The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Text version of this page
County:BEXARLet Date:05/03/24
Type:LANDSCAPE DEVELOPMENTSeq No:3241
Time:146 WORKING DAYSProject ID:C 24-8-148
Highway:US 90Contract #:05243241
Length:1.930CCSJ:0024-08-148
Limits: 
From:0.27 MILES EAST OF 36TH STCheck:$12,000
To:1.66 MILES WEST OF 36TH STMisc Cost:
Estimate$618,864.48% Over/UnderCompany
Bidder 1$484,934.12-21.64%APEX LANDSCAPE & IRRIGATION, LLC
Bidder 2$526,036.00-15.00%TIGHT LINE CONSTRUCTION, LLC
Bidder 3$534,938.00-13.56%ENCINO LANDSCAPE, INC.
Bidder 4$544,001.00-12.10%DIAMOND R CONTRACTING, LLC
Bidder 5$913,383.05+47.59%YELLOWSTONE LANDSCAPE - CENTRAL, INC.
Item CodeDescriptionUnitQuantityUnit Est.BidderUnit Bid
1616012GENERAL USE COMPOSTCY1,245.00040.001
2
3
4
5
18.820
35.000
50.000
25.000
42.033
1706001IRRIGATION SYSTEMLS1.000160,000.001
2
3
4
5
155,300.000
125,000.000
100,000.000
150,000.000
119,179.860
1926002PLANT MATERIAL (1-GAL)EA914.00020.001
2
3
4
5
10.000
10.000
15.000
15.000
9.657
1926004PLANT MATERIAL (5-GAL)EA509.00035.001
2
3
4
5
27.500
35.000
35.000
30.000
31.490
1926005PLANT MATERIAL (15-GAL)EA556.000150.001
2
3
4
5
150.000
150.000
175.000
110.000
140.217
1926006PLANT MATERIAL (30-GAL)EA66.000260.001
2
3
4
5
350.000
350.000
275.000
500.000
322.720
1926013MULCHSY11,564.0003.001
2
3
4
5
2.480
3.000
5.000
3.500
21.252
1926016PLANT BED PREPARATIONSY11,564.0005.001
2
3
4
5
2.250
3.000
2.000
2.000
3.494
1926049PLANT MATERIAL (MIN 4' TRNK HT) (PALM)EA19.0001,000.001
2
3
4
5
1,200.000
700.000
500.000
1,000.000
1,772.667
1936001PLANT MAINTENANCEMO9.0002,000.001
2
3
4
5
1,250.000
2,000.000
1,500.000
3,000.000
1,275.364
1936003PLANT REPLACEMENT (1-GAL)EA92.00015.001
2
3
4
5
10.000
10.000
1.000
50.000
10.812
1936005PLANT REPLACEMENT (5-GAL)EA54.00030.001
2
3
4
5
28.000
35.000
1.000
100.000
35.505
1936007IRRIGATION SYSTEM OPER AND MAINTMO9.0001,500.001
2
3
4
5
750.000
1,500.000
1,000.000
3,000.000
16,167.123
5006001MOBILIZATIONLS1.00061,485.481
2
3
4
5
51,000.000
55,000.000
70,000.000
60,000.000
92,541.662
5026001008BARRICADES, SIGNS AND TRAFFIC HANDLINGMO9.0005,000.001
2
3
4
5
2,370.000
3,500.000
2,000.000
2,500.000
1,661.667
5066041002BIODEG EROSN CONT LOGS (INSTL) (12")LF3,002.0006.001
2
3
4
5
2.000
6.000
8.000
2.000
3.958
5066043002BIODEG EROSN CONT LOGS (REMOVE)LF300.0001.001
2
3
4
5
1.000
5.000
0.010
2.100
0.358
61856005002TMA (MOBILE OPERATION)DAY2.000800.001
2
3
4
5
1.000
500.000
300.000
2,000.000