Tabulation of Bids for Project RMC - 631191001
| Text version of this page | |||
| County: | MADISON | Let Date: | 12/13/16 | 
| Type: | CHANNEL AND SCOUR REPAIR | Seq No: | 1713 | 
| Time: | 25 W | Project ID: | RMC - 631191001 | 
| Highway: | SH0090 | Contract #: | 12161713 | 
| Length: | 0.000 | CCSJ: | 6311-91-001 | 
| Limits: | |||
| From: | VARIOUS | Check: | $3,000.00 | 
| To: | VARIOUS | Misc Cost: | |
| Estimate | $169,288.00 | % Over/Under | Company | 
| Bidder 1 | $158,724.00 | -6.24% | BECK-REIT & SONS, LTD. | 
| Bidder 2 | $184,363.00 | +8.90% | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | 
| Bidder 3 | $202,506.00 | +19.62% | SJ&J CONSTRUCTION, LLC | 
| Bidder 4 | $212,117.50 | +25.30% | 3LW MANAGEMENT, LLC | 
| Bidder 5 | $216,898.43 | +28.12% | TREVWAY, INC. | 
| Bidder 6 | $238,590.00 | +40.94% | FNH CONSTRUCTION, LLC | 
| Bidder 7 | $239,230.00 | +41.32% | CHAMPION INFRASTRUCTURE, LLC | 
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid | 
| 1326019 | EMBANKMENT (VEHICLE) (ORD COMP) (TY B) | CY | 992.000 | 30.00 | 1 2 3 4 5 6 7 | 28.000 36.000 28.000 65.000 66.000 30.000 40.000 | 
| 1646035 | DRILL SEEDING (PERM) (RURAL) (CLAY) | SY | 330.000 | 0.30 | 1 2 3 4 5 6 7 | 3.000 3.000 1.000 1.000 6.320 2.000 5.000 | 
| 1646041 | DRILL SEEDING (TEMP) (WARM) | SY | 165.000 | 0.30 | 1 2 3 4 5 6 7 | 3.000 2.000 1.000 1.000 6.320 2.000 5.000 | 
| 1646043 | DRILL SEEDING (TEMP) (COOL) | SY | 165.000 | 0.30 | 1 2 3 4 5 6 7 | 3.000 2.000 1.000 1.000 6.320 2.000 5.000 | 
| 1696001 | SOIL RETENTION BLANKETS (CL 1) (TY A) | SY | 330.000 | 3.00 | 1 2 3 4 5 6 7 | 7.000 15.000 2.000 2.750 6.510 10.000 10.000 | 
| 4006005 | CEM STABIL BKFL | CY | 30.000 | 110.00 | 1 2 3 4 5 6 7 | 188.000 200.000 150.000 155.000 212.000 140.000 60.000 | 
| 4016001 | FLOWABLE BACKFILL | CY | 171.000 | 225.00 | 1 2 3 4 5 6 7 | 188.000 166.000 250.000 220.000 200.000 450.000 200.000 | 
| 4036006 | TEMPORARY SPL SHORING (COFFERDAM) | SF | 121.000 | 35.00 | 1 2 3 4 5 6 7 | 90.000 65.000 30.000 75.000 109.000 100.000 150.000 | 
| 4326002 | RIPRAP (CONC) (5 IN) | CY | 3.000 | 500.00 | 1 2 3 4 5 6 7 | 600.000 2000.000 1000.000 650.000 1347.310 650.000 500.000 | 
| 4326030 | RIPRAP (STONE COMMON) (GROUT) (12 IN) | CY | 100.000 | 350.00 | 1 2 3 4 5 6 7 | 155.000 275.000 250.000 250.000 211.350 185.000 300.000 | 
| 4326033 | RIPRAP (STONE PROTECTION) (18 IN) | CY | 146.000 | 140.00 | 1 2 3 4 5 6 7 | 155.000 225.000 180.000 150.000 161.000 185.000 300.000 | 
| 4606007 | CMP (GAL STL 48 IN) | LF | 75.000 | 140.00 | 1 2 3 4 5 6 7 | 166.000 150.000 350.000 145.000 109.000 300.000 400.000 | 
| 5006001 | MOBILIZATION | LS | 1.000 | 15390.00 | 1 2 3 4 5 6 7 | 16000.000 16000.000 30000.000 20000.000 20000.000 21000.000 20000.000 | 
| 5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 3500.00 | 1 2 3 4 5 6 7 | 2800.000 2100.000 5000.000 6000.000 6000.000 8500.000 3000.000 | 
| 5066038003 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 500.000 | 3.50 | 1 2 3 4 5 6 7 | 5.000 3.000 3.000 4.500 4.000 4.000 10.000 | 
| 5066039003 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 500.000 | 1.50 | 1 2 3 4 5 6 7 | 3.000 1.000 1.000 1.500 1.000 2.000 5.000 |