Tabulation of Bids for Project STP 2022(697)HES
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | MONTGOMERY | Let Date: | 08/03/22 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3021 |
Time: | 260 WORKING DAYS | Project ID: | STP 2022(697)HES |
Highway: | FM 1774 | Contract #: | 08223021 |
Length: | 5.053 | CCSJ: | 1400-04-040 |
Limits: | |||
From: | FM 1488 | Check: | $53,000 |
To: | SH 249 | Misc Cost: |
Estimate | $2,662,997.29 | % Over/Under | Company |
Bidder 1 | $1,870,035.50 | -29.78% | THIRD COAST SERVICES LLC |
Bidder 2 | $1,914,622.70 | -28.10% | ALLSTATE SIGNAL & CONSTRUCTION, LLC |
Bidder 3 | $2,011,325.39 | -24.47% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
Bidder 4 | $2,258,166.75 | -15.20% | VACA UNDERGROUND UTILITIES INC |
Bidder 5 | $2,370,263.01 | -10.99% | SICE, INC. |
Bidder 6 | $2,383,616.84 | -10.49% | FLORIDA TRAFFIC CONTROL DEVICES, INC. |
Bidder 7 | $2,452,971.80 | -7.89% | TRAF-TEX, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006001 | PREPARING ROW | AC | 2.000 | 12,000.00 | 1 2 3 4 5 6 7 | 800.000 455.000 2,190.000 4,500.000 13,920.430 4,309.310 2,281.000 |
4166029 | DRILL SHAFT (RDWY ILL POLE) (30 IN) | LF | 1,920.000 | 248.92 | 1 2 3 4 5 6 7 | 118.000 186.300 191.040 140.000 192.490 186.000 142.000 |
4326009 | RIPRAP (CONC) (CL B) (4") | CY | 67.200 | 373.03 | 1 2 3 4 5 6 7 | 1,050.000 766.000 708.500 600.000 1,671.780 927.940 1,341.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 2.800 | 550.00 | 1 2 3 4 5 6 7 | 245.000 905.000 708.500 900.000 1,780.390 985.940 366.000 |
5006001 | MOBILIZATION | LS | 1.000 | 242,090.66 | 1 2 3 4 5 6 7 | 185,000.000 7,300.000 165,087.210 75,000.000 228,145.330 134,628.510 63,614.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 12.000 | 7,603.08 | 1 2 3 4 5 6 7 | 900.000 1,100.000 3,284.590 3,000.000 8,137.220 1,159.920 1,745.000 |
6106288 | IN RD IL (TY SA) 50T-10 (400W EQ) LED | EA | 192.000 | 4,536.71 | 1 2 3 4 5 6 7 | 3,980.000 3,934.500 4,372.400 4,500.000 5,015.340 5,013.120 4,680.000 |
6186046 | CONDT (PVC) (SCH 80) (2") | LF | 41,675.000 | 10.00 | 1 2 3 4 5 6 7 | 7.100 7.840 5.660 11.500 5.310 10.630 14.000 |
6186047 | CONDT (PVC) (SCH 80) (2") (BORE) | LF | 8,180.000 | 27.49 | 1 2 3 4 5 6 7 | 8.000 12.620 12.560 16.000 9.540 17.330 18.650 |
6206007 | ELEC CONDR (NO.8) BARE | LF | 49,855.000 | 1.35 | 1 2 3 4 5 6 7 | 1.100 1.460 1.010 1.750 0.760 1.020 1.600 |
6206008 | ELEC CONDR (NO.8) INSULATED | LF | 99,710.000 | 1.20 | 1 2 3 4 5 6 7 | 1.150 1.560 1.140 1.800 0.950 1.130 1.680 |
6246010 | GROUND BOX TY D (162922)W/APRON | EA | 11.000 | 1,082.43 | 1 2 3 4 5 6 7 | 985.000 1,013.000 1,168.750 1,300.000 1,439.350 1,037.880 899.000 |
6286006 | ELC SRV TY A 120/240 060(NS)SS(E)GC(O) | EA | 7.000 | 5,429.45 | 1 2 3 4 5 6 7 | 6,785.000 4,627.000 2,599.000 7,000.000 7,729.480 6,256.690 9,457.000 |
61856002002 | TMA (STATIONARY) | DAY | 172.000 | 300.00 | 1 2 3 4 5 6 7 | 125.000 141.000 74.750 130.000 377.270 222.040 245.000 |