The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | BELL | Let Date: | 08/01/24 |
Type: | REPLACE MAINLANE STRIPING | Seq No: | 3014 |
Time: | 45 WORKING DAYS | Project ID: | F 2B24(459) |
Highway: | IH 14 | Contract #: | 08243014 |
Length: | 0.000 | CCSJ: | 0231-03-160 |
Limits: | |||
From: | PADDY HAMILTON RD | Check: | $40,000 |
To: | CORYELL CL | Misc Cost: |
Estimate | $1,995,966.38 | % Over/Under | Company |
Bidder 1 | $1,467,608.80 | -26.47% | BATTERSON, LLP |
Bidder 2 | $1,522,540.48 | -23.72% | TRAFFIC HIGHWAY MAINTENANCE, LLC |
Bidder 3 | $1,672,975.25 | -16.18% | TRP INFRASTRUCTURE SERVICES, LLC |
Bidder 4 | $1,796,468.35 | -10.00% | L&L COMPANY |
Bidder 5 | $2,430,179.14 | +21.75% | STRIPE LINES, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 180,000.00 | 1 2 3 4 5 | 93,000.000 333,000.000 125,000.000 1.000 25,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 15,000.00 | 1 2 3 4 5 | 2,500.000 49,000.000 10,000.000 1.000 15,000.000 |
6686077 | PREFAB PAV MRK TY C (W) (ARROW) | EA | 47.000 | 270.00 | 1 2 3 4 5 | 200.000 500.000 225.000 300.000 285.000 |
6686083 | PREFAB PAV MRK TY C (W) (LNDP ARROW) | EA | 9.000 | 500.00 | 1 2 3 4 5 | 425.000 1,200.000 495.000 400.000 475.000 |
6686084 | PREFAB PAV MRK TY C (W) (NUMBER) | EA | 120.000 | 121.00 | 1 2 3 4 5 | 200.000 120.000 215.000 150.000 165.000 |
6686085 | PREFAB PAV MRK TY C (W) (WORD) | EA | 45.000 | 320.00 | 1 2 3 4 5 | 270.000 500.000 275.000 350.000 300.000 |
6726010 | REFL PAV MRKR TY II-C-R | EA | 49,375.000 | 5.00 | 1 2 3 4 5 | 6.000 2.000 5.500 5.000 6.940 |
60386004 | MULTIPOLYMER PAV MRK (W)(6")(SLD) | LF | 448,282.000 | 0.65 | 1 2 3 4 5 | 0.580 0.400 0.700 0.850 1.150 |
60386005 | MULTIPOLYMER PAV MRK (W)(6")(BRK) | LF | 224,141.000 | 0.75 | 1 2 3 4 5 | 0.580 0.600 0.750 0.850 1.150 |
60386006 | MULTIPOLYMER PAV MRK (W)(6")(DOT) | LF | 1,382.000 | 1.89 | 1 2 3 4 5 | 1.000 2.650 1.500 0.850 1.770 |
60386007 | MULTIPOLYMER PAV MRK (W)(8")(SLD) | LF | 284,778.000 | 2.25 | 1 2 3 4 5 | 1.050 0.410 0.900 1.800 2.000 |
60386011 | MULTIPOLYMER PAV MRK (W)(12")(SLD) | LF | 6,525.000 | 4.51 | 1 2 3 4 5 | 4.000 5.000 4.000 2.000 6.250 |
60386012 | MULTIPOLYMER PAV MRK (W)(12")(LNDP) | LF | 4,842.000 | 5.00 | 1 2 3 4 5 | 4.000 7.000 2.000 2.500 6.250 |
60386013 | MULTIPOLYMER PAV MRK (W)(24")(SLD) | LF | 2,176.000 | 6.30 | 1 2 3 4 5 | 8.000 15.000 10.000 3.000 15.000 |
60386017 | MULTIPOLYMER PAV MRK (Y)(6")(SLD) | LF | 448,282.000 | 0.65 | 1 2 3 4 5 | 0.580 0.400 0.700 0.850 1.150 |
61856005002 | TMA (MOBILE OPERATION) | DAY | 82.000 | 200.00 | 1 2 3 4 5 | 100.000 1,950.000 995.000 1.000 25.000 |