Tabulation of Bids for Project C 549-2-35
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | FANNIN | Let Date: | 08/02/24 |
Type: | INTERSECTION IMPROVEMENT | Seq No: | 3224 |
Time: | 32 WORKING DAYS | Project ID: | C 549-2-35 |
Highway: | SH 121 | Contract #: | 08243224 |
Length: | 0.000 | CCSJ: | 0549-02-035 |
Limits: | |||
From: | AT US 69 | Check: | $11,000 |
To: | . | Misc Cost: |
Estimate | $528,887.00 | % Over/Under | Company |
Bidder 1 | $516,689.00 | -2.31% | WG ENGINEERING & CONSTRUCTION, LLC |
Bidder 2 | $628,527.87 | +18.84% | AMERICAN LIGHTING AND SIGNALIZATION, LLC |
Bidder 3 | $665,434.50 | +25.82% | MICA CORPORATION |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4166026 | DRILL SHAFT (HIGH MAST POLE) (60 IN) | LF | 100.000 | 670.00 | 1 2 3 | 729.000 681.800 772.000 |
4326001 | RIPRAP (CONC)(4 IN) | CY | 8.100 | 620.00 | 1 2 3 | 725.000 499.940 2,955.000 |
5006001 | MOBILIZATION | LS | 1.000 | 48,080.00 | 1 2 3 | 55,850.000 55,973.000 62,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 5,000.00 | 1 2 3 | 7,258.000 3,745.000 31,525.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 50.000 | 4.00 | 1 2 3 | 4.000 7.080 95.000 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 50.000 | 1.00 | 1 2 3 | 2.500 3.540 44.000 |
6136005 | HI MST IL POLE (150 FT)( 80 MPH) | EA | 4.000 | 53,000.00 | 1 2 3 | 44,028.000 57,625.300 48,900.000 |
6146008 | LED HI MST IL ASM (6 FIXT) (ASYM)(TY B) | EA | 4.000 | 27,000.00 | 1 2 3 | 34,228.000 51,925.900 31,450.000 |
6186046 | CONDT (PVC) (SCH 80) (2") | LF | 110.000 | 13.00 | 1 2 3 | 24.000 26.040 22.500 |
6186075 | CONDT (RM) (3") (BORE) | LF | 335.000 | 88.00 | 1 2 3 | 80.000 42.800 88.000 |
6226002 | DCT CBL (3 NO.8) (2 INSULATED 1 BARE) | LF | 1,485.000 | 20.00 | 1 2 3 | 3.500 4.400 26.400 |
6246009 | GROUND BOX TY D (162922) | EA | 4.000 | 1,500.00 | 1 2 3 | 1,225.000 1,774.570 1,820.000 |
6286010 | ELC SRV TY A 120/240 060(NS)SS(E)SP(U) | EA | 2.000 | 5,000.00 | 1 2 3 | 6,352.000 10,566.900 14,550.000 |
61856002002 | TMA (STATIONARY) | DAY | 7.000 | 275.00 | 1 2 3 | 280.000 304.440 480.000 |