Tabulation of Bids for Project STP 2018(769)
| Text version of this page | |||
| County: | GRAYSON | Let Date: | 04/03/18 |
| Type: | LANDSCAPE AND SCENIC ENHANCEMENT | Seq No: | 3015 |
| Time: | 30 WORKING DAYS | Project ID: | STP 2018(769) |
| Highway: | SH 56 | Contract #: | 04183015 |
| Length: | 0.104 | CCSJ: | 0045-02-034 |
| Limits: | |||
| From: | BU 377 B | Check: | $2,000 |
| To: | COLLINSVILLE STREET | Misc Cost: | $10,000.00 |
| Estimate | $114,480.00 | % Over/Under | Company |
| Bidder 1 | $153,070.94 | +33.71% | OLD FIREHOUSE GYM LLC |
| Bidder 2 | $153,354.00 | +33.96% | HARTBEAT CONSTRUCTION |
| Bidder 3 | $184,259.00 | +60.95% | APEX LANDSCAPE & IRRIGATION, LLC |
| Bidder 4 | $191,499.00 | +67.28% | WEST TEXAS REBAR PLACERS INC. |
| Bidder 5 | $218,195.00 | +90.60% | TIGHT LINE CONSTRUCTION, LLC |
| Bidder 6 | $229,908.00 | +100.83% | BXB GROUP INCORPORATION |
| Bidder 7 | $263,536.00 | +130.20% | SJ&J CONSTRUCTION, LLC |
| Bidder 8 | $269,957.95 | +135.81% | ED BELL CONSTRUCTION COMPANY |
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
| 1046001 | REMOVING CONC (PAV) | SY | 702.000 | 8.00 | 1 2 3 4 5 6 7 8 | 7.610 20.000 25.000 15.000 25.000 41.000 20.000 42.000 |
| 1046015 | REMOVING CONC (SIDEWALKS) | SY | 42.000 | 12.00 | 1 2 3 4 5 6 7 8 | 12.000 22.000 25.000 20.000 25.000 32.000 20.000 31.500 |
| 1046021 | REMOVING CONC (CURB) | LF | 742.000 | 10.00 | 1 2 3 4 5 6 7 8 | 4.000 5.000 8.000 9.000 25.000 11.000 8.000 7.350 |
| 1046028 | REMOVING CONC (MISC) | SY | 2.000 | 20.00 | 1 2 3 4 5 6 7 8 | 22.000 25.000 800.000 30.000 600.000 495.000 20.000 315.000 |
| 1106003 | EXCAVATION (SPECIAL) | CY | 68.000 | 40.00 | 1 2 3 4 5 6 7 8 | 9.000 35.000 15.000 50.000 150.000 169.000 70.000 84.000 |
| 1326019 | EMBANKMENT (VEHICLE)(ORD COMP)(TY B) | CY | 31.000 | 30.00 | 1 2 3 4 5 6 7 8 | 31.000 55.000 28.000 40.000 250.000 229.000 30.000 157.500 |
| 1706001 | IRRIGATION SYSTEM | LS | 1.000 | 10,000.00 | 1 2 3 4 5 6 7 8 | 13,036.000 14,000.000 27,500.000 11,000.000 15,000.000 16,295.000 25,000.000 15,000.000 |
| 1926004 | PLANT MATERIAL (5-GAL) | EA | 92.000 | 30.00 | 1 2 3 4 5 6 7 8 | 24.000 16.000 35.000 25.000 45.000 69.000 30.000 60.000 |
| 1926014 | PLANT SOIL MIX | CY | 82.000 | 30.00 | 1 2 3 4 5 6 7 8 | 32.630 35.000 65.000 35.000 100.000 157.000 130.000 175.000 |
| 1926024 | PLANT MATERIAL (30 GAL) (TREE) | EA | 2.000 | 280.00 | 1 2 3 4 5 6 7 8 | 637.250 300.000 300.000 300.000 500.000 797.000 500.000 800.000 |
| 3406104 | D-GR HMA(SQ) TY-D SAC-B PG64-22 | TON | 15.000 | 70.00 | 1 2 3 4 5 6 7 8 | 105.000 150.000 375.000 400.000 500.000 501.000 300.000 200.000 |
| 4166002 | DRILL SHAFT (24 IN) | LF | 25.000 | 80.00 | 1 2 3 4 5 6 7 8 | 125.000 150.000 150.000 200.000 125.000 278.000 100.000 157.500 |
| 5006001 | MOBILIZATION | LS | 1.000 | 10,100.00 | 1 2 3 4 5 6 7 8 | 20,000.000 18,000.000 17,000.000 12,000.000 28,000.000 22,700.000 30,000.000 30,000.000 |
| 5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 2,000.00 | 1 2 3 4 5 6 7 8 | 3,100.000 5,700.000 5,000.000 1,500.000 1,500.000 2,750.000 4,000.000 21,000.000 |
| 5066040003 | BIODEG EROSN CONT LOGS (INSTL) (8") | LF | 100.000 | 5.00 | 1 2 3 4 5 6 7 8 | 5.940 3.000 3.000 3.000 1.000 8.000 8.000 6.300 |
| 5066043003 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 100.000 | 2.00 | 1 2 3 4 5 6 7 8 | 0.920 2.000 1.000 1.000 1.000 2.000 6.000 1.100 |
| 5286002 | COLORED TEXTURED CONC (6") | SY | 310.000 | 70.00 | 1 2 3 4 5 6 7 8 | 165.000 87.000 110.000 180.000 100.000 120.000 150.000 115.000 |
| 5296008 | CONC CURB & GUTTER (TY II) | LF | 745.000 | 18.00 | 1 2 3 4 5 6 7 8 | 26.000 29.000 15.000 50.000 10.000 19.000 30.000 50.000 |
| 5316004 | CURB RAMPS (TY 1) | EA | 2.000 | 1,500.00 | 1 2 3 4 5 6 7 8 | 1,400.000 1,800.000 1,200.000 2,000.000 3,500.000 1,407.000 3,000.000 1,500.000 |
| 5316006 | CURB RAMPS (TY 3) | EA | 1.000 | 1,500.00 | 1 2 3 4 5 6 7 8 | 1,200.000 1,700.000 1,400.000 2,000.000 3,500.000 1,509.000 3,000.000 1,500.000 |
| 5316010 | CURB RAMPS (TY 7) | EA | 2.000 | 1,500.00 | 1 2 3 4 5 6 7 8 | 1,000.000 1,600.000 1,000.000 2,200.000 3,500.000 2,121.000 3,000.000 1,500.000 |
| 5316016 | CURB RAMPS (TY 21) | EA | 3.000 | 1,800.00 | 1 2 3 4 5 6 7 8 | 2,000.000 2,400.000 2,500.000 2,500.000 3,250.000 2,121.000 4,000.000 1,500.000 |
| 6246001 | GROUND BOX TY A (122311) | EA | 1.000 | 800.00 | 1 2 3 4 5 6 7 8 | 1,400.000 615.000 795.000 1,000.000 750.000 1,714.000 2,000.000 525.000 |
| 6446068 | RELOCATE SM RD SN SUP&AM TY 10BWG | EA | 2.000 | 450.00 | 1 2 3 4 5 6 7 8 | 355.000 448.000 250.000 400.000 450.000 1,248.000 500.000 525.000 |
| 6776003 | ELIM EXT PAV MRK & MRKS (8") | LF | 55.000 | 1.00 | 1 2 3 4 5 6 7 8 | 1.280 12.000 20.000 3.000 100.000 9.000 4.000 1.050 |
| 6776008 | ELIM EXT PAV MRK & MRKS (ARROW) | EA | 1.000 | 50.00 | 1 2 3 4 5 6 7 8 | 47.000 200.000 580.000 100.000 1,500.000 308.000 100.000 84.000 |
| 6776009 | ELIM EXT PAV MRK & MRKS (DBL ARROW) | EA | 1.000 | 80.00 | 1 2 3 4 5 6 7 8 | 74.000 250.000 500.000 150.000 1,500.000 308.000 200.000 105.000 |
| 6776012 | ELIM EXT PAV MRK & MRKS (WORD) | EA | 1.000 | 60.00 | 1 2 3 4 5 6 7 8 | 54.000 300.000 500.000 100.000 1,500.000 308.000 200.000 94.500 |
| 10026002 | LANDSCAPE AMENITY (TY 1) | EA | 1.000 | 3,000.00 | 1 2 3 4 5 6 7 8 | 2,500.000 4,700.000 10,000.000 4,000.000 2,500.000 4,744.000 30,000.000 4,200.000 |
| 10056001 | LOOSE AGGR FOR GROUNDCOVER (TYPE I) | CY | 27.000 | 35.00 | 1 2 3 4 5 6 7 8 | 70.080 57.000 200.000 200.000 200.000 289.000 200.000 315.000 |
| 60006004 | INSTALL UNDERGROUND CONDUIT | LF | 324.000 | 30.00 | 1 2 3 4 5 6 7 8 | 8.000 7.000 15.000 9.000 20.000 21.000 50.000 21.000 |