Tabulation of Bids for Project NH 2017(134)
| Text version of this page | |||
| County: | DONLEY | Let Date: | 10/06/16 | 
| Type: | DISTRICT WIDE SEALCOAT | Seq No: | 3224 | 
| Time: | 72 WORKING DAYS | Project ID: | NH 2017(134) | 
| Highway: | US 287 | Contract #: | 10163224 | 
| Length: | 12.842 | CCSJ: | 0042-07-068 | 
| Limits: | |||
| From: | CLARENDON ECL, SOUTH | Check: | $100,000.00 | 
| To: | HEDLEY WCL, (NBL) | Misc Cost: | $116,726.00 | 
| Estimate | $5,022,310.72 | % Over/Under | Company | 
| Bidder 1 | $3,887,167.58 | -22.60% | CDM HOLDINGS, LLC | 
| Bidder 2 | $3,991,041.57 | -20.53% | MISSOURI PETROLEUM PRODUCTS COMPANY LLC | 
| Bidder 3 | $3,997,776.36 | -20.40% | RONALD R. WAGNER & CO., LP | 
| Bidder 4 | $4,017,953.38 | -20.00% | NORTHEASTERN PAVERS, INC. | 
| Bidder 5 | $4,062,523.01 | -19.11% | LIPHAM ASPHALT AND PAVING COMPANY, LLC | 
| Bidder 6 | $4,166,371.03 | -17.04% | BRANNAN PAVING CO., LTD. | 
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid | 
| 3166004 | ASPH (TIER I) | GAL | 426203.000 | 2.70 | 1 2 3 4 5 6 | 2.300 2.220 2.405 2.100 2.150 2.290 | 
| 3166018 | ASPH (CHFRS - 2P) | GAL | 545765.000 | 2.70 | 1 2 3 4 5 6 | 2.200 1.990 2.235 2.000 2.000 2.160 | 
| 3166078 | AGGR (TY - B GR - 4 SAC - A) | CY | 6930.000 | 108.00 | 1 2 3 4 5 6 | 60.000 62.000 56.130 80.000 62.000 69.560 | 
| 3166126 | AGGR (TY - PB GR - 4 SAC - A) | CY | 9224.000 | 115.00 | 1 2 3 4 5 6 | 90.000 99.000 93.390 102.000 92.000 107.820 | 
| 5006001 | MOBILIZATION | LS | 1.000 | 320000.00 | 1 2 3 4 5 6 | 225000.000 371000.000 291418.000 325000.000 475000.000 321000.000 | 
| 5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 4.000 | 1200.00 | 1 2 3 4 5 6 | 8750.000 1000.000 0.010 1.000 7500.000 0.010 | 
| 6626109 | WK ZN PAV MRK SHT TERM (TAB) TY W | EA | 10569.000 | 0.55 | 1 2 3 4 5 6 | 0.750 0.500 0.010 0.010 1.000 0.500 | 
| 6626111 | WK ZN PAV MRK SHT TERM (TAB) TY Y - 2 | EA | 50283.000 | 0.55 | 1 2 3 4 5 6 | 0.750 0.500 0.010 0.010 1.000 0.500 | 
| 6666167 | REFL PAV MRK TY II (W) 4" (BRK) | LF | 37860.000 | 0.12 | 1 2 3 4 5 6 | 0.080 0.110 0.110 0.110 0.110 0.125 | 
| 6666170 | REFL PAV MRK TY II (W) 4" (SLD) | LF | 913897.000 | 0.12 | 1 2 3 4 5 6 | 0.080 0.110 0.110 0.110 0.110 0.090 | 
| 6666205 | REFL PAV MRK TY II (Y) 4" (BRK) | LF | 146440.000 | 0.12 | 1 2 3 4 5 6 | 0.080 0.110 0.110 0.110 0.110 0.125 | 
| 6666207 | REFL PAV MRK TY II (Y) 4" (SLD) | LF | 656689.000 | 0.12 | 1 2 3 4 5 6 | 0.080 0.110 0.110 0.110 0.110 0.090 | 
| 6666211 | REFL PAV MRK TY II (Y) 8" (SLD) | LF | 700.000 | 0.26 | 1 2 3 4 5 6 | 0.350 0.260 0.260 0.260 0.260 0.495 | 
| 6666326 | RE PM W / RET REQ TY II (Y) 4" (BRK) | LF | 19060.000 | 0.12 | 1 2 3 4 5 6 | 0.080 0.110 0.110 0.110 0.110 0.135 | 
| 6726007 | REFL PAV MRKR TY I - C | EA | 486.000 | 3.15 | 1 2 3 4 5 6 | 2.000 2.250 2.250 2.250 2.250 2.600 | 
| 6726009 | REFL PAV MRKR TY II - A - A | EA | 4136.000 | 2.65 | 1 2 3 4 5 6 | 2.000 2.250 2.250 2.250 2.250 2.600 | 
| 6726010 | REFL PAV MRKR TY II - C - R | EA | 1607.000 | 3.10 | 1 2 3 4 5 6 | 2.000 3.000 3.000 3.000 3.000 2.600 |