Timeline - Cedar Hill

 

Timeline - Cedar Hill

Below is a timeline of the Property Exchange - Dallas District Cedar Hill. Substantial Completion will occur at 18 Months (545 calendar days).

Sept. 29, 2011
Authorization by the Texas Transportation Commission to issue request for proposals and qualifications.

Dec. 21, 2011
TxDOT issues request for proposal and qualifications.

Jan. 12, 2012
Pre-Proposal Meeting

Feb. 21, 2012
Deadline to submit proposals and qualifications.

Feb. 29, 2012 thru March 2, 2012
Interviews TxDOT evaluation and short list of top ranked private entities

March 5, 2012 thru March 23, 2012
Selection of best-value proposal and negotiations of Development and Exchange Agreement (DEA) with conditional award, contingent upon commission approval.

April 26, 2012
Authorization by the Texas Transportation Commission to award DEA.

May 18, 2012
Executive DEA, contingent upon receipt of bond and insurance.

June 1, 2012
Issue Notice to Proceed. Construction begins.