Tabulation of Bids for Project STP 2021(106)

Last Update: Tuesday, January 26, 2021

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Text version of this page
County:FOARDLet Date:11/05/20
Type:ACP OVERLAYSeq No:3213
Time:102 WORKING DAYSProject ID:STP 2021(106)
Highway:US 70Contract #:11203213
Length:5.200CCSJ:0146-04-029
Limits: 
From:COTTLE C/L, EASTCheck:$100,000
To:FM 654Misc Cost:
Estimate$6,165,123.50% Over/UnderCompany
Bidder 1$5,097,897.25-17.31%DUININCK, INC.
Bidder 2$5,416,871.57-12.14%ZACK BURKETT CO.
Bidder 3$5,490,947.05-10.94%RK HALL, LLC
Bidder 4$5,671,305.90-8.01%A. L. HELMCAMP, INC.
Bidder 5$5,699,280.45-7.56%GILVIN-TERRILL, LTD.
Bidder 6$5,838,638.98-5.30%KIEWIT INFRASTRUCTURE SOUTH CO.
Bidder 7$7,738,943.91+25.53%J. LEE MILLIGAN, INC.
Item CodeDescriptionUnitQuantityUnit Est.BidderUnit Bid
1346004BACKFILL (TY A OR B)STA817.000150.001
2
3
4
5
6
7
155.000
275.000
170.000
130.000
241.000
60.000
130.000
1646034DRILL SEEDING (PERM) (RURAL) (SANDY)AC37.470400.001
2
3
4
5
6
7
305.000
354.000
300.000
320.000
300.000
463.910
330.000
1686001VEGETATIVE WATERINGMG1,462.00020.001
2
3
4
5
6
7
25.000
30.000
15.500
10.000
25.000
44.180
20.000
3146013001EMULS ASPH (EROSN CONT)(CSS-1H)GAL36,270.0003.451
2
3
4
5
6
7
2.850
2.750
2.600
2.900
3.400
3.440
4.090
3546021PLANE ASPH CONC PAV(0" TO 2")SY3,736.0005.001
2
3
4
5
6
7
3.800
2.000
3.000
3.300
6.000
4.970
6.600
4326045RIPRAP (MOW STRIP)(4 IN)CY354.000640.001
2
3
4
5
6
7
650.000
885.000
620.000
560.000
807.000
717.950
720.000
4966099REMOVE STR (RAIL)LF100.00032.001
2
3
4
5
6
7
25.500
59.000
10.000
15.000
5.000
11.050
135.000
5006001MOBILIZATIONLS1.000514,231.001
2
3
4
5
6
7
400,000.000
165,000.000
136,300.000
480,000.000
550,000.000
495,854.210
770,000.000
5026001008BARRICADES, SIGNS AND TRAFFIC HANDLINGMO6.00018,000.001
2
3
4
5
6
7
14,000.000
2,250.000
8,875.000
14,000.000
10,000.000
20,000.000
36,000.000
5066020005CONSTRUCTION EXITS (INSTALL) (TY 1)SY300.00020.001
2
3
4
5
6
7
40.500
1.000
15.000
10.000
46.000
39.110
50.000
5066024005CONSTRUCTION EXITS (REMOVE)SY300.0005.001
2
3
4
5
6
7
15.000
1.000
2.000
3.000
9.000
14.560
7.000
5066042005BIODEG EROSN CONT LOGS (INSTL) (18")LF700.0005.001
2
3
4
5
6
7
4.700
5.450
4.620
4.900
6.000
6.630
8.500
5336003RUMBLE STRIPS (SHOULDER) ASPHALTLF157,885.0000.101
2
3
4
5
6
7
0.170
0.190
0.170
0.180
0.200
0.130
0.250
5336004RUMBLE STRIPS (CENTERLINE) ASPHALTLF76,452.0000.101
2
3
4
5
6
7
0.160
0.240
0.240
0.200
0.300
0.150
0.300
5406002001MTL W-BEAM GD FEN (STEEL POST)LF4,600.00028.001
2
3
4
5
6
7
21.000
30.100
21.000
22.000
20.500
28.170
28.300
5406017001MTL BM GD FEN (LONG SPAN SYSTEM)LF300.00022.001
2
3
4
5
6
7
23.500
30.100
23.500
24.000
23.000
28.170
28.300
5406020001MTL W - BEAM GD FEN (LOW FILL CULVERT)LF200.00050.001
2
3
4
5
6
7
67.000
64.900
67.000
70.000
66.000
60.750
61.000
5426001REMOVE METAL BEAM GUARD FENCELF4,800.0002.001
2
3
4
5
6
7
2.000
3.540
2.050
2.200
2.000
3.310
3.350
5426005RM MTL BM GD FEN TRANS (T101)EA4.000600.001
2
3
4
5
6
7
255.000
354.000
255.000
260.000
250.000
331.360
335.000
5446001GUARDRAIL END TREATMENT (INSTALL)EA60.0003,000.001
2
3
4
5
6
7
2,500.000
3,540.000
2,500.000
2,600.000
2,425.000
3,313.610
3,325.000
5446003GUARDRAIL END TREATMENT (REMOVE)EA60.000180.001
2
3
4
5
6
7
255.000
354.000
255.000
260.000
250.000
331.360
335.000
6586016INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)EA95.00025.001
2
3
4
5
6
7
29.500
20.650
30.000
31.000
29.000
19.330
20.000
6626110WK ZN PAV MRK SHT TERM (TAB)TY YEA4,674.0001.101
2
3
4
5
6
7
1.250
1.000
1.500
0.700
1.000
1.790
1.300
6666303007RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)LF170,288.0000.351
2
3
4
5
6
7
0.320
0.390
0.350
0.350
0.400
0.390
0.440
6666312007RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)LF18,630.0000.351
2
3
4
5
6
7
0.370
0.390
0.370
0.350
0.400
0.410
0.440
6666315007RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)LF65,506.0000.351
2
3
4
5
6
7
0.370
0.390
0.370
0.350
0.400
0.410
0.440
6666430007REFL PAV MRK TY I (W)24"(SLD)(110MIL)LF28.00030.001
2
3
4
5
6
7
11.000
18.290
11.000
16.500
20.000
12.150
22.200
6726009REFL PAV MRKR TY II-A-AEA1,397.0003.501
2
3
4
5
6
7
3.550
4.890
3.500
4.400
3.250
3.870
3.600
30766045D-GR HMA TY-D SAC-A PG70-28TON41,880.000105.001
2
3
4
5
6
7
84.050
91.000
100.000
98.000
89.700
95.000
128.000
30766066TACK COATGAL38,090.0002.501
2
3
4
5
6
7
2.400
3.150
3.250
2.000
3.700
3.120
3.850
61856002002TMA (STATIONARY)DAY82.000195.001
2
3
4
5
6
7
200.000
250.000
350.000
150.000
350.000
362.360
570.000
61856003002TMA (MOBILE OPERATION)HR120.00075.001
2
3
4
5
6
7
81.000
1.000
80.000
50.000
95.000
86.280
90.000