Tabulation of Bids for Project STP 2B24(176)HES
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | WISE | Let Date: | 06/05/24 |
Type: | HIGHWAY IMPROVEMENT | Seq No: | 3018 |
Time: | 135 WORKING DAYS | Project ID: | STP 2B24(176)HES |
Highway: | US 81 | Contract #: | 06243018 |
Length: | 0.000 | CCSJ: | 0013-07-086 |
Limits: | |||
From: | FM 1655 | Check: | $100,000 |
To: | US 380F | Misc Cost: |
Estimate | $6,019,413.74 | % Over/Under | Company |
Bidder 1 | $5,886,834.11 | -2.20% | GRATIOT CONSTRUCTION, LTD. |
Bidder 2 | $6,774,211.50 | +12.54% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 3 | $7,253,891.27 | +20.51% | HJC FARMS, INC. |
Bidder 4 | $7,533,994.85 | +25.16% | FNH CONSTRUCTION, LLC |
Bidder 5 | $7,622,449.23 | +26.63% | SILVER CREEK CONSTRUCTION, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006001 | PREPARING ROW | AC | 33.050 | 2,950.00 | 1 2 3 4 5 | 1,000.000 3,100.000 1,000.000 20,000.000 12,500.000 |
1056011 | REMOVING STAB BASE AND ASPH PAV (2"-6") | SY | 1,291.000 | 15.00 | 1 2 3 4 5 | 9.000 16.500 5.350 20.000 15.000 |
1326004 | EMBANKMENT (FINAL)(DENS CONT)(TY B) | CY | 208.000 | 80.00 | 1 2 3 4 5 | 62.500 42.000 27.280 100.000 100.000 |
1606006 | FURNISHING AND PLACING TOPSOIL (3") | SY | 1,291.000 | 8.00 | 1 2 3 4 5 | 10.250 7.350 10.000 10.000 60.000 |
1646021 | CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) | SY | 193,563.000 | 1.00 | 1 2 3 4 5 | 0.250 0.600 0.680 0.500 0.420 |
1646029 | CELL FBR MLCH SEED(TEMP)(WARM) | SY | 96,782.500 | 0.50 | 1 2 3 4 5 | 0.210 0.350 0.630 0.500 0.390 |
1646031 | CELL FBR MLCH SEED(TEMP)(COOL) | SY | 96,780.000 | 0.50 | 1 2 3 4 5 | 0.230 0.300 0.640 0.500 0.390 |
1686001 | VEGETATIVE WATERING | MG | 13,549.410 | 30.00 | 1 2 3 4 5 | 0.010 60.000 100.000 10.000 20.000 |
4326046 | RIPRAP (MOW STRIP)(5 IN) | CY | 4,670.720 | 360.00 | 1 2 3 4 5 | 445.000 514.000 500.000 500.000 560.000 |
5006001 | MOBILIZATION | LS | 1.000 | 335,940.49 | 1 2 3 4 5 | 600,000.000 237,000.000 500,000.000 700,000.000 757,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 9.000 | 9,385.00 | 1 2 3 4 5 | 60,000.000 10,200.000 2,031.910 8,500.000 20,000.000 |
5066002005 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 1,066.000 | 43.00 | 1 2 3 4 5 | 39.000 45.000 44.280 30.000 39.000 |
5066011005 | ROCK FILTER DAMS (REMOVE) | LF | 1,066.000 | 15.50 | 1 2 3 4 5 | 11.000 12.600 10.350 15.000 11.000 |
5066041005 | BIODEG EROSN CONT LOGS (INSTL) (12") | LF | 1,672.000 | 6.50 | 1 2 3 4 5 | 5.000 5.750 5.060 18.000 5.000 |
5066043005 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 1,672.000 | 1.50 | 1 2 3 4 5 | 1.000 1.150 1.150 9.000 1.000 |
5126001 | PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | LF | 7,444.000 | 91.00 | 1 2 3 4 5 | 105.000 112.000 125.000 110.000 102.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 402.000 | 10.00 | 1 2 3 4 5 | 4.000 10.000 1.000 3.000 12.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 3.000 | 200.00 | 1 2 3 4 5 | 225.000 500.000 100.000 500.000 350.000 |
5436002 | CABLE BARRIER SYSTEM (TL-4) | LF | 95,868.000 | 16.50 | 1 2 3 4 5 | 10.750 11.550 10.810 16.000 11.000 |
5436020 | CABLE BARRIER TERMINAL SECTION (TL-4) | EA | 83.000 | 4,000.00 | 1 2 3 4 5 | 2,100.000 2,150.000 3,317.000 4,250.000 3,000.000 |
5456005 | CRASH CUSH ATTEN (REMOVE) | EA | 1.000 | 1,750.00 | 1 2 3 4 5 | 1,500.000 5,000.000 1,000.000 2,500.000 1,000.000 |
5456007 | CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | EA | 4.000 | 25,000.00 | 1 2 3 4 5 | 50,000.000 54,500.000 40,000.000 35,000.000 35,000.000 |
6586027 | INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI) | EA | 73.000 | 35.00 | 1 2 3 4 5 | 50.000 50.000 37.950 100.000 30.000 |
6586101 | INSTL OM ASSM (OM-2Z)(WFLX)SRF)SRF | EA | 83.000 | 193.00 | 1 2 3 4 5 | 50.000 120.000 169.500 100.000 30.000 |
7726001 | POST AND CABLE FENCE (REMOVAL) | LF | 670.000 | 15.00 | 1 2 3 4 5 | 5.000 7.400 1.000 15.000 3.000 |
30766001 | D-GR HMA TY-B PG64-22 | TON | 803.000 | 145.00 | 1 2 3 4 5 | 300.000 310.000 164.450 200.000 630.000 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 4.000 | 12,800.00 | 1 2 3 4 5 | 1.000 13,000.000 10,000.000 16,500.000 20,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 662.000 | 150.00 | 1 2 3 4 5 | 1.000 230.000 100.000 250.000 350.000 |
61856005002 | TMA (MOBILE OPERATION) | DAY | 20.000 | 400.00 | 1 2 3 4 5 | 1.000 900.000 200.000 550.000 700.000 |