Tabulation of Bids for Project RMC - 632849001
| Text version of this page | |||
| County: | MIDLAND | Let Date: | 04/03/18 |
| Type: | EMERGENCY MBGF REPAIR | Seq No: | 4013 |
| Time: | 366 CALENDAR DAYS | Project ID: | RMC - 632849001 |
| Highway: | IH0020 | Contract #: | 04184013 |
| Length: | 0.001 | CCSJ: | 6328-49-001 |
| Limits: | |||
| From: | VARIOUS | Check: | $9,000 |
| To: | VARIOUS | Misc Cost: | |
| Estimate | $438,552.50 | % Over/Under | Company |
| Bidder 1 | $350,762.00 | -20.02% | T&L CLEANING SERVICES LLC |
| Bidder 2 | $417,172.00 | -4.88% | HJC FARMS, INC. |
| Bidder 3 | $470,904.00 | +7.38% | K-BAR SERVICES, INC. |
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
| 5006033 | MOBILIZATION (CALLOUT) | EA | 20.000 | 500.00 | 1 2 3 | 100.000 250.000 100.000 |
| 5006034 | MOBILIZATION (EMERGENCY) | EA | 30.000 | 500.00 | 1 2 3 | 300.000 250.000 300.000 |
| 5406005 | TERMINAL ANCHOR SECTION | EA | 5.000 | 300.00 | 1 2 3 | 1.000 1.000 100.000 |
| 5406016 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 5.000 | 300.00 | 1 2 3 | 1,200.000 1.000 1,000.000 |
| 5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 5.000 | 100.00 | 1 2 3 | 100.000 1.000 1.000 |
| 5426003 | REMOVE DOWNSTREAM ANCHOR TERMINAL | EA | 5.000 | 100.00 | 1 2 3 | 1.000 1.000 1.000 |
| 5446003 | GUARDRAIL END TREATMENT (REMOVE) | EA | 60.000 | 100.00 | 1 2 3 | 100.000 50.000 100.000 |
| 5446005 | GDRAIL END TRT(INST)(WOOD POST)(TY II) | EA | 20.000 | 5,000.00 | 1 2 3 | 3,000.000 3,250.000 3,500.000 |
| 5446007 | GDRAIL END TRT(INSTALL)(HBA POST) | EA | 40.000 | 3,000.00 | 1 2 3 | 2,900.000 4,250.000 4,000.000 |
| 5456026 | CRASH CUSHION ATTEN (INSTALL) (QUAD)(N) | EA | 2.000 | 20,000.00 | 1 2 3 | 15,000.000 15,000.000 20,000.000 |
| 6586015 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 | EA | 100.000 | 5.00 | 1 2 3 | 30.000 5.000 30.000 |
| 6586028 | INSTL DEL ASSM (D-SY)SZ (BRF)GF1 | EA | 75.000 | 5.00 | 1 2 3 | 30.000 5.000 30.000 |
| 7706001 | REPAIR RAIL ELEMENT (W - BEAM) | LF | 4,500.000 | 20.00 | 1 2 3 | 18.000 20.000 25.000 |
| 7706002 | REPAIR RAIL ELEMENT (THRIE - BEAM) | LF | 25.000 | 10.50 | 1 2 3 | 20.000 1.000 10.000 |
| 7706003 | REP RAIL ELMNT(THRIE-BM TRANS TO W -BM) | LF | 25.000 | 15.00 | 1 2 3 | 20.000 1.000 10.000 |
| 7706004 | REPAIR RAIL ELEMENT (CURVED RAIL) | LF | 250.000 | 20.00 | 1 2 3 | 20.000 1.000 20.000 |
| 7706010 | REM / REPL TIMBER/STL POST W/O CONC FND | EA | 300.000 | 50.00 | 1 2 3 | 38.000 50.000 50.000 |
| 7706011 | REM / REPL TIMBER / STL POST W/CONC FND | EA | 15.000 | 40.00 | 1 2 3 | 50.000 40.000 80.000 |
| 7706016 | REPAIR STEEL POST WITH BASE PLATE | EA | 25.000 | 100.00 | 1 2 3 | 150.000 1.000 200.000 |
| 7706017 | REALIGN POSTS | EA | 150.000 | 5.00 | 1 2 3 | 10.000 5.000 20.000 |
| 7706019 | REMOVE & REPLACE BLOCKOUT | EA | 300.000 | 15.00 | 1 2 3 | 10.000 15.000 18.000 |
| 7706023 | REPAIR OF TERMINAL ANCHORS POSTS | EA | 2.000 | 20.00 | 1 2 3 | 1.000 1.000 22.000 |
| 7726005 | POST AND CABLE FENCE(REMV / REPL POSTS) | EA | 50.000 | 40.00 | 1 2 3 | 50.000 35.000 60.000 |
| 7726006 | POST AND CABLE FENCE(RMV/REPL CNC ANCH) | EA | 10.000 | 40.00 | 1 2 3 | 10.000 35.000 150.000 |
| 7726007 | POST AND CABLE FENCE (REMV/ REPL CABLE) | LF | 500.000 | 5.00 | 1 2 3 | 1.000 4.000 4.000 |
| 7726009 | POST AND CABLE FENCE (REPAIR) | LF | 500.000 | 7.50 | 1 2 3 | 1.000 1.000 8.000 |
| 61856002 | TMA (STATIONARY) | DAY | 50.000 | 300.00 | 1 2 3 | 100.000 400.000 300.000 |