Tabulation of Bids for Project RMC - 636837001
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | SAN AUGUSTINE | Let Date: | 10/07/20 |
Type: | TREE AND BRUSH REMOVAL & TREE TRIMMING | Seq No: | 1101 |
Time: | 200 W | Project ID: | RMC - 636837001 |
Highway: | SH0103 | Contract #: | 10201101 |
Length: | 0.000 | CCSJ: | 6368-37-001 |
Limits: | |||
From: | VARIOUS LOCATIONS IN SAN AUGUSTINE | Check: | $5,000 |
To: | MAINTENANCE SECTION | Misc Cost: |
Estimate | $268,625.00 | % Over/Under | Company |
Bidder 1 | $222,150.00 | -17.30% | K & R CONTRACTORS |
Bidder 2 | $230,190.00 | -14.31% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
Bidder 3 | $239,395.00 | -10.88% | AZA CONSTRUCTION INC |
Bidder 4 | $246,070.00 | -8.40% | ACE CONTRACTORS, INC. |
Bidder 5 | $251,420.00 | -6.40% | JBM IRRIGATION |
Bidder 6 | $278,455.00 | +3.66% | BT CONSTRUCTORS, LLC |
Bidder 7 | $288,950.00 | +7.57% | LELAND & BRADLEE CONSTRUCTION, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006033 | MOBILIZATION (CALLOUT) | EA | 6.000 | 1,500.00 | 1 2 3 4 5 6 7 | 500.000 550.000 1,000.000 500.000 950.000 5,000.000 8,000.000 |
7526005 | TREE REMOVAL (4" - 12" DIA) | EA | 2,400.000 | 60.00 | 1 2 3 4 5 6 7 | 50.000 43.000 50.000 62.500 67.500 56.000 60.000 |
7526006 | TREE REMOVAL (12" - 18" DIA) | EA | 400.000 | 95.00 | 1 2 3 4 5 6 7 | 75.000 87.000 70.000 70.000 75.000 88.000 80.000 |
7526007 | TREE REMOVAL (18" - 24" DIA) | EA | 135.000 | 115.00 | 1 2 3 4 5 6 7 | 100.000 124.000 100.000 80.000 100.000 157.000 90.000 |
7526008 | TREE REMOVAL (24" - 30" DIA) | EA | 90.000 | 165.00 | 1 2 3 4 5 6 7 | 300.000 249.000 170.000 200.000 150.000 192.000 120.000 |
7526009 | TREE REMOVAL (30" - 36" DIA) | EA | 60.000 | 325.00 | 1 2 3 4 5 6 7 | 175.000 339.000 350.000 300.000 225.000 262.000 150.000 |
7526010 | TREE REMOVAL (36" - 42" DIA) | EA | 30.000 | 440.00 | 1 2 3 4 5 6 7 | 200.000 400.000 450.000 300.000 225.000 308.000 250.000 |
7526011 | TREE REMOVAL (42" - 48" DIA) | EA | 15.000 | 450.00 | 1 2 3 4 5 6 7 | 250.000 400.000 885.000 350.000 230.000 396.000 500.000 |
7526012 | TREE REMOVAL (48" - 60" DIA) | EA | 4.000 | 475.00 | 1 2 3 4 5 6 7 | 350.000 400.000 1,000.000 500.000 350.000 594.000 1,000.000 |
7526013 | TREE REMOVAL (60" - 72" DIA) | EA | 4.000 | 475.00 | 1 2 3 4 5 6 7 | 500.000 450.000 1,200.000 500.000 400.000 776.000 1,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 20.000 | 200.00 | 1 2 3 4 5 6 7 | 250.000 400.000 1.000 1.000 1.000 200.000 500.000 |