DBE Construction Report for FORTSON CONTRACTING INC
DBE Construction Report for FORTSON CONTRACTING INC | ||||
Last Update: Wednesday, September 7, 2005 |
FORTSON CONTRACTING INC | Vendor #: | 03870 |
772 FM 1126 | DBE Certification Status: | CERTIFIED |
RICE, TX 75155 | Expiration Date: | 07/31/05 |
Phone: (903)326-5036 | Fax: | (903)326-5002 |
Let Date: | 2002-04 | County: | TARRANT |
CCSJ: | 0171-05-055 | District: | FORT WORTH |
Project ID: | DPR 2001(869) | Pct Complete: | 100% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
Let Date: | 2002-08 | County: | ELLIS |
CCSJ: | 0172-04-028 | District: | DALLAS |
Project ID: | NH 2002(61) | Pct Complete: | 100% |
Commitment Amount: | 447,311.16 | ||
Commitment Work: | MBGF, TERM ANCHOR SECT, REACT 350, SINGLE GDRAI | ||
Prime Contractors: | GAREY CONSTRUCTION LTD | ||
Let Date: | 2002-11 | County: | COLLIN |
CCSJ: | 0364-04-022 | District: | DALLAS |
Project ID: | NH 2002(933) | Pct Complete: | 87% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | AUSTIN BRIDGE & ROAD, L | ||
Let Date: | 2003-05 | County: | MCLENNAN |
CCSJ: | 0015-01-190 | District: | WACO |
Project ID: | IM 35-4(213) | Pct Complete: | 100% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2003-05 | County: | MCLENNAN |
CCSJ: | 0015-01-192 | District: | WACO |
Project ID: | IM 35-4(215) | Pct Complete: | 88% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2003-07 | County: | LIMESTONE |
CCSJ: | 1191-03-025 | District: | WACO |
Project ID: | C 1191-3-25 | Pct Complete: | 87% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2003-07 | County: | TARRANT |
CCSJ: | 0172-09-013 | District: | FORT WORTH |
Project ID: | STP 2003(536)MM | Pct Complete: | 96% |
Commitment Amount: | 142,320.50 | ||
Commitment Work: | MTL BEAM GD FEN, TERM ANCHOR, REMOV METAL BEAM GD FEN, OBJ MRK ASM, (OM-2SR), SINGLE GUADRAIL TER TRACC (INSTALL), (MOVE) (RESET | ||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
Let Date: | 2003-07 | County: | ELLIS |
CCSJ: | 0172-13-001 | District: | DALLAS |
Project ID: | NH 2003(533) | Pct Complete: | 74% |
Commitment Amount: | 568,537.95 | ||
Commitment Work: | RAIL, MBGF, REMOV TERM ANCH, DELIN, OBJ MRK, QUADGUARD, SGT, TRAC | ||
Prime Contractors: | J.D. ABRAMS, L.P T. J. LAMBRECHT CONSTRUCTION, INC |
||
Let Date: | 2003-07 | County: | TARRANT |
CCSJ: | 0172-09-013 | District: | FORT WORTH |
Project ID: | STP 2003(536)MM | Pct Complete: | 96% |
Commitment Amount: | 146,542.50 | ||
Commitment Work: | DRILL SHAFT (18"), (30"), (36"), (42" | ||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
Let Date: | 2003-07 | County: | MCLENNAN |
CCSJ: | 0258-09-118 | District: | WACO |
Project ID: | BR 2003(539) | Pct Complete: | 99% |
Commitment Amount: | 72,044.00 | ||
Commitment Work: | MBGF, TERM ANCHOR SECT, MAILBOX, SM RD ASSM, DEL ASM, OBJ MRK, SINGLE GDRL TERM, REAC | ||
Prime Contractors: | DAYCO CONSTRUCTION CO | ||
Let Date: | 2003-08 | County: | TARRANT |
CCSJ: | 2266-02-096 | District: | FORT WORTH |
Project ID: | NH 2003(61) | Pct Complete: | 97% |
Commitment Amount: | 144,788.63 | ||
Commitment Work: | TERM ANCHOR (12 GAL), MTL BM GD FEN (BLK OUT), DEL ASSM TY A, OBJ MRK ASM TY 2 FLEX, SINGLE G RAIL, TRAC | ||
Prime Contractors: | ZACHRY CONSTRUCTION CORPORATIO | ||
Let Date: | 2003-08 | County: | HENDERSON |
CCSJ: | 1099-05-009 | District: | TYLER |
Project ID: | MG 2003(561) | Pct Complete: | 83% |
Commitment Amount: | 80,828.00 | ||
Commitment Work: | MBGF, DEL ASM, OBJ MRK, SINGLE GUARDRAIL, TRAC | ||
Prime Contractors: | A. L. HELMCAMP, INC | ||
Let Date: | 2003-08 | County: | HILL |
CCSJ: | 0048-09-023 | District: | WACO |
Project ID: | BOR 2001(616) | Pct Complete: | 26% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2003-09 | County: | DALLAS |
CCSJ: | 2374-04-055 | District: | DALLAS |
Project ID: | IM 35E-6(382) | Pct Complete: | 100% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | W.W. WEBBER INC | ||
Let Date: | 2004-03 | County: | LEON |
CCSJ: | 0335-03-039 | District: | BRYAN |
Project ID: | STP 2004(277) | Pct Complete: | 36% |
Commitment Amount: | 43,665.00 | ||
Commitment Work: | MBGF, REMOV TERM ANCHOR SECT, SINGLE GRDRL TER | ||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2004-03 | County: | FALLS |
CCSJ: | 0049-02-009 | District: | WACO |
Project ID: | NH 2004(261) | Pct Complete: | 40% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2004-05 | County: | DENTON |
CCSJ: | 0364-03-066 | District: | DALLAS |
Project ID: | NH 2001(366) | Pct Complete: | 33% |
Commitment Amount: | 238,872.00 | ||
Commitment Work: | TERM ANCHOR SECT, MBGF, REMOV TERM ANCHOR, DEL ASMOBJ MRKASM, REMOV SINGLE GDRAIL, SINGL GUARDRAIL TER | ||
Prime Contractors: | AUSTIN BRIDGE & ROAD, L | ||
Let Date: | 2004-05 | County: | KAUFMAN |
CCSJ: | 0451-02-023 | District: | DALLAS |
Project ID: | STP 2004(28) | Pct Complete: | 78% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | GAREY CONSTRUCTION LTD PEACHTREE CONSTRUCTION, LTD |
||
Let Date: | 2004-06 | County: | MILAM |
CCSJ: | 0185-04-033 | District: | BRYAN |
Project ID: | NH 2004(461) | Pct Complete: | 48% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | JAMES CONSTRUCTION GROUP, L.L.C | ||
Let Date: | 2004-07 | County: | MCLENNAN |
CCSJ: | 2506-01-021 | District: | WACO |
Project ID: | STP 2000(272) | Pct Complete: | 47% |
Commitment Amount: | 22,333.75 | ||
Commitment Work: | MBGF, DEL ASM, OBJ MRK, SINGLE GUARDRAIL TER | ||
Prime Contractors: | BIG CREEK CONSTRUCTION, LTD | ||
Let Date: | 2004-07 | County: | NAVARRO |
CCSJ: | 0092-06-075 | District: | DALLAS |
Project ID: | NH 2004(522) | Pct Complete: | 23% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | W.W. WEBBER INC | ||
Let Date: | 2004-08 | County: | BURLESON |
CCSJ: | 0116-02-027 | District: | BRYAN |
Project ID: | NH 2004(611) | Pct Complete: | 37% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2004-08 | County: | BURLESON |
CCSJ: | 0116-02-027 | District: | BRYAN |
Project ID: | NH 2004(611) | Pct Complete: | 37% |
Commitment Amount: | 37,623.60 | ||
Commitment Work: | REMOVE RAIL, MBGF, REMOVE MBGF, REMOVE SGL GDRAIL,SINGLE GDRAIL TER | ||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2004-08 | County: | ELLIS |
CCSJ: | 0260-02-036 | District: | DALLAS |
Project ID: | C 260-2-36 | Pct Complete: | 100% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | APAC-TEXAS, INC | ||
Let Date: | 2004-09 | County: | GRIMES |
CCSJ: | 0212-04-027 | District: | BRYAN |
Project ID: | STP 2004(678) | Pct Complete: | 27% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2004-09 | County: | COLLIN |
CCSJ: | 3476-02-004 | District: | DALLAS |
Project ID: | BR 2003(534) | Pct Complete: | 41% |
Commitment Amount: | 52,493.00 | ||
Commitment Work: | MBGF, REMOV TERM ANCHOR SECT, DEL ASM , OBJ MARK ASM, SINGLE GUARDRAIL TER | ||
Prime Contractors: | AUSTIN BRIDGE & ROAD, L | ||
Let Date: | 2004-10 | County: | DALLAS |
CCSJ: | 0581-02-112 | District: | DALLAS |
Project ID: | NH 2004(723) | Pct Complete: | 22% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | AUSTIN BRIDGE & ROAD, L | ||
Let Date: | 2004-10 | County: | DENTON |
CCSJ: | 0918-46-101 | District: | DALLAS |
Project ID: | BR 2000(684) | Pct Complete: | 100% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | L & N BRIDGE, LL | ||
Let Date: | 2004-11 | County: | DENTON |
CCSJ: | 0196-01-093 | District: | DALLAS |
Project ID: | IM 35-6(386) | Pct Complete: | 100% |
Commitment Amount: | 29,315.00 | ||
Commitment Work: | TERM ANCHOR SECT, MBGF, OBJ MRK, SINGLE GUARDRAIL,REAC | ||
Prime Contractors: | MCMAHON CONTRACTING, L.P | ||
Let Date: | 2004-12 | County: | LEON |
CCSJ: | 0917-16-021 | District: | BRYAN |
Project ID: | BR 2002(598) | Pct Complete: | 42% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | FUQUA CONSTRUCTION CO., INC | ||
Let Date: | 2004-12 | County: | ELLIS |
CCSJ: | 0596-02-031 | District: | DALLAS |
Project ID: | BR 2005(33) | Pct Complete: | 48% |
Commitment Amount: | 56,504.00 | ||
Commitment Work: | TEMP RAILING,MBGF,DEL ASM TY, OBJ MRK , SINGLE GUARDRAIL TERM, TRAC | ||
Prime Contractors: | W.W. WEBBER INC | ||
Let Date: | 2004-12 | County: | TARRANT |
CCSJ: | 0081-12-035 | District: | FORT WORTH |
Project ID: | IMD 35W-5(129) | Pct Complete: | 43% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | JACKSON CONSTRUCTION, LTD | ||
Let Date: | 2005-01 | County: | DENTON |
CCSJ: | 0918-46-140 | District: | DALLAS |
Project ID: | BR 2002(873) | Pct Complete: | 94% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | L & N BRIDGE, LL | ||
Let Date: | 2005-01 | County: | MILAM |
CCSJ: | 0209-05-041 | District: | BRYAN |
Project ID: | BR 2005(116) | Pct Complete: | 25% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | JAMES CONSTRUCTION GROUP, L.L.C | ||
Let Date: | 2005-02 | County: | WISE |
CCSJ: | 0902-20-066 | District: | FORT WORTH |
Project ID: | BR 2003(470) | Pct Complete: | 57% |
Commitment Amount: | 16,820.00 | ||
Commitment Work: | MTL W/BEAM GRND.FEN,TER. ANCHOR, RMV.MBGF, GUARD RAIL END TRMT, INSTL. DEL ASSM, INSTL. OM ASSM | ||
Prime Contractors: | M. J. LEE CONSTRUCTION COMPAN | ||
Let Date: | 2005-02 | County: | DALLAS |
CCSJ: | 8050-18-042 | District: | DALLAS |
Project ID: | NH 2005(186) | Pct Complete: | 8% |
Commitment Amount: | 141,635.00 | ||
Commitment Work: | MTL W-BEAM GD FENCE,GUARDRAIL END TREATMENT CRASH CUSH ATTEN,INSTL OM ASS | ||
Prime Contractors: | MCCARTHY BUILDING COMPANIES, INC | ||
Let Date: | 2005-02 | County: | MCLENNAN |
CCSJ: | 0049-01-085 | District: | WACO |
Project ID: | NH 2005(179) | Pct Complete: | 53% |
Commitment Amount: | 0.00 | ||
Commitment Work: | |||
Prime Contractors: | BIG CREEK CONSTRUCTION, LTD | ||
Let Date: | 2005-03 | County: | MCLENNAN |
CCSJ: | 0209-07-031 | District: | WACO |
Project ID: | STP 2005(259) | Pct Complete: | 2% |
Commitment Amount: | 33,017.00 | ||
Commitment Work: | RAIL(TY),MTL W-BEAM GD FEN(STEEL POST) RMV METAL BEAM GUARD FN, GD RAIL END TRT,INSTL DE ASSM,INSTL OM ASSM(OM-2SRA)(WC)GN | ||
Prime Contractors: | BIG CREEK CONSTRUCTION, LTD | ||
Let Date: | 2005-04 | County: | ELLIS |
CCSJ: | 0918-22-073 | District: | DALLAS |
Project ID: | BR 2001(507) | Pct Complete: | 55% |
Commitment Amount: | 58,185.00 | ||
Commitment Work: | RAIL, MBGF (TIM POST), GRDRL ED TRT (INST), INST OM ASSM (OM-3L & OM-3R)(FLX)(GRD | ||
Prime Contractors: | COPPELL CONSTRUCTION CO., INC | ||
Let Date: | 2005-05 | County: | ELLIS |
CCSJ: | 1139-02-014 | District: | DALLAS |
Project ID: | BR 2005(394) | Pct Complete: | 7% |
Commitment Amount: | 73,684.00 | ||
Commitment Work: | TEMP RAIL, MTL BEAN GD FENCE.CRASH CUSH ATTEN, INSTALL OM ASSEM, INSTALL DEL ASSE | ||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
Let Date: | 2005-05 | County: | DENTON |
CCSJ: | 0134-09-047 | District: | DALLAS |
Project ID: | BR 2000(72) | Pct Complete: | 0% |
Commitment Amount: | 104,688.20 | ||
Commitment Work: | MTL BM GD FEN, TERM ANCHOR, MTL BM GD FEN TRANS, REMOV MTL BM GD FEN, END TRT, CRASH CUSH, SM R INSTAL DEL ASSM, REMOVE DELIN & OBJ MRKS ASSM | ||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
Let Date: | 2005-06 | County: | TARRANT |
CCSJ: | 0902-48-621 | District: | FORT WORTH |
Project ID: | BR 98(76) | Pct Complete: | 0% |
Commitment Amount: | 50,150.00 | ||
Commitment Work: | REACT 350 (RMV & RST), REACT 350 (RMV), REACT 350 (NARROW 4-S | ||
Prime Contractors: | COPPELL CONSTRUCTION CO., INC | ||
Let Date: | 2005-06 | County: | NAVARRO |
CCSJ: | 0999-01-026 | District: | DALLAS |
Project ID: | STP 2005(507) | Pct Complete: | 0% |
Commitment Amount: | 23,568.00 | ||
Commitment Work: | MTL W-BEAM GD FENCE,TERM ANCHOR SECT.,RMV. GUARD FENCE,MAILBOX INSTALL,RMV. ANCHOR SECT.,INSTAL OMASSM,INSTL DEL ASSM, REMOVE DELIN & OBJ. MRK. A | ||
Prime Contractors: | BIG CREEK CONSTRUCTION, LTD | ||
Let Date: | 2005-06 | County: | KAUFMAN |
CCSJ: | 0751-03-033 | District: | DALLAS |
Project ID: | BR 2005(458) | Pct Complete: | 0% |
Commitment Amount: | 18,687.25 | ||
Commitment Work: | MTL W-BEAM GD FEN,MTLTHRIE-BEAM GD FEN(TIM POST) INSTL DEL ASM (D-SW) SZ 1( FLEX/(D-SW) SZ(TYC CTB(B1) INSTALL OM ASSM | ||
Prime Contractors: | L.A. SEARS CONSTRUCTION, INC | ||
Let Date: | 2005-06 | County: | BELL |
CCSJ: | 0231-03-089 | District: | WACO |
Project ID: | NH 2005(500) | Pct Complete: | 0% |
Commitment Amount: | 369,365.00 | ||
Commitment Work: | RAIL, MBGF (STL PST), TRM ACH SEC, MBGF (THR-BM), RMV MBGF, RMV TRM ACH, GDRL ED TRT (RMV)&(IST) CRSH CUSH ATN, IST DL ASM, IST OM ASM, IST DL ASS | ||
Prime Contractors: | YOUNG CONTRACTORS, INC | ||
Let Date: | 2005-07 | County: | SMITH |
CCSJ: | 0245-07-025 | District: | TYLER |
Project ID: | STP 2005(96) | Pct Complete: | 0% |
Commitment Amount: | 27,256.25 | ||
Commitment Work: | MTL W-BEAM GD FEN (TIM POST), RMV MBGF, RMV TERM ANCH SECT, GRDRL END TRMT INSTL/RMV, INSTL DE AS | ||
Prime Contractors: | AUSTIN BRIDGE & ROAD, L | ||
Let Date: | 2005-07 | County: | SOMERVELL |
CCSJ: | 0259-02-039 | District: | FORT WORTH |
Project ID: | BR 2005(676) | Pct Complete: | 0% |
Commitment Amount: | 60,704.50 | ||
Commitment Work: | MBGF (TIM POST), MBGF TRANSITION, RMV MBGF, GRDRL END TRT, INST DEL ASSM, INST OM ASS | ||
Prime Contractors: | ELLIS-MCGINNIS CONSTRUCTION CO | ||
Let Date: | 2005-07 | County: | BELL |
CCSJ: | 0184-04-025 | District: | WACO |
Project ID: | NH 2005(397) | Pct Complete: | 0% |
Commitment Amount: | 78,167.75 | ||
Commitment Work: | MBGF; GUARDRAIL END TREATMENT; CRASH CUSH ATTEN; INSTALL DEL ASSM; INSTL OM ASS | ||
Prime Contractors: | JAMES CONSTRUCTION GROUP, L.L.C | ||
Let Date: | 2005-07 | County: | VAN ZANDT |
CCSJ: | 0910-12-047 | District: | TYLER |
Project ID: | BR 2005(45) | Pct Complete: | 0% |
Commitment Amount: | 26,920.00 | ||
Commitment Work: | RAIL; MBGF; GDRAIL END TRT; INSTALL DEL ASS | ||
Prime Contractors: | L & N BRIDGE, LL | ||
Let Date: | 2005-07 | County: | DALLAS |
CCSJ: | 2374-03-064 | District: | DALLAS |
Project ID: | IM 20-5(133) | Pct Complete: | 0% |
Commitment Amount: | 421,768.75 | ||
Commitment Work: | METL W-BEAM,TERM ANCHR, MTL BEAM GD FEN,GUARDRAIL END TREATMENT,CRASH CUSH ATTEN | ||
Prime Contractors: | ED BELL CONSTRUCTION COMPAN | ||
|