DBE Construction Report for TRICON PRECAST, LTD.

 
 
Last Update: Wednesday, September 7, 2005
TRICON PRECAST, LTD. Vendor #: 00897
15055 HENRY ROAD DBE Certification Status: CERTIFIED
HOUSTON, TX 77060 Expiration Date: 05/31/06
Phone: (281)931-9832 Fax: (281)931-0061
 
Let Date: 1999-07 County: WEBB
CCSJ: 0018-06-131 District: LAREDO
Project ID: NH 99(462) Pct Complete: 100%
Commitment Amount: 497,667.50
Commitment Work: MANUFACTURE RETAINING WALL
Prime Contractors: DEAVERS CONSTRUCTION, L.P
 
Let Date: 2000-04 County: NUECES
CCSJ: 3596-01-002 District: CORPUS CHRISTI
Project ID: NH 2000(387) Pct Complete: 100%
Commitment Amount: 94,952.52
Commitment Work: CL A CONC, GASE PIPELIN
Prime Contractors: HAAS-ANDERSON CONSTRUCTION, LTD
 
Let Date: 2000-04 County: NUECES
CCSJ: 3596-01-002 District: CORPUS CHRISTI
Project ID: NH 2000(387) Pct Complete: 100%
Commitment Amount: 16,206.48
Commitment Work: PORT CONC TRAF BAR
Prime Contractors: HAAS-ANDERSON CONSTRUCTION, LTD
 
Let Date: 2001-08 County: WALKER
CCSJ: 0109-09-043 District: BRYAN
Project ID: STP 2001(655)UM Pct Complete: 51%
Commitment Amount: 411,727.62
Commitment Work: RETAINING WALL, PORT CONC TRAF BA
Prime Contractors: SMITH & COMPAN
 
Let Date: 2001-09 County: TITUS
CCSJ: 0222-01-033 District: ATLANTA
Project ID: HP 835(1) Pct Complete: 95%
Commitment Amount: 79,715.00
Commitment Work: MANUFACTURE CONTRACT TRAFFIC BARRIER
Prime Contractors: LONGVIEW BRIDGE AND ROAD, LTD
 
Let Date: 2001-11 County: SAN JACINTO
CCSJ: 0177-02-059 District: LUFKIN
Project ID: STP 2001(287)HES Pct Complete: 95%
Commitment Amount: 15,683.19
Commitment Work: PLACE AND TIE REBAR FOR ABUTMENTS, BENTS, AND SLAB
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2001-11 County: SAN JACINTO
CCSJ: 0177-02-059 District: LUFKIN
Project ID: STP 2001(287)HES Pct Complete: 95%
Commitment Amount: 285,795.00
Commitment Work: PORT CONC TRAF BA
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2002-09 County: SAN PATRICIO
CCSJ: 0101-05-026 District: CORPUS CHRISTI
Project ID: MG 2001(599) Pct Complete: 100%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2002-12 County: GRAYSON
CCSJ: 0047-03-050 District: PARIS
Project ID: NH 2003(4) Pct Complete: 72%
Commitment Amount: 45,678.60
Commitment Work: RETAINING WALL (TEMP
Prime Contractors: RUSHING PAVING COMPANY, LTD
 
Let Date: 2002-12 County: HARRIS
CCSJ: 0508-01-294 District: HOUSTON
Project ID: IM 10-7(390) Pct Complete: 92%
Commitment Amount: 1,230,344.00
Commitment Work: REINFORCING STEEL FOR CONCRETE PAVIN
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2002-12 County: HARRIS
CCSJ: 0508-01-294 District: HOUSTON
Project ID: IM 10-7(390) Pct Complete: 92%
Commitment Amount: 567,163.00
Commitment Work: RETAINING WALL, SOIL ANCHO
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2002-12 County: HARRIS
CCSJ: 0508-01-294 District: HOUSTON
Project ID: IM 10-7(390) Pct Complete: 92%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2003-01 County: MONTGOMERY
CCSJ: 0177-05-088 District: HOUSTON
Project ID: NH 2001(93) Pct Complete: 100%
Commitment Amount: 914,773.20
Commitment Work: SUPPLY PRE-CAST PANELS FOR RETAINING WALL (100% GOAL CREDIT
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2003-01 County: MONTGOMERY
CCSJ: 0177-05-088 District: HOUSTON
Project ID: NH 2001(93) Pct Complete: 100%
Commitment Amount: 1,090,541.83
Commitment Work: ASPH STAB BS, HOT MIX, HMA
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2003-03 County: HARRIS
CCSJ: 0508-01-302 District: HOUSTON
Project ID: IM 10-7(392) Pct Complete: 91%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2003-03 County: HARRIS
CCSJ: 0508-01-302 District: HOUSTON
Project ID: IM 10-7(392) Pct Complete: 91%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2003-03 County: HARRIS
CCSJ: 0508-01-302 District: HOUSTON
Project ID: IM 10-7(392) Pct Complete: 91%
Commitment Amount: 1,017,620.94
Commitment Work: REINFORCING STEE
Prime Contractors: DHT CODE 12529 NOT FOUN
 
Let Date: 2003-03 County: CHAMBERS
CCSJ: 0508-02-091 District: BEAUMONT
Project ID: NH 2003(324) Pct Complete: 43%
Commitment Amount: 2,159,531.00
Commitment Work: CEM STABIL BKFL, CMP, CULV, RC PIPE, INLET MANH, WINGWALL, SAFE END TRT, SET, INLET, REMOV OLD ST
Prime Contractors: MCCARTHY BUILDING COMPANIES, INC
 
Let Date: 2003-03 County: CHAMBERS
CCSJ: 0508-02-091 District: BEAUMONT
Project ID: NH 2003(324) Pct Complete: 43%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: MCCARTHY BUILDING COMPANIES, INC
 
Let Date: 2003-04 County: WALLER
CCSJ: 0409-02-021 District: HOUSTON
Project ID: BR 2001(297) Pct Complete: 94%
Commitment Amount: 35,068.00
Commitment Work: RETAINING WAL
Prime Contractors: LONE STAR ROAD CONSTRUCTION, LTD
 
Let Date: 2003-04 County: WALLER
CCSJ: 0409-02-021 District: HOUSTON
Project ID: BR 2001(297) Pct Complete: 94%
Commitment Amount: 19,362.30
Commitment Work: MBGF, SM RD SGN ASSM, SINGLE GUARDRAI
Prime Contractors: LONE STAR ROAD CONSTRUCTION, LTD
 
Let Date: 2003-04 County: WALLER
CCSJ: 0409-02-021 District: HOUSTON
Project ID: BR 2001(297) Pct Complete: 94%
Commitment Amount: 175,795.95
Commitment Work: CEM TRT BASE, DRVWY, HOT MI
Prime Contractors: LONE STAR ROAD CONSTRUCTION, LTD
 
Let Date: 2003-04 County: COMAL
CCSJ: 0016-05-091 District: SAN ANTONIO
Project ID: IM 35-2(302) Pct Complete: 100%
Commitment Amount: 79,409.00
Commitment Work: MOBILIZATION, PERM BOWD, FLOWABLE, GATE VALVE, CUT AND REPLACE ASPH PAV, RELAY SHRT SERV, PIP WTR, GATE VALVE AND BOX, TIE I
Prime Contractors: HUNTER INDUSTRIES, LTD
 
Let Date: 2003-04 County: COMAL
CCSJ: 0016-05-091 District: SAN ANTONIO
Project ID: IM 35-2(302) Pct Complete: 100%
Commitment Amount: 11,049.50
Commitment Work: TEMP EARTH WAL
Prime Contractors: HUNTER INDUSTRIES, LTD
 
Let Date: 2003-05 County: GALVESTON
CCSJ: 0389-11-032 District: HOUSTON
Project ID: HP 1258(1) Pct Complete: 99%
Commitment Amount: 535,645.91
Commitment Work: DRILL SHAFT, RIPRAP, SOUND WALL, ANTIGRAFFITI COA
Prime Contractors: J.D. ABRAMS, L.P
 
Let Date: 2003-06 County: TRAVIS
CCSJ: 3136-01-126 District: TEXAS TURNPIKE AUTHORITY
Project ID: TTA 2002(97) Pct Complete: 69%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
GILBERT TEXAS CONSTRUCTION, L.P
 
Let Date: 2003-07 County: HARRIS
CCSJ: 0271-06-090 District: HOUSTON
Project ID: NH 2003(538) Pct Complete: 86%
Commitment Amount: 2,734,067.50
Commitment Work: RETAINING WALL, PORT CONC TRAF BA
Prime Contractors: BALFOUR BEATTY CONSTRUCTION, INC
 
Let Date: 2003-08 County: CHAMBERS
CCSJ: 3510-10-002 District: BEAUMONT
Project ID: NH 2003(506) Pct Complete: 40%
Commitment Amount: 314,259.55
Commitment Work: SUPPLY MSE WALL PANELS AND PORT CTB (100% GOAL CREDIT
Prime Contractors: J.D. ABRAMS, L.P
 
Let Date: 2003-08 County: WILLIAMSON
CCSJ: 0683-01-070 District: TEXAS TURNPIKE AUTHORITY
Project ID: TTA 2002(245) Pct Complete: 70%
Commitment Amount: 470,556.00
Commitment Work: FURNISH AND INSTALL CONC TRAF BAR, FURNISH LOW PRF (TY 1), (TY 2
Prime Contractors: GRANITE CONSTRUCTION COMPAN
J.D. ABRAMS, L.P
 
Let Date: 2003-09 County: WILLIAMSON
CCSJ: 0683-01-069 District: TEXAS TURNPIKE AUTHORITY
Project ID: TTA 2002(243) Pct Complete: 55%
Commitment Amount: 408,435.50
Commitment Work: PORT CONC TRAF BAR (FRUN & INSTALL), PORT CONC (LOW PRF TY 1), (TY 2
Prime Contractors: AUSTIN BRIDGE & ROAD, L
 
Let Date: 2003-09 County: BEXAR
CCSJ: 0521-04-209 District: SAN ANTONIO
Project ID: NH 2001(783) Pct Complete: 36%
Commitment Amount: 1,369,832.90
Commitment Work: RETAINING WALL, TEMP EARTH WALLS, RET WALL (SOIL NAIL), ASHLAR STONE FI
Prime Contractors: DEAN WORD COMPANY, LTD
 
Let Date: 2003-10 County: JEFFERSON
CCSJ: 0200-15-008 District: BEAUMONT
Project ID: HP 103(1) Pct Complete: 56%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: APAC-TEXAS, INC
 
Let Date: 2003-12 County: COMAL
CCSJ: 0016-04-091 District: SAN ANTONIO
Project ID: NH 2000(980) Pct Complete: 66%
Commitment Amount: 815,785.66
Commitment Work: RETAIN WALL (MSE), SSTR COPING, SOIL NAIL (WALL), TEMP EARTH WAL
Prime Contractors: HUNTER INDUSTRIES, LTD
 
Let Date: 2004-01 County: BEXAR
CCSJ: 0521-04-189 District: SAN ANTONIO
Project ID: NH 2004(190) Pct Complete: 29%
Commitment Amount: 1,602,938.00
Commitment Work: MSE WALL PANELS, STANDARD COPING, CONECTOR COPIN
Prime Contractors: MCCARTHY BUILDING COMPANIES, INC
 
Let Date: 2004-03 County: TRAVIS
CCSJ: 0683-07-003 District: TEXAS TURNPIKE AUTHORITY
Project ID: TTA 2002(252) Pct Complete: 58%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: AUSTIN BRIDGE & ROAD, L
 
Let Date: 2004-03 County: HARDIN
CCSJ: 0200-10-065 District: BEAUMONT
Project ID: NH 2003(640) Pct Complete: 100%
Commitment Amount: 74,205.00
Commitment Work: PROT CONC TRAF BARRIE
Prime Contractors: APAC-TEXAS, INC
 
Let Date: 2004-04 County: HARRIS
CCSJ: 3510-05-009 District: HOUSTON
Project ID: STP 2004(294)MM Pct Complete: 100%
Commitment Amount: 1,091,396.22
Commitment Work: SUPPLY RETAINING WALL (100% GHOAL CREDIT
Prime Contractors: W.W. WEBBER INC
 
Let Date: 2004-07 County: FORT BEND
CCSJ: 0188-09-030 District: HOUSTON
Project ID: BR 2002(4) Pct Complete: 51%
Commitment Amount: 87,933.20
Commitment Work: SUPPLY RETAINING WALLS, HALF COPING AND STANDARD COPING (100% GOAL CREDIT
Prime Contractors: BEYER CONSTRUCTION, LL
 
Let Date: 2004-07 County: HARRIS
CCSJ: 0027-10-063 District: HOUSTON
Project ID: MG 2004(396) Pct Complete: 92%
Commitment Amount: 37,858.00
Commitment Work: RETAINING WALL (DRILL SHAFT
Prime Contractors: FORDE CONSTRUCTION COMPANY, INC
 
Let Date: 2004-08 County: FORT BEND
CCSJ: 0027-08-108 District: HOUSTON
Project ID: STP 2004(641)MM Pct Complete: 21%
Commitment Amount: 213,626.12
Commitment Work: CEM TRT BS, CONSTRUCT DETOUR
Prime Contractors: W.W. WEBBER INC
 
Let Date: 2004-08 County: JASPER
CCSJ: 0065-02-045 District: BEAUMONT
Project ID: NH 2004(607) Pct Complete: 27%
Commitment Amount: 186,120.00
Commitment Work: CONC TRAF BARRIE
Prime Contractors: ALLCO, LTD
 
Let Date: 2004-08 County: FORT BEND
CCSJ: 0027-08-108 District: HOUSTON
Project ID: STP 2004(641)MM Pct Complete: 21%
Commitment Amount: 780,572.51
Commitment Work: RETAINING WAL
Prime Contractors: W.W. WEBBER INC
 
Let Date: 2004-08 County: ELLIS
CCSJ: 0442-03-031 District: DALLAS
Project ID: NH 2004(312) Pct Complete: 32%
Commitment Amount: 1,162,938.00
Commitment Work: MANUFACTURER RETANING WAL
Prime Contractors: ED BELL CONSTRUCTION COMPAN
 
Let Date: 2004-09 County: MONTGOMERY
CCSJ: 0177-05-055 District: HOUSTON
Project ID: NH 2004(698) Pct Complete: 31%
Commitment Amount: 2,681,406.33
Commitment Work: RETN WALL, PORT CONC TRAF BAR, TEMP EARTH WAL
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2004-09 County: CAMERON
CCSJ: 0039-08-086 District: PHARR
Project ID: MG 2003(303) Pct Complete: 28%
Commitment Amount: 722,525.00
Commitment Work: FURNISH RETAINING WAL
Prime Contractors: BALLENGER CONSTRUCTION COMPAN
 
Let Date: 2004-09 County: CAMERON
CCSJ: 0039-19-042 District: PHARR
Project ID: MG 2004(548) Pct Complete: 15%
Commitment Amount: 5,841,339.92
Commitment Work: MSE PANELS,COPING,FASCIA PANEL
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2004-09 County: DALLAS
CCSJ: 0047-07-189 District: DALLAS
Project ID: STP 2004(680)MM Pct Complete: 55%
Commitment Amount: 256,788.00
Commitment Work: SUPPLY PRECAST WALL AND COPING (100% GOAL CREDIT
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2004-10 County: FORT BEND
CCSJ: 1965-02-006 District: HOUSTON
Project ID: STP 2004(735) Pct Complete: 100%
Commitment Amount: 42,415.20
Commitment Work: HM (TYD)(LEVEL-UP)(PF 70-22
Prime Contractors: SILVA, INC
 
Let Date: 2004-10 County: FORT BEND
CCSJ: 1965-02-006 District: HOUSTON
Project ID: STP 2004(735) Pct Complete: 100%
Commitment Amount: 162,900.00
Commitment Work: RETAINING WALL (MSE
Prime Contractors: SILVA, INC
 
Let Date: 2004-10 County: GALVESTON
CCSJ: 1607-02-016 District: HOUSTON
Project ID: HP 300(100) Pct Complete: 44%
Commitment Amount: 191,100.00
Commitment Work: FURNISH PRECAST LOW PROFILE BARRIE
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2004-12 County: HARRIS
CCSJ: 0271-07-254 District: HOUSTON
Project ID: NH 2005(85) Pct Complete: 28%
Commitment Amount: 3,181,147.35
Commitment Work: RETAINING WALL, PORT CONC TRAF BAR, PROT CTB, TEMPEARTH WALL
Prime Contractors: BALFOUR BEATTY CONSTRUCTION, INC
 
Let Date: 2005-01 County: BEXAR
CCSJ: 0521-04-190 District: SAN ANTONIO
Project ID: NH 2005(136) Pct Complete: 1%
Commitment Amount: 1,039,625.17
Commitment Work: RETAINING WALL (MSE WALL PNLS, COPING FOR SSTR RAIL, STANDARD COPING) MOBILIZATION, TEMP EART WALL
Prime Contractors: AUSTIN BRIDGE & ROAD, L
 
Let Date: 2005-01 County: WALKER
CCSJ: 0212-02-017 District: BRYAN
Project ID: STP 2005(118) Pct Complete: 16%
Commitment Amount: 75,710.00
Commitment Work: PORT CONC TRAF BAR (SUPP&INSTL
Prime Contractors: SMITH & COMPAN
 
Let Date: 2005-02 County: NUECES
CCSJ: 0074-06-201 District: CORPUS CHRISTI
Project ID: IM 37-1(126) Pct Complete: 54%
Commitment Amount: 332,176.00
Commitment Work: MSE PNLS TPL,PC COPING W/BAR TPL, PC COPING PLAI
Prime Contractors: GILBERT TEXAS CONSTRUCTION, L.P
 
Let Date: 2005-02 County: DALLAS
CCSJ: 8050-18-042 District: DALLAS
Project ID: NH 2005(186) Pct Complete: 8%
Commitment Amount: 395,628.80
Commitment Work: RETAINING WALL PANELS, FRACTURED FIN FINISH,CONCRETE, CIPING FOR C-411 RAI, RETAINED SOIL TEM WAL
Prime Contractors: MCCARTHY BUILDING COMPANIES, INC
 
Let Date: 2005-05 County: HARRIS
CCSJ: 0912-71-696 District: HOUSTON
Project ID: CM 99(758) Pct Complete: 2%
Commitment Amount: 189,610.00
Commitment Work: PRECAST CONC TRAF BARRIER,PORT CTB LP TY1,TY2, TY
Prime Contractors: J.D. ABRAMS, L.P
 
Let Date: 2005-06 County: GALVESTON
CCSJ: 0976-03-049 District: HOUSTON
Project ID: NH 2005(486) Pct Complete: 0%
Commitment Amount: 573,240.00
Commitment Work: LOW PORFILE CTB TY1,TY2
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2005-06 County: HARRIS
CCSJ: 0720-03-084 District: HOUSTON
Project ID: NH 2005(416) Pct Complete: 2%
Commitment Amount: 1,072,065.07
Commitment Work: RET WALL (MSE), PORT CTB (FUR & INS)(SIL SLP)(TY2), PORT CTB (FUR & ISN)(LOW PROF)(TY1
Prime Contractors: W.W. WEBBER INC
 
Let Date: 2005-06 County: FORT BEND
CCSJ: 0089-09-064 District: HOUSTON
Project ID: DMO 2005(515) Pct Complete: 0%
Commitment Amount: 3,255,588.25
Commitment Work: PRECAST MSE WALL PNLS,MATERIAL MOB,COPING RAIL, STAND. COPING
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2005-06 County: WALLER
CCSJ: 0114-11-065 District: HOUSTON
Project ID: BR 2005(483) Pct Complete: 0%
Commitment Amount: 191,730.00
Commitment Work: MANUFACTURE PORTABLE CT
Prime Contractors: LONE STAR ROAD CONSTRUCTION, LTD
 
Let Date: 2005-06 County: CAMERON
CCSJ: 0220-07-051 District: PHARR
Project ID: MG 2004(778) Pct Complete: 0%
Commitment Amount: 388,550.00
Commitment Work: PERM CTB (SGL SLP)(SPL)42
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2005-07 County: TRAVIS
CCSJ: 0015-13-259 District: AUSTIN
Project ID: BR 2001(10) Pct Complete: 0%
Commitment Amount: 790,897.12
Commitment Work: MANUFACTURE RETAINING WALL (MSE) & RAIL (TY T201 & TY C201
Prime Contractors: CAPITAL EXCAVATION COMPAN
 
Let Date: 2005-07 County: HARRIS
CCSJ: 0050-06-068 District: HOUSTON
Project ID: NH 2005(717) Pct Complete: 0%
Commitment Amount: 1,493,113.50
Commitment Work: PORT CTB(FUR&INSTL)
Prime Contractors: TEXAS STERLING CONSTRUCTION, L.P
 
Let Date: 2005-07 County: BRAZOS
CCSJ: 0050-02-092 District: BRYAN
Project ID: NH 2005(774) Pct Complete: 0%
Commitment Amount: 1,033,307.24
Commitment Work: RETAINING WALL; PORT CT
Prime Contractors: GLENN FUQUA, INC
 
Let Date: 2005-08 County: SABINE
CCSJ: 0064-05-051 District: LUFKIN
Project ID: BR 2005(818) Pct Complete: 0%
Commitment Amount: 50,625.00
Commitment Work: PORT CTB(FUR&INST)(SAFETY SH)(TYI), PORTCTB (FUR&INST)(F-SHAPE)(TY I
Prime Contractors: LONGVIEW BRIDGE AND ROAD, LTD