Tabulation of Bids for Project C 915-00-238
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | BEXAR | Let Date: | 05/05/22 |
Type: | PURCHASE AND INSTALL SIGNS & EQUIP | Seq No: | 3223 |
Time: | 290 WORKING DAYS | Project ID: | C 915-00-238 |
Highway: | VA | Contract #: | 05223223 |
Length: | 0.001 | CCSJ: | 0915-00-238 |
Limits: | |||
From: | DISTRICTWIDE GUIDE SIGNS FY 2022 | Check: | $43,000 |
To: | . | Misc Cost: |
Estimate | $2,174,551.20 | % Over/Under | Company |
Bidder 1 | $1,675,784.44 | -22.94% | THE LEVY COMPANY, INC. |
Bidder 2 | $2,163,531.45 | -0.51% | MICA CORPORATION |
Bidder 3 | $2,517,240.00 | +15.76% | E-Z BEL CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4166004 | DRILL SHAFT (36 IN) | LF | 34.000 | 253.00 | 1 2 3 | 290.830 454.000 430.000 |
4166006 | DRILL SHAFT (48 IN) | LF | 26.000 | 450.00 | 1 2 3 | 428.980 738.000 780.000 |
4166023 | DRILL SHAFT (SIGN MTS) (54 IN) | LF | 31.000 | 630.00 | 1 2 3 | 488.670 775.000 950.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 11.000 | 600.00 | 1 2 3 | 941.370 1,298.000 950.000 |
4966035 | REMOV STR (DRILL SHAFT) | EA | 6.000 | 6,100.00 | 1 2 3 | 2,025.890 1,812.000 2,300.000 |
5006001 | MOBILIZATION | LS | 1.000 | 213,784.00 | 1 2 3 | 125,191.260 196,095.000 300,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 17.000 | 8,600.00 | 1 2 3 | 2,835.780 11,577.000 16,000.000 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 125.000 | 42.00 | 1 2 3 | 62.320 44.000 50.000 |
5406016001 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 1.000 | 2,200.00 | 1 2 3 | 1,445.000 1,600.000 3,500.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 1.000 | 3,800.00 | 1 2 3 | 3,555.000 4,000.000 4,500.000 |
6186064 | CONDT (RM) (1") | LF | 60.000 | 50.00 | 1 2 3 | 21.690 44.200 70.000 |
6186070 | CONDT (RM) (2") | LF | 60.000 | 60.00 | 1 2 3 | 75.160 58.200 95.000 |
6246009 | GROUND BOX TY D (162922) | EA | 1.000 | 1,800.00 | 1 2 3 | 1,030.050 2,830.000 1,500.000 |
6366003001 | ALUMINUM SIGNS (TY O) | SF | 873.000 | 35.00 | 1 2 3 | 27.850 33.400 50.000 |
6366007001 | REPLACE EXISTING ALUMINUM SIGNS(TY A) | SF | 3,633.000 | 78.00 | 1 2 3 | 47.920 41.850 50.000 |
6366008001 | REPLACE EXISTING ALUMINUM SIGNS(TY G) | SF | 4,636.000 | 78.00 | 1 2 3 | 36.010 35.950 60.000 |
6366009001 | REPLACE EXISTING ALUMINUM SIGNS(TY O) | SF | 11,950.000 | 48.00 | 1 2 3 | 50.180 61.240 60.000 |
6446030 | IN SM RD SN SUP&AM TYS80(1)SA(T) | EA | 39.000 | 758.80 | 1 2 3 | 875.920 1,282.000 925.000 |
6446066 | IN SM RD SN SUP&AM (RAIL MOUNT) | EA | 10.000 | 5,200.00 | 1 2 3 | 3,551.340 7,865.000 3,750.000 |
6446076 | REMOVE SM RD SN SUP&AM | EA | 1.000 | 115.00 | 1 2 3 | 154.570 682.000 175.000 |
6476003 | REMOVE LRSA | EA | 1.000 | 1,300.00 | 1 2 3 | 1,146.090 1,812.000 1,750.000 |
6506028 | INS OH SN SUP(30 FT BAL TEE) | EA | 1.000 | 43,800.00 | 1 2 3 | 35,381.190 35,660.000 50,000.000 |
6506032 | INS OH SN SUP(30 FT CANT) | EA | 1.000 | 31,100.00 | 1 2 3 | 32,616.830 32,360.000 45,000.000 |
6506084 | INS OH SN SUP(75 FT BRDG) | EA | 1.000 | 63,120.00 | 1 2 3 | 56,713.970 50,590.000 75,000.000 |
6506089 | INS OH SN SUP(80 FT BRDG) | EA | 2.000 | 55,000.00 | 1 2 3 | 64,261.920 66,470.000 85,000.000 |
6506204 | REMOVE OVERHD SIGN SUP | EA | 2.000 | 9,000.00 | 1 2 3 | 6,682.470 9,230.000 18,000.000 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 102.000 | 110.00 | 1 2 3 | 121.350 227.000 115.000 |
60076094 | FIBER OPTIC FUSION SPLICE | EA | 2.000 | 250.00 | 1 2 3 | 281.660 431.000 650.000 |
60076095 | FIBER OPTIC PATCH PANEL (6 POSITION) | EA | 2.000 | 2,800.00 | 1 2 3 | 1,096.000 1,315.000 3,000.000 |
60286001 | INSTALL DMS (POLE MTD CABINET) | EA | 1.000 | 24,300.00 | 1 2 3 | 8,505.540 29,205.000 25,000.000 |
60286002 | INSTALL DMS (FOUNDATION MTD CABINET) | EA | 1.000 | 16,080.00 | 1 2 3 | 13,608.230 33,340.000 25,000.000 |
61236001 | ETHERNET SWITCH (INSTALL ONLY) | EA | 2.000 | 510.00 | 1 2 3 | 438.560 2,275.000 1,000.000 |
61856005002 | TMA (MOBILE OPERATION) | DAY | 220.000 | 250.00 | 1 2 3 | 378.880 419.000 400.000 |