Tabulation of Bids for Project RMC - 630201001
Text version of this page | |||
County: | DALLAS | Let Date: | 10/06/16 |
Type: | MISCCELLANEOUS CONCRETE REPAIR | Seq No: | 4211 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 630201001 |
Highway: | US0067 | Contract #: | 10164211 |
Length: | 0.001 | CCSJ: | 6302-01-001 |
Limits: | |||
From: | VARIOUS ROADWAYS IN THE SOUTHWEST | Check: | $6,000.00 |
To: | DALLAS COUNTY MAINTENANCE SECTION | Misc Cost: | $1.00 |
Estimate | $324,140.40 | % Over/Under | Company |
Bidder 1 | $445,740.00 | +37.51% | GIBSON & ASSOCIATES, INC. |
Bidder 2 | $499,180.00 | +54.00% | IOWA BRIDGE & CULVERT, LC |
Bidder 3 | $507,130.00 | +56.45% | O. TREVINO CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4016001 | FLOWABLE BACKFILL | CY | 60.000 | 240.00 | 1 2 3 |
405.000 300.000 275.000 |
4296007 | CONC STR REPAIR (VERTICAL & OVERHEAD) | SF | 480.000 | 90.00 | 1 2 3 |
168.000 175.000 146.000 |
4326001 | RIPRAP (CONC) (4 IN) | CY | 105.000 | 500.00 | 1 2 3 |
600.000 750.000 1015.000 |
5006001 | MOBILIZATION | LS | 1.000 | 24010.40 | 1 2 3 |
43000.000 49900.000 50500.000 |
5126025 | PORT CTB (MOVE) (SGL SLP) (TY 1) | LF | 75.000 | 5.00 | 1 2 3 |
90.000 150.000 180.000 |
5126077 | PORT CTB (DES SOURCE) (SAFETY SH) | LF | 500.000 | 20.00 | 1 2 3 |
35.000 75.000 65.000 |
5126078 | PORT CTB (MOVE) (SAFETY SH) | LF | 250.000 | 20.00 | 1 2 3 |
55.000 150.000 100.000 |
5126087002 | PORT CTB (ALIGNING) | LF | 2000.000 | 30.00 | 1 2 3 |
16.000 25.000 22.000 |
5296001 | CONC CURB (TY I) | LF | 2400.000 | 10.00 | 1 2 3 |
32.000 30.000 30.000 |
5296002 | CONC CURB (TY II) | LF | 10.000 | 18.00 | 1 2 3 |
50.000 28.000 195.000 |
5296008 | CONC CURB & GUTTER (TY II) | LF | 500.000 | 100.00 | 1 2 3 |
50.000 40.000 55.000 |
5316001 | CONC SIDEWALKS (4") | SY | 200.000 | 50.00 | 1 2 3 |
105.000 100.000 115.000 |
7766002 | REP (CONC PARAPETW / STL POST / RAIL - T | LF | 100.000 | 300.00 | 1 2 3 |
400.000 150.000 225.000 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 5.000 | 95.00 | 1 2 3 |
300.000 1000.000 305.000 |