Tabulation of Bids for Project C 815-3-15
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | DENTON | Let Date: | 05/04/23 |
Type: | REHABILITATE EXISTING ROADWAY | Seq No: | 3028 |
Time: | 116 WORKING DAYS | Project ID: | C 815-3-15 |
Highway: | FM 424 | Contract #: | 05233028 |
Length: | 1.546 | CCSJ: | 0815-03-015 |
Limits: | |||
From: | US 380 | Check: | $37,000 |
To: | US 377 | Misc Cost: |
Estimate | $1,827,904.81 | % Over/Under | Company |
Bidder 1 | $2,064,269.71 | +12.93% | ED BELL CONSTRUCTION COMPANY |
Bidder 2 | $2,148,448.26 | +17.54% | TEXAS MATERIALS GROUP, INC. |
Bidder 3 | $2,156,449.69 | +17.97% | EUROVIA ATLANTIC COAST LLC |
Bidder 4 | $2,531,180.54 | +38.47% | JAGOE-PUBLIC COMPANY |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 48.000 | 1,300.00 | 1 2 3 4 | 1,500.000 4,000.000 850.000 2,000.000 |
1046017 | REMOVING CONC (DRIVEWAYS) | SY | 543.000 | 12.00 | 1 2 3 4 | 21.000 30.000 26.000 20.000 |
1056096 | REMOV STAB BASE AND ASPH PAV (0"-12") | SY | 1,821.000 | 2.65 | 1 2 3 4 | 21.000 8.250 11.000 40.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 832.000 | 16.00 | 1 2 3 4 | 3.000 20.000 100.000 50.000 |
1326006 | EMBANKMENT (FINAL)(DENS CONT)(TY C) | CY | 2,197.000 | 30.00 | 1 2 3 4 | 31.500 29.000 75.000 65.000 |
1346004 | BACKFILL (TY A OR B) | STA | 81.700 | 220.00 | 1 2 3 4 | 200.000 375.000 420.000 180.000 |
1506001 | BLADING | STA | 48.000 | 160.00 | 1 2 3 4 | 200.000 160.000 190.000 1,600.000 |
1616017 | COMPOST MANUF TOPSOIL (4") | SY | 38,195.000 | 1.40 | 1 2 3 4 | 0.700 1.500 1.240 3.200 |
1646035 | DRILL SEEDING (PERM) (RURAL) (CLAY) | SY | 38,195.000 | 0.23 | 1 2 3 4 | 0.200 0.360 0.360 0.230 |
1646051 | DRILL SEED (TEMP)(WARM OR COOL) | SY | 12,732.000 | 0.25 | 1 2 3 4 | 0.400 0.360 0.360 0.150 |
1686001 | VEGETATIVE WATERING | MG | 7,576.000 | 7.00 | 1 2 3 4 | 1.000 0.010 1.000 5.000 |
3516008 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | SY | 200.000 | 130.00 | 1 2 3 4 | 150.000 220.000 200.000 125.000 |
4036001 | TEMPORARY SPL SHORING | SF | 455.000 | 36.00 | 1 2 3 4 | 70.000 60.000 40.000 57.000 |
4326051 | RIPRAP (STONE COMMON)(GROUT)(18 IN) | CY | 31.000 | 180.00 | 1 2 3 4 | 525.000 600.000 450.000 290.000 |
4646003001 | RC PIPE (CL III)(18 IN) | LF | 246.000 | 75.00 | 1 2 3 4 | 120.000 70.000 58.000 115.000 |
4646005001 | RC PIPE (CL III)(24 IN) | LF | 210.000 | 90.00 | 1 2 3 4 | 125.000 95.000 80.000 140.000 |
4646012001 | RC PIPE (CL III)(60 IN) | LF | 38.000 | 375.00 | 1 2 3 4 | 1,000.000 630.000 425.000 700.000 |
4666105 | HEADWALL (CH - PW - 0) (DIA= 60 IN) | EA | 2.000 | 26,400.00 | 1 2 3 4 | 27,500.000 27,000.000 18,000.000 25,000.000 |
4676363 | SET (TY II) (18 IN) (RCP) (6: 1) (P) | EA | 22.000 | 900.00 | 1 2 3 4 | 1,000.000 1,500.000 1,250.000 2,000.000 |
4676395 | SET (TY II) (24 IN) (RCP) (6: 1) (P) | EA | 6.000 | 1,600.00 | 1 2 3 4 | 1,500.000 1,800.000 1,555.000 2,200.000 |
4806001 | CLEAN EXIST CULVERTS | EA | 2.000 | 2,600.00 | 1 2 3 4 | 750.000 5,400.000 2,500.000 3,900.000 |
4966004 | REMOV STR (SET) | EA | 28.000 | 370.00 | 1 2 3 4 | 400.000 140.000 120.000 410.000 |
4966005 | REMOV STR (WINGWALL) | EA | 2.000 | 1,500.00 | 1 2 3 4 | 6,000.000 900.000 750.000 1,600.000 |
4966007 | REMOV STR (PIPE) | LF | 456.000 | 22.00 | 1 2 3 4 | 20.000 12.000 10.000 100.000 |
5006001 | MOBILIZATION | LS | 1.000 | 166,100.00 | 1 2 3 4 | 206,400.000 210,000.000 200,000.000 250,000.540 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 22,000.00 | 1 2 3 4 | 31,500.000 10,000.000 28,000.000 41,000.000 |
5066002005 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 130.000 | 35.00 | 1 2 3 4 | 60.500 175.000 43.530 58.000 |
5066011005 | ROCK FILTER DAMS (REMOVE) | LF | 130.000 | 17.00 | 1 2 3 4 | 30.250 45.000 14.600 17.500 |
5066020005 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 105.000 | 30.00 | 1 2 3 4 | 26.400 60.000 46.420 38.000 |
5066024005 | CONSTRUCTION EXITS (REMOVE) | SY | 105.000 | 8.50 | 1 2 3 4 | 13.200 20.000 12.590 13.000 |
5066038005 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 44.000 | 3.30 | 1 2 3 4 | 3.300 23.250 23.060 7.000 |
5066039005 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 44.000 | 0.90 | 1 2 3 4 | 1.100 6.500 6.460 1.200 |
5066041005 | BIODEG EROSN CONT LOGS (INSTL) (12") | LF | 605.000 | 5.78 | 1 2 3 4 | 4.400 6.000 5.880 7.000 |
5066043005 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 605.000 | 1.70 | 1 2 3 4 | 1.100 2.500 2.430 1.200 |
5306005 | DRIVEWAYS (ACP) | SY | 871.000 | 60.00 | 1 2 3 4 | 75.000 85.000 85.000 57.000 |
5306017 | DRIVEWAYS (CONC) (HES) | SY | 543.000 | 130.00 | 1 2 3 4 | 157.500 162.000 145.000 150.000 |
5336001 | RUMBLE STRIPS (SHOULDER) | LF | 15,516.000 | 0.25 | 1 2 3 4 | 0.330 0.200 0.440 0.300 |
5336002 | RUMBLE STRIPS (CENTERLINE) | LF | 7,758.000 | 0.25 | 1 2 3 4 | 0.330 0.200 0.440 0.300 |
5606011 | MAILBOX INSTALL-S (TWW-POST) TY 4 | EA | 10.000 | 550.00 | 1 2 3 4 | 302.500 300.000 280.000 320.000 |
6446001 | IN SM RD SN SUP&AM TY10BWG(1)SA(P) | EA | 14.000 | 800.00 | 1 2 3 4 | 687.500 650.000 710.000 725.000 |
6446004 | IN SM RD SN SUP&AM TY10BWG(1)SA(T) | EA | 2.000 | 960.00 | 1 2 3 4 | 863.500 900.000 850.000 915.000 |
6446007 | IN SM RD SN SUP&AM TY10BWG(1)SA(U) | EA | 1.000 | 1,200.00 | 1 2 3 4 | 1,023.000 1,100.000 900.000 1,100.000 |
6446036 | IN SM RD SN SUP&AM TYS80(1)SA(U-BM) | EA | 1.000 | 1,300.00 | 1 2 3 4 | 1,133.000 1,250.000 1,300.000 1,200.000 |
6586099 | INSTL OM ASSM (OM-2Z)(WFLX)GND | EA | 4.000 | 130.00 | 1 2 3 4 | 55.000 60.000 60.000 60.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 408.000 | 0.23 | 1 2 3 4 | 5.000 1.000 2.000 2.800 |
6666030007 | REFL PAV MRK TY I (W)8"(DOT)(100MIL) | LF | 450.000 | 2.00 | 1 2 3 4 | 1.320 1.200 1.500 2.300 |
6666036007 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | LF | 1,710.000 | 1.05 | 1 2 3 4 | 0.990 0.900 1.150 1.700 |
6666048007 | REFL PAV MRK TY I (W)24"(SLD)(100MIL) | LF | 135.000 | 7.00 | 1 2 3 4 | 7.700 7.000 8.500 8.100 |
6666054007 | REFL PAV MRK TY I (W)(ARROW)(100MIL) | EA | 10.000 | 135.00 | 1 2 3 4 | 130.900 119.000 175.000 170.000 |
6666078007 | REFL PAV MRK TY I (W)(WORD)(100MIL) | EA | 11.000 | 150.00 | 1 2 3 4 | 136.400 124.000 225.000 190.000 |
6666141007 | REFL PAV MRK TY I (Y)12"(SLD)(100MIL) | LF | 470.000 | 5.00 | 1 2 3 4 | 2.750 2.500 4.250 5.200 |
6666309007 | RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) | LF | 15,711.000 | 0.57 | 1 2 3 4 | 0.640 0.580 0.780 1.200 |
6666321007 | RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) | LF | 17,970.000 | 0.80 | 1 2 3 4 | 0.640 0.580 0.780 1.200 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 450.000 | 4.00 | 1 2 3 4 | 3.840 3.490 5.000 5.800 |
30776001 | SP MIXES SP-B PG64-22 | TON | 2,348.000 | 110.00 | 1 2 3 4 | 125.000 135.000 135.000 120.000 |
30776013 | SP MIXES SP-C SAC-B PG64-22 | TON | 4,027.000 | 125.00 | 1 2 3 4 | 140.000 137.000 132.000 125.000 |
30776075 | TACK COAT | GAL | 2,663.000 | 3.50 | 1 2 3 4 | 1.750 4.250 2.850 1.750 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 2.000 | 20,000.00 | 1 2 3 4 | 7,500.000 7,000.000 17,500.000 25,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 25.000 | 300.00 | 1 2 3 4 | 150.000 1,490.000 330.000 500.000 |
61856003002 | TMA (MOBILE OPERATION) | HR | 35.000 | 110.00 | 1 2 3 4 | 75.000 110.000 100.000 150.000 |