let Date: | Jun 2023 |
Highway: | US 77 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0209-01-071 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | @ FM 3148 | Fund Cat: | 8 |
Limits To: | @FM 3148 | ESTIMATE: | $190,807 |
Length: | 0.2 | Actual | $0 |
District: | WACO | Let Date: | Jun 2023 |
Highway: | US 77 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0209-01-072 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | @ LYNDALE DR | Fund Cat: | 8 |
Limits To: | @ LYNDALE DR | ESTIMATE: | $198,653 |
Length: | 0.1 | Actual | $0 |
District: | WACO | Let Date: | Jun 2023 |
Highway: | FM 1695 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 2506-01-044 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | @ REGAL DR | Fund Cat: | 8 |
Limits To: | @ REGAL DR | ESTIMATE: | $263,217 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0209-01-071 | ||
Length: | 0.5 | ||
Estimate: | $652,677 | ||
Actual: | |||
CCSJ: 0258-08-038 |
|||
District: | WACO | Let Date: | Apr 2023 |
Highway: | SH 6 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0258-08-038 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | .5 MI N OF BAYLOR CAMP RD | Fund Cat: | 8 |
Limits To: | .5 MI S OF BAYLOR CAMP RD | ESTIMATE: | $651,267 |
Length: | 0.5 | Actual | $0 |
Back... | Totals for 0258-08-038 | ||
Length: | 0.5 | ||
Estimate: | $651,267 | ||
Actual: | |||
CCSJ: 0831-04-030 |
|||
District: | WACO | Let Date: | Apr 2023 |
Highway: | FM 1860 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0831-04-030 |
Description: | INTERSECTION IMPROVEMENT | Handling Code: | |
Limits From: | 0.10 MI W OF SH6 | Fund Cat: | 8 |
Limits To: | SH6 | ESTIMATE: | $129,402 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0831-04-030 | ||
Length: | 0 | ||
Estimate: | $129,402 | ||
Actual: | |||
CCSJ: 0909-00-062 |
|||
District: | WACO | Let Date: | Nov 2022 |
Highway: | VA | Let Status: | Tentative |
Project ID: | C 909-00-62 | CSJ: | 0909-00-062 |
Description: | BRIDGE MAINTENANCE | Handling Code: | |
Limits From: | HILLSBORO AREA OFFICE | Fund Cat: | 1 |
Limits To: | MCLENNAN AREA OFFICE | ESTIMATE: | $2,875,022 |
Length: | 0.0 | Actual | $1,726,900 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0909-00-062 | ||
Length: | 0 | ||
Estimate: | $2,875,022 | ||
Actual: | $1,726,900 | ||
CCSJ: 0909-22-193 |
|||
District: | WACO | Let Date: | Mar 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ()TAPS | CSJ: | 0909-22-193 |
Description: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Handling Code: | LC |
Limits From: | ALONG MKT EAST RAIL FROM WACO DRIVE | Fund Cat: | 3 |
Limits To: | GHOLSON ROAD | ESTIMATE: | $2,510,929 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0909-22-193 | ||
Length: | 0 | ||
Estimate: | $2,510,929 | ||
Actual: | |||
CCSJ: 0909-22-195 |
|||
District: | WACO | Let Date: | Jan 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ()HESG | CSJ: | 0909-22-195 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | HILLCREST @ MCARTHUR DRIVE | Fund Cat: | 3 |
Limits To: | HILLCREST @ MCARTHUR DRIVE | ESTIMATE: | $251,862 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0909-22-195 | ||
Length: | 0 | ||
Estimate: | $251,862 | ||
Actual: | |||
CCSJ: 2311-01-044 |
|||
District: | WACO | Let Date: | Oct 2022 |
Highway: | FM 3051 | Let Status: | Approved |
Project ID: | STP 2023(050)HES | CSJ: | 2311-01-044 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | 0.15 MI W OF CARSON | Fund Cat: | 8 |
Limits To: | BRAZOS RIVER | ESTIMATE: | $467,580 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 2311-01-044 | ||
Length: | 0 | ||
Estimate: | $467,580 | ||
Actual: | |||
CCSJ: 3448-02-007 |
|||
District: | WACO | Let Date: | Aug 2023 |
Highway: | FM 3268 | Let Status: | Tentative |
Project ID: | STP () | CSJ: | 3448-02-007 |
Description: | WIDEN ROAD - ADD SHOULDERS | Handling Code: | |
Limits From: | FM 185 | Fund Cat: | 1 |
Limits To: | FM 3047 | ESTIMATE: | $1,980,000 |
Length: | 2.3 | Actual | $0 |
Back... | Totals for 3448-02-007 | ||
Length: | 2.3 | ||
Estimate: | $1,980,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |