Tabulation of Bids for Project STP 2019(315)HES
| Text version of this page | |||
| County: | COLLINGSWORTH | Let Date: | 12/05/18 |
| Type: | MILLED CENTERLINE RUMBLE STRIPS | Seq No: | 3020 |
| Time: | 25 WORKING DAYS | Project ID: | STP 2019(315)HES |
| Highway: | FM 338 | Contract #: | 12183020 |
| Length: | 40.488 | CCSJ: | 0449-01-019 |
| Limits: | |||
| From: | US 83 EAST | Check: | $3,000 |
| To: | FM 1642 | Misc Cost: | $4,500.00 |
| Estimate | $120,912.64 | % Over/Under | Company |
| Bidder 1 | $72,769.78 | -39.82% | TEXAS PANHANDLE CONSTRUCTION, INC. |
| Bidder 2 | $84,213.40 | -30.35% | L&L COMPANY |
| Bidder 3 | $89,273.73 | -26.17% | TRP CONSTRUCTION GROUP, LLC |
| Bidder 4 | $108,117.36 | -10.58% | STRIPE-A-ZONE, INC. |
| Bidder 5 | $126,250.81 | +4.41% | BARRICADES UNLIMITED |
| Bidder 6 | $136,766.69 | +13.11% | TOTAL HIGHWAY MAINTENANCE, LLC |
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
| 5006001 | MOBILIZATION | LS | 1.000 | 25,000.00 | 1 2 3 4 5 6 | 2,750.000 1.000 5,250.000 10,000.000 13,000.000 12,000.000 |
| 5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 3,000.00 | 1 2 3 4 5 6 | 2,000.000 1.000 2,500.000 1,500.000 3,000.000 4,500.000 |
| 5336004 | RUMBLE STRIPS (CENTERLINE) ASPHALT | LF | 136,176.000 | 0.21 | 1 2 3 4 5 6 | 0.180 0.220 0.180 0.195 0.245 0.240 |
| 6666312007 | RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | LF | 31,700.000 | 0.31 | 1 2 3 4 5 6 | 0.225 0.280 0.320 0.460 0.390 0.480 |
| 6666315007 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 125,556.000 | 0.28 | 1 2 3 4 5 6 | 0.225 0.280 0.300 0.340 0.390 0.450 |
| 6726007 | REFL PAV MRKR TY I-C | EA | 128.000 | 3.50 | 1 2 3 4 5 6 | 3.000 5.000 5.000 4.000 2.950 4.000 |
| 6726009 | REFL PAV MRKR TY II-A-A | EA | 2,095.000 | 3.00 | 1 2 3 4 5 6 | 2.500 4.000 2.750 4.000 2.950 3.750 |
| 61856005 | TMA (MOBILE OPERATION) | DAY | 12.000 | 800.00 | 1 2 3 4 5 6 | 42.000 100.000 25.000 200.000 500.000 250.000 |