Tabulation of Bids for Project RMC - 630483001
Text version of this page | |||
County: | CULBERSON | Let Date: | 10/05/16 |
Type: | POTHOLE REPAIR | Seq No: | 4014 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 630483001 |
Highway: | RM0652 | Contract #: | 10164014 |
Length: | 100.000 | CCSJ: | 6304-83-001 |
Limits: | |||
From: | VARIOUS LOCATIONS | Check: | $10,000.00 |
To: | VARIOUS LOCATIONS | Misc Cost: |
Estimate | $495,393.75 | % Over/Under | Company |
Bidder 1 | $683,925.00 | +38.06% | DAN WILLIAMS COMPANY |
Bidder 2 | $990,358.00 | +99.91% | ALLIED PAVING CO. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1056015 | REMOVING STAB BASE & ASPH PAV (8" - 10") | SY | 5000.000 | 6.00 | 1 2 |
10.000 18.900 |
3106027 | PRIME COAT (MC - 30 OR AE - P) | GAL | 250.000 | 3.50 | 1 2 |
14.000 6.300 |
5006001 | MOBILIZATION | LS | 1.000 | 16718.75 | 1 2 |
30000.000 84000.000 |
5026015 | FURN ADDITIONAL TRUCKMOUNT ATTENUATOR | HR | 5.000 | 60.00 | 1 2 |
75.000 52.500 |
5106001 | ONE - WAY TRAF CONT (FLAGGER CONT) | HR | 350.000 | 30.00 | 1 2 |
115.000 23.630 |
5106002 | ONE - WAY TRAF CONT (PILOT CAR) | HR | 200.000 | 100.00 | 1 2 |
155.000 42.000 |
5106004 | ONE - WAY TRAFFIC CONTROL (PORT TRAF SIG | DAY | 20.000 | 900.00 | 1 2 |
1000.000 52.500 |
7006007 | POTHOLE REPAIR (SAW - CUT) | TON | 1500.000 | 170.00 | 1 2 |
200.000 335.000 |
70226002 | 1 LANE CLOSURE - 2 LANE ROAD, PAVED SHLD | EA | 200.000 | 600.00 | 1 2 |
900.000 1134.000 |
70226005 | FREEWAY 1 LANE CLOSURE | EA | 30.000 | 800.00 | 1 2 |
960.000 2100.000 |